Which of the following options does the triple bottom line entail?

A.

Time, cost and quality

B.

People, planet and profit

C.

Energy, water and materials

D.

Health, safety and environment

A new tenant in an existing office building is pursuing LEED certification. The tenant would like to encourage alternative transportation methods. Which of the following items can be used to satisfy this request and achieve LEED Location and Transportation Credit?

A.

Provide underground parking

B.

Designate preferred parking for motorcycles

C.

Develop on a brownfield site after remediation

D.

Develop an alternative commuting incentive program

Which of the following must a waste reduction, reuse and recycling program collect and measure?

A.

Excavated soil and land-clearing debris

B.

Hazardous materials leaving the building

C.

Recycled content 0t purchased office supplies

D.

Waste diverted through recycling and reuse

Which of the following credit categories is affected by increasing the amount of ventilation in an occupied space?

A.

Water Efficiency

B.

Indoor Ventilation and Energy

C.

Indoor Environmental Quality

D.

Materials and Resources

Which of the following is a strategy that a design team should consider In order to decrease the Impact of a new construction project?

A.

Maximize views of the existing wetland

B.

Select native plants to provide habitat for local fauna

C.

Locate the project in an existing office park with ample parking

D.

Increase the project's footprint to maximize roof space for a solar array

Volatile organic compounds (VOCs) negatively impact which of the following entities?

A.

Quality of daylight

B.

Quality of indoor air

C.

Durability of a product

D.

Ability to recycle a product

Flush out process is performed to remove which of the following?

A.

voc

B.

Waste

C.

Graywater

D.

Blackwater

The LEED reviewer advised a project team that an inappropriate rating system was chosen for a newly constructed school in operation for one year and undergoing minor improvements. What should the project team have done differently to avoid this error?

A.

Allow the LEED Project Administrator sole responsibility to review the appropriate rating system for the project

B.

Select LEED for Schools New Construction and Major Renovations Rating System, as this project is classified as a school

C.

Select LEED for Existing Buildings: Operations and Maintenance Rating System, as the Operational and Maintenance phase has begun

D.

Review the appropriate rating system and determine the best adaptation to use with consultation from U.S. Green Building Council

An office without transit access can substantially reduce its transportation impact if

A.

ample parking spaces are provided

B.

the office is located at a major intersection

C.

workers are able to walk from the office to basic services

D.

green power is purchased to offset projected automobile travel

Relating to water efficiency in LEED. gallons per minute or liters per minute refers to the amount of

A.

stormwater runoff

B.

captured rainwater

C.

water used by flow fixtures

D.

water used by flush fixtures