When following the LEED Building Design and Construction Integrative Process credit, which of the following is the approach for the design team to follow?

A.

Locate a solid waste provider that has sorting capabilities

B.

Assure the aesthetics will match existing neighborhood conditions

C.

Identify synergies among building systems and equipment

D.

Determine if green vehicles will be applicable to the project

Water Efficiency Prerequisite, Outdoor Water Use Reduction, Option 2. Reduced Irrigation, requires that a project ' s landscape water requirement be reduced by what percentage from the calculated baseline for the project site ' s peak watering month?

A.

20%

B.

25%

C.

30%

D.

40%

Which of the following project team members should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning?

A.

Owner

B.

Contractor

C.

Occupants

D.

Facility manager

According to ASHRAE 90.1-2019, small commercial buildings under 25,000 ft² (2,323 m²) require energy monitoring:

A.

At 15-minute intervals for total project electricity use

B.

At least monthly for submetered end-use electricity

C.

At least monthly for whole-building energy use for each energy source

What is a viable strategy for optimizing open space under Sustainable Sites Credit, Open Space? U

A.

Coordinate open space features during the construction phase

B.

Minimize the floor-area ratio (FAR) and accessibility for open space

C.

Design a parking and road footprint layout that is not near open land

D.

Coordinate open space features early during the site planning phase

What is the minimum number of members of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

A.

One

B.

Two

C.

Four

D.

Six

Commissioning (Cx) and verification are requirements to qualify for LEED certification. What are the basic systems that need to be commissioned?

A.

Electrical, Mechanical, Plumbing, and Renewable Energy

B.

Electrical, Structural, Mechanical, and Lighting

C.

Electrical, Structural, Audio Visual, and Envelope

D.

Electrical, Plumbing, Telecommunications, and Fire Suppression

The design team and project owner decided not to pursue Energy and Atmosphere Credit, Enhanced Commissioning, but would hire a Commissioning Authority (CxA) to oversee the requirements for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification. What is a required responsibility for the CxA to achieve the stated objective?

A.

Verify installation and performance of the commissioned systems

B.

Review the building10 months after substantial completion

C.

Verify that training requirements are completed

D.

Develop a systems manual for the commissioned systems

A new facility has a comprehensive advanced energy metering system that measures energy consumption across multiple subsystems. The facilities manager aims to use this data to enhance energy management practices and improve overall building performance.

The facilities manager can utilize the advanced energy metering system to optimize energy use and reduce costs in the new student center by:

A.

Adjusting the setpoints of the HVAC system based solely on outdoor temperature changes

B.

Using automated alerts from the metering system to address sudden spikes in energy use

C.

Scheduling regular audits for all installed lighting systems to ensure compatibility with energy meters

The gross floor area of a LEED project should be no less than what percent of the gross land area within the LEED project boundary?

A.

3%

B.

1%

C.

2%

D.

4%