The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses. Which of the following checkpoints would be appropriate? 2 credits

A.

The bidder’s test policy should enforce that incident management fully conforms to IEEE 1044.

B.

The bidder’s project strategy shows that the data content of all the test environments conforms to EU standards.

C.

The bidder’s test plan shows that the application will be delivered for acceptance in six months time.

D.

The bidder’s project test plan depicts a phased implementation with later delivery dates to be confirmed and states that test deliverables will be developed using IEEE 829 as a guide.

Which of the following product risks would be most effectively addressed just by static testing? 3 credits

A.

In the delivered application, one of the countries, as specified in the requirements, has not been correctly implemented.

B.

The application takes too long to process a request for additional cover.

C.

The test cases do not cover the key requirements.

D.

The successful bidder may not deliver all the required functionality on time.

A test assessment has been carried out using the selected model as a reference framework. A number of recommendations have been identified and you are asked to prioritize them. Based on your knowledge of the project, you are expecting severe resistance to change. Which of the following would be the most important selection criterion for defining the priority of the recommendations? 2 credits

A.

Synchronized with the overall long-term organizational strategy

B.

Defined according to the maturity model used

C.

Most visible to stakeholders

D.

Low costs actions first

Comparing TMMi and TPI, which is not a valid reason for choosing either TPI or TMMi? 2 credits

A.

If the scope of test performance improvement covers all test levels, TMMi is preferred since TPI focusses mainly on black-box testing.

B.

If the organization is already applying CMMI, TMMi may be preferred since it has the same structure and uses the same terminology. TMMi addresses management commitment very strongly and is therefore more suitable to support a top-down improvement process.

C.

TPI is much more a bottom-up model that is suitable for addressing test topics for a specific (test) project.

D.

TMMi can only be used with the traditional V model,whereas TPI can be used with all types of software life cycles.

Model characteristics:

Which THREE of the below mentioned characteristics relate to TMMi? 1 credit

A.

5 maturity levels

B.

Focussed on higher level testing

C.

20 key areas

D.

Highly related to CMMI

E.

Continuous model

F.

Staged model

G.

Focussed on component and integration testing

Which of the following team roles would be most appropriate to enhance the team and why? 2 credits

A.

A person with the ability to complete tasks

B.

A quality assurance officer

C.

A person with in-depth technical skills

D.

A person who brings new ideas to the team

In addition to introducing the new team member, you have decided to raise motivation. Which of the measures listed below would be the best measure to take in order to increase the motivation of the team? 2 credits

A.

Provide more time for testing in the schedule

B.

Allow people to take some time off

C.

Introduce entry criteria to the testing phase

D.

Organize a meeting with senior management in which they address the importance of good testing for this project

You are considering involving users during test execution. In general, what is the main reason for involving users during test execution? 1 credit

A.

They are a cheap resource

B.

They have good testing skills

C.

This can serve as a way to build their confidence in the system

D.

They have the ability to also focus on invalid test cases

Considerable attention will be given in this project to defining exit criteria and on reporting back on their status. Which combination of TWO exit criteria from the list would be best to use? 1 credit

I. Total number of defects found

II. Percentage of test cases executed

III. Total test effort planned versus total actual test effort spent

IV. Defect trend (number of defects found per test run over time

A.

(i) and (ii)

B.

(i) and (iv)

C.

(ii) and (iii)

D.

(ii) and (iv)

You have been given responsibility for the non-functional testing of a safety-critical monitoring & diagnostics package in the medical area. Which of the following would you least expect to see addressed in the test plan? 1 credit

A.

Availability

B.

Safety

C.

Portability

D.

Reliability