A CM team on a new project which is in the pre-design phase is planning their climate resiliency strategy. Which of the following is the team's BEST first step in this process?

A.

Collect relevant data and reports.

B.

Establish a third-party certification.

C.

Establish QA/QC specifications.

D.

Hire a commissioning agent.

A CM's responsibility for safety on the jobsite includes

A.

no obligation for safety as it is the contractor's responsibility.

B.

a professional obligation shared with others.

C.

certifying subcontractor compliance.

D.

drafting the contractor's safety plan.

The general contractor on a $1.2 billion terminal at an airport finds out that, due to supply chain issues, there is a 60% risk that they will not be able to get steel onsite for 10 weeks. The late start date of steel installation is four weeks away. Such a delay would cost the owner $75,000 per week to recover. What is the expected monetary value of risk?

A.

$270,000

B.

$450,000

C.

$1.2 million

D.

$2.7 million

A project in schematic design with sustainability goals will soon begin a value engineering study. Which of the following would ensure that the value engineering study will not harm the project's sustainability?

A.

Add a LEED Platinum requirement.

B.

Establish clear sustainability functional requirements.

C.

Hold a partnering workshop first.

D.

Add a LEED Silver requirement.

A dispute arises during construction after the contractor encounters what they feel is unsuitable material. The CM is not notified about the areas of concern, and the contractor hauls 10.000 cy of material offsite. Three months later, the contractor submits a claim for additional cost to haul the material off. The CM should advise the owner that

A.

the owner should pay for the haul.

B.

the claim is not valid because the contractor failed to provide timely notice.

C.

the owner should pay the claim due to lack of owner information.

D.

the owner should pay 50% of the haul since the contractor did not notify the CM first.

During the design phase, the CM should perform which of the following tasks?

A.

Review contract milestones, payment procedures, and communication procedures.

B.

Review cost estimate, schematic design, and scheduling conferences with regulatory agencies.

C.

Review staffing assignments, labor affidavits, and historical trust.

D.

Review plans, final Right-of-Way (ROW) documents, and as-built submittals.

A construction manager is responsible for the bid review and evaluation of an $85 million high school project. All bids must be submitted in person at the clients Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?

A.

Put the contractor's unopened bid in tight security until the bid opening has been completed.

B.

Send the bid back to the contractor and apologize for the mishap.

C.

Include the unopened bid. since it clearly was an oversight.

D.

Inform the Owner and review the instructions to bidders for guidance on how to proceed.

Which of the following addresses the administrative and reporting requirements for a Construction Manager during execution of a project?

A.

Project Administration Guidelines

B.

Standards of Practice

C.

Construction Administration Guidelines

D.

Contract Administration Guidelines

A CM is milling and paving a 2-mile-long bridge with a surface that is in total failure. The owner gave the contractor October 24 as the fixed completion date. Meanwhile, the owner has promised the public that work hours would be 7am–7pm, 5 days per week and that the bridge would be completed by September 1.

The bridge deck is poured on a steel grid deck, but this type of operation has never been performed in the state and complications from weather have slowed progress. The contractor has requested to work nonstop 24/7 to meet the deadline told to the public.

The CM should

A.

tell the contractor they have until September 1 and can only work 7am–7pm.

B.

discuss with the owner and tell the contractor to do only 1/2 of the bridge.

C.

meet with the owner and contractor to vet all issues/options and make a decision.

D.

meet with the contractor to go over realistic time frames and make a decision.