There are differences in how quality is managed in Traditional Project Management and Scrum approaches to project delivery. Which of the following statements is FALSE in this regard?

A.

In traditional project management, once the user clarifies their quality expectations, it is the Project Manager who defines those user expectations in measurable terms.

B.

In traditional project management, changes can be made only through a formal change management system.

C.

In Scrum, the Scrum Master and the Scrum Team collaborate and decide on the Acceptance Criteria for the User Stories.

D.

In Scrum, development of the product is carried out by the Scrum Team in short iterations called Sprints.

Which of the following is the Scrum Master's responsibility with respect to the quality aspect of a Scrum project?

A.

Reviewing and accepting/rejecting the developed deliverable

B.

Defining the range of tools that the Scrum Team can use

C.

Ensuring that Scrum processes are followed by everyone

D.

Working on the deliverables and making appropriate changes to them

Following are some examples of risks and issues that might be encountered during the course of a Scrum project. Identify which of the following are risks, not issues.

I. After extensive training, marketing representatives might still not be ready to take orders after the project is launched.

II. The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.

III. Funding was not approved.

IV. Requirements, as currently defined, are unclear.

A.

II only

B.

I and III

C.

II and IV

D.

I and II

One of the responsibilities of the Scrum Master is to ensure that the Product Owner does not change the Acceptance Criteria of a committed User Story in the middle of a Sprint. In this regard, which of the following statements about Acceptance Criteria is correct?

A.

User Story Workshops are held as part of Sprint Review.

B.

Acceptance Criteria provide the objectivity required for the User Story to be considered Done or not Done.

C.

The Scrum Master defines and communicates the Acceptance Criteria to the Scrum Team.

D.

During the Sprint Retrospect Meeting, the Acceptance Criteria provide context for the Product Owner to decide if a User Story has been completed satisfactorily.

You are a Scrum Master on a project creating an optical fiber cable network across the country. The project has reached the Create User Stories process. Which of the following is NOT an input to this process?

A.

The Prioritized Product Backlog

B.

Identified Risks

C.

Personas

D.

Done Criteria

When a Scrum Team completes developing the functionalities or features they had committed to for the current Sprint, what would be the next step?

I. The Scrum Team would demonstrate the developed functionality to the end-user.

II. The Scrum Master would deliver the developed functionality to the production environment.

III. The Scrum Team would evaluate the functionality against the Acceptance Criteria.

IV. The Scrum Master might reject the developed functionality based on feedback from the stakeholders.

A.

I and III

B.

II and IV

C.

All of the above

D.

None of the above

In Scrum, the Scrumboard is ______ at the end of each Sprint.

A.

Updated with new tasks and completed tasks

B.

Placed beside the new one to compare team velocities in Sprints

C.

Analyzed by the Scrum Master to understand project progress in that particular Sprint

D.

Reset or wiped off

A software company has a portfolio including various types of projects. The projects vary in size, complexity, cost, and other factors. The organization currently follows the Waterfall model of project management and is considering making a transition to Scrum, but is not sure if Scrum can be adopted for all of its projects. As a Scrum Master, which of the following projects would be the BEST candidates for Scrum?

I. Software which has already been developed and new updates are to be released within a fixed time and budget.

II. New innovative software in which there is no guaranteed outcome.

III. A project where skills of developers are unique and are required on multiple projects.

IV. A project where the development team is spread across multiple geographies.

A.

I and III

B.

I, II, and III

C.

II and III

D.

I, II, III, and IV

Which of the following is a responsibility of the Scrum Master in the context of change in Scrum?

A.

Eliminating all changes that may affect the quality of deliverables and processes.

B.

Facilitating identification of Change Requests by the Scrum Team and their assessment and prioritization by the Product Owner.

C.

Providing requests for changes in a project.

D.

Approving changes that are amended, removed, or added according to project requirements and communicating the same to the Scrum Team.

As a Program Scrum Master, which of the following responsibilities should you fulfill?

A.

Assess the viability of a Program by creating a Business Case for all the projects that are part of the Program

B.

Envision the objectives, outcomes, and releases of a Program

C.

Facilitate and teach Scrum practices to everyone involved in the Program

D.

Directly influence all the projects in the Program throughout the development process