Under Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification, a current facilities requirements and operations and maintenance plan must contain which information necessary to operate the building efficiently?

A.

Any changes in schedules or setpoints for different seasons, days of the week, and times of day

B.

Only changes in schedules or setpoints for peak usages during seasons, days of the week, and times of day

C.

Any changes in schedules during peak times, or for different seasons, peak-usage days of the week, and times of day

D.

Any changes in schedules or setpoints focusing on only the hottest and coldest periods of the seasons, peak-use days of the week, and times of day

A newly constructed school has installed solar thermal systems and wind turbines on site. To achieve the maximum number of Energy and Atmosphere points, which team members must be included?

A.

Energy Modeler and Contractor

B.

Construction Manager and Energy Modeler

C.

Energy Modeler and Commissioning (Cx) Agent

D.

Commissioning (Cx) Agent and Facilities Manager