Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

A.

The Sprint Backlog.

B.

The Sprint Goal

C.

The release plan.

D.

Sprint Review minutes.

What it the main reason for the Scrum Master to be at the Daily Scrum?

A.

To gather status and progress information to report to management.

B.

To write down any changes to the Sprint Backlog, including adding new items, and tracking progress on the burn-down.

C.

He or she does not have to be there; he or she only has to ensure the Development Team has a Daily Scrum.

D.

To make sure every team member answers the three questions.

When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

A.

Yes, but only for Scrum Teams whose work has dependencies.

B.

Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.

C.

No, each Scrum Team stands alone.

D.

No, that is far too hard and must be done in a hardening Sprint.

Which three of the following are true about Scrum? (Choose the best three answers.)

A.

Scrum implements self-management by replacing Project Managers with Scrum Masters.

B.

Each component of Scrum serves a specific purpose and is essential to Scrum’s success and your usage

of Scrum to develop complex products.

C.

Scrum is a methodology where you can pick and choose which parts of Scrum you think will work for your

environment.

D.

Scrum is a framework for developing and sustaining complex products.

E.

Scrum is based on empiricism and lean thinking.

When a Development Team determines that it will not be able to finish the complete forecast, who has to be

present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

A.

The Development Team.

B.

The Product Owner and all stakeholders.

C.

The Product Owner and the Development Team.

D.

The Scrum Master, project manager and Development Team.

To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, a Development Team to implement those ideas and a Scrum Master to help guide the process.

A.

True

B.

False