As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do?

A.

Inform the Product Owner at the Sprint Review, but prior to the demonstration.

B.

Find another Scrum Team to give the excess work to.

C.

As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.

D.

Reduce the definition of “Done” and get all of the Product Backlog items “Done” by the new definition.

The purpose of a Sprint is to produce a done Increment of product.

A.

True

B.

False

What is the key concern when multiple Development Teams are working from the same Product Backlog?

A.

Minimizing dependencies between teams.

B.

Clear definition of requirements.

C.

Meeting original scope projections.

D.

Making sure there’s enough work for everyone on every team.

E.

Maximizing velocity.

When multiple teams work together on the same product, each team should maintain a separate Product Backlog.

A.

True

B.

False

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update management on what is being worked on.

D.

Answer QUESTION NO:s from the Development Team about items in the current Sprint.

Which of these may a Scrum Team deliver at the end of a Sprint?

(choose the best answer)

A.

A single document, if that is what management asked for.

B.

A valuable, useful Increment that meets the Definition of Done.

C.

Failing unit tests, to identify acceptance tests for the next Sprint.

D.

An Increment of software with minor known bugs in it.

How much work Is required of the Developers to complete a Product Backlog Item selected during the Sprint Planning?

(choose the best answer)

A.

All development work and at least some testing.

B.

as much as is required to meet the Scrum Team ' s Definition of Done.

C.

A proportional amount of time on analysis, design development and testing

D.

As much as they can fit into the Sprint, with remaining work deferred to the next Sprint

Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)

A.

The Project Manager

B.

The Product Owner

C.

The Scrum Master

D.

The Scrum Team

E.

All of the above

When might a Sprint be abnormally cancelled?

A.

When the Development Team feels that the work is too hard.

B.

When the Sprint Goal becomes obsolete.

C.

When the sales department has an important new opportunity.

D.

When it becomes clear that not everything will be finished by the end of the Sprint.

The CEO asks the Developers to add a " very important " item to a Sprint that is in progress.

What should the Developers do?

(choose the best answer)

A.

Add the item to the top of the Product Backlog.

B.

Add the item to the current Sprint Backlog and begin work immediately since the

request came from the CEO.

C.

Add the item to the Sprint Backlog for the next Sprint.

D.

Discuss the item with the other members of the Scrum Team so the team can

decide what to do.

E.

Add the item to the current Sprint and drop an item of equal size.