Which of the following Water Efficiency credits differ between LEED Building Design and Construction: New Construction and LEED Building Design and Construction: Healthcare?
When following the LEED Building Design and Construction Integrative Process credit, which of the following is the approach for the design team to follow?
In the Indoor Environmental Quality Credit, Low-Emitting Materials, what types of products need to be evaluated for
both Volatile Organic Compound (VOC) content of the material and VOC emissions of the material?
In order to achieve the requirements of LEED, the Electrical Vehicle Supply Equipment (EVSE) must comply with:
The design team and project owner decided not to pursue Energy and Atmosphere Credit, Enhanced Commissioning, but would hire a Commissioning Authority (CxA) to oversee the requirements for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification. What is a required responsibility for the CxA to achieve the stated objective?
A project in a cold climate does not want a highly reflective roof because they want the heat absorption. How can this
project comply with Sustainable Sites Credit, Heat Island Reduction?
The current facilities requirements (CFR) and operations and maintenance plan (OMP) required for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification must include
Building Product Disclosure and Optimization is based on market
An office building design has demonstrated reductions in landscape water use of 30% over baseline and indoor water use of 40%. These reductions qualify the project for:
Which of the following criteria does a project need to implement in order to qualify for Sustainable Sites Credit: Site Development - Protect or Restore Habitat, Option 1?