ACM agent has assisted the owner by creating contractual safety requirements. By reviewing the contractor's safety submittals, the CM

A.

certifies that the submittals cover all site conditions that may occur.

B.

approves the contractors fall protection program.

C.

determines if the contract specifications have been met.

D.

accepts responsibility and liability for site safety.

Which of the following statements BEST describes the recommended approach CMs should take with respect to building information modeling (BIM)?

A.

The CM should assure the owner has considered using BIM.

B.

The CM should not recommend the use of BIM.

C.

The CM should require the owner to use BIM.

D.

The CM should not discuss BIM unless requested by the owner.

A project manager is working on a new transit station project. This client has never used an agency CM before. The project manager wishes to engage the client in defining the scope, budget, schedule, environmental conditions, and basic systems to be utilized. Which of the following would be MOST useful in engaging the client and defining the project requirements?

A.

Quality Management Plan

B.

Project Procedures Manual

C.

Kickoff Partnering Meeting

D.

Project Management Plan

Which of the following is a key element of a safety culture?

A.

Time is of the essence

B.

Maximizing profit

C.

Prompt accident notification

D.

Ownership and management buy-in

When developing schedule specifications, which of the following practices should the CM recommend to the Owner to avoid disputes regarding weatherdelays per year?

A.

Using a recognized reference such as NOAA. define the number of allowable "normal" weather impact days expected to occur on the project within the contract documents.

B.

Ask the contractor to specify the number of weather days they believe necessary for the project.

C.

Defer all issues related to weather to NOAA.

D.

Consult a local meteorologist to determine the best estimate of the number of weather days to allow on the project.

An agency CM is assigned to a new construction project using the CMAA A-2 Standard Form of Agreement between owner and contractor. The project is experiencing concurrent critical path delays caused by the contractor and the architect. What is the BEST guidance the agency CM could give the owner for dealing with these events?

A.

The owner should plan for delayed completion.

B.

Direct both the architect and GC to mitigate each delay and have the agency CM perform a schedule impact analysis to allocate delay responsibility.

C.

The architect and GC should be directed to add resources to mitigate each of their delays at no additional cost to the owner.

D.

The owner should charge the contractor daily liquidated damages.

Float, date, and duration are examples of

A.

schedule elements.

B.

schedule parameters.

C.

constraints.

D.

logic elements.

In what decade was the new occupation of "construction manager" created to fulfill an identified need?

A.

1930s

B.

1950s

C.

1980s

D.

1970s

Contract administration includes, but is not limited to, planning for implementation of drawings, specifications, and

A.

standards.

B.

owner's scope of work.

C.

permits.

D.

licenses.

A written safety program should include all applicable laws, codes, and regulations, and must

A.

be approved by the Owner.

B.

be developed by the CM.

C.

meet the contractual requirements.

D.

be a shared responsibility with the project team.