Which of the following can be considered a previously undeveloped slle?

A.

An area of 10 acres (4 hectares), with a previously developed building footprint totaling 8 acres (3 hectares)

B.

An area of 8 acres (0.61 hectare), with a previously developed building footprint totaling 4 acres (2 hectares)

C.

An area of 0.8 acre (0.32 hectare), with a previously developed building footprint totaling 0.2 acre (0 .08 hectare)

D.

An area of 0.5 acre (0.20 hectare) that is an improved park with manicured landscaping and paved playground areas

A LEEDV for Neighborhood Development registered project donates salvaged lumber to a localcommunity organization for their use in buildinglow income housing. What creditcanthis action contribute towards?

A.

GIB Prerequisite Construction Activity Pollution Prevention

B.

GIB Credit Building Reuse

C.

GIB Credit Recycled and Reused Infrashtructure

D.

GIB Credit Solid Waste Management

What agency is responsible for identifying prime and unique sods in agriculture and older associated industries?

A.

American Farmland Trust or local equivalent

B.

Stale Natural Heritage Program or local equivalent

C.

Natural Resources Conservation Service or local equivalent

D.

Department of Environmental Conservation or local equivalent

Which of the following la an eligible source of renewable energy tot Green Infrastructure and Buildings Credit. Renewable Energy Production?

A.

Wind energy

B.

Ground-source Heat pump

C.

Combust on of municipal solid waste

D.

Forest biomass waste other than mill residue

Whichof the following sites meets the Minimum Program Requirements (MPR) fora project targeting LEED for Neighborhood Development certification?

A.

A site with an area of 1.600 acres (647.50 hectares) that contains two habitable buildings

B.

A site with an area of 1.200 acres (465.62 hectares) that contains five habitable buildings

C.

A silo with an area of 1 .200 acres (485 62 hectares) that contains one Habitable building

D.

A site with an area of 1.600 acres (647.50 hectares) that doesn’t contain any habitable buildings

A developer is lookingfor a site to construct a LEED for Neighborhood Development project.Which contextual attribute would most contribute to gaining this certification?

A.

A site with waterfront as part of its boundary

B.

Previously disturbed land surrounding the site

C.

A nearby office park

D.

A load utility that supplies renewable energy to the site

What information is required to determine if a project quality for the Green Infrastructure and Buildings Credit. Wastewater Management?

A.

Rainwater reuse rate

B.

Cost of installing wastewater system

C.

Average amount of annual wastewater generated

D.

Ability to connect to existing wastewater infrastructure

A project team has achieved the require men is for Neighborhood Pattern and Design Credit. Community Outreach and Involvement. Option 1: Community Outreach. Which of the following additional actions would earn the project a total or two points?

A.

Conduct an Interactive workshop open to the public for at least two days

B.

Modify Die projects conceptual design as a direct result of community input

C.

Establish ongoing moans for communication between the developer and the community

D.

Obtain full entitlement and endorsements from the local land use and Building permitting jurisdictions

A developer has built a snow storage system that uses snow collected in the winter to cool water that serves the neighborhood central plant during the summer.Which credit will this system contribute to?

A.

Green Infrastructure and Buildings. Optimize Building Energy Performance

B.

Green Infrastructure and Buildings. Outdoor Water Use Reduction

C.

Green Infrastructure and Buildings Heal Island Reduction

D.

Green Infrastructure and Buildings. Renewable Energy Production

A developer is considering purchasing a 400-acc (161 hectare) site which la currently zoned (or two dwelling units(DU) per sere (five DU/hectare).Which initial action during the entitlement process would help make the site eligible for LEED for NeighborhoodDevelopment certification?

A.

Create an overlay district

B.

Rezone the project for a higher density

C.

Build commercial uses around the development border

D.

Contact the Location and Planning Technical Advisory Group for initial review