Which of the following are topics for the Developers to discuss at the Daily scrum as they inspect their progress toward the Sprint Goal?

(choose the best three answers)

A.

what have we learned since yesterday, and now should we modify our plan to increase our ability to meet the Sprint Goal?

B.

Are mere any impediments Clocking progress toward the sprint Goal?

C.

What will I be working on tomorrow?

D.

Are mere any decisions that need to be made to maintain progress toward the sprint Goal?

E.

Why were you late?

F.

How many hours Old I spend on the project yesterday

G.

win todays work negatively impact our ability to meet the sprint Goal for the Split following this one?

A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)

A.

Ensuring that the most valuable functionality is produced first, at all times.

B.

Interacting with stakeholders.

C.

Providing the Development Team with detailed specifications.

D.

Describing features as Use Cases.

E.

Creating detailed functional test cases.

Which Scrum Values are exhibited by not building Product Backlog items that have low business value? (Choose three.)

A.

Economic Value Added.

B.

Respect.

C.

Focus.

D.

Earned Value.

E.

Courage.

How is management external to the Scrum Team involved in the Daily Scrum? (Choose the best answer.)

A.

The Scrum Master speaks on their behalf.

B.

Managers are not required at the Daily Scrum.

C.

Management gives an update at the start of each Daily Scrum.

D.

The Product Owner represents their opinions.

A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give? (Choose the best answer.)

A.

Product Backlog items must be estimated in story points.

B.

Estimates are made by the people doing the work.

C.

Estimates must be in relative units.

D.

Scrum forbids estimating.

E.

Estimates are made by the Product Owner, but are best checked with the Development Team.

Which topics should be discussed in the Sprint Review?

A.

The Scrum process, and how it was used during the Sprint.

B.

Coding and engineering practices.

C.

Sprint results.

D.

All of the above.

What is the purpose of a Sprint Review?

A.

To take time to judge the validity of the project.

B.

To inspect the product increment with the stakeholders and collect feedback on next steps.

C.

To review the Scrum Team’s activities and processes during the Sprint.

D.

To build team sprint.

In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn’t figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able to agree on a Sprint Goal, however.

Which of the following two actions should the Scrum Master support? (Choose two.)

A.

Cancel the Sprint. Send the entire team to an advanced Scrum training and then start a new Sprint.

B.

Forecast the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial design and plan. Once the time-box for the Sprint Planning meeting is over, start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint.

C.

Continue the Sprint Planning meeting past its time-box until an adequate number of Product Backlog items are well enough understood for the Development Team to make a complete forecast. Then start the Sprint.

D.

Discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.

E.

Ask everyone to take as much time as needed to analyze the Product Backlog first, and then reconvene another Sprint Planning meeting.