Which of the following is a strategy for preventing light pollution?

A.

Install up-lighting

B.

Install shielded fixtures

C.

Install high performance windows

D.

Use dark paving materials to diminish light distribution

Which is an example of a low-cost Water Efficiency strategy?

A.

Install new flush valves or flow restrictors

B.

Install subsurface cisterns to collect stormwater

C.

Use only compostable toilets throughout the facility

D.

Incorporate an on-site blackwater treatment system

What plumbing fixture eliminates water use?

A.

Ultrasonic toilet

B.

WaterSense labeled toilet

C.

Low-flow lavatory

D.

Composting toilet

Which type of water should be considered an alternative water source?

A.

Rainwater

B.

Dirty water

C.

Blackwater

D.

Potable water

Which of the following sites is most appropriate to encourage a walkable street design?

A.

A neighborhood that includes a diversity of use

B.

An area with a decreased building-height-to-street-width ratio

C.

A development that uses many culs-de-sac in the street design

D.

A project in an area designed with streets to facilitate increased speed limits

A new community center is in the early design phase and aims to achieve LEED certification. The project team has discussed the importance of integrating sustainability principles across all stages of design and construction. They are considering strategies related to energy performance, sustainable site development, water savings, and indoor environmental quality. Which strategy should the project team prioritize in order to maximize points across multiple LEED credit categories?

A.

Optimize daylighting and ventilation

B.

Source materials locally

C.

Conduct a comprehensive energy model

D.

Delay sustainability decisions until construction documents are complete

Approximately what percentage of the Earth’s water is fresh water?

A.

4%

B.

1%

C.

2%

D.

3%

The project team for a new office building would like to achieve Materials and Resources Credit Construction and Demolition Waste Management Which strategy contributes to achieving this goal?

A.

Providing an on-site location for all waste to be sorted

B.

Purchasing Renewable Energy Certificates (RECs)

C.

Providing an off-site location for all waste and construction debris

D.

Providing a centralized location in the building for recycling office products

LEED certification steps generally proceed in which of the following order?

A.

Project Registration, Application Preparation, Submission, Application Review, Certification

B.

Application Preparation, Application Review, Project Registration, Submission, Certification

C.

Select LEED rating system, Submission, Application Review, Project Registration, Certification

D.

Application Preparation, Project Registration, Application Review, Submission, Certification

What is the primary purpose of using low cubicle partitions in office buildings?

A.

To reduce Volatile Organic Compounds (VOCs) levels

B.

To reduce CO₂ levels

C.

To increase the spread of daylight

D.

To increase thermal comfort