True or False: The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal.

A.

True

B.

False

Which of the following is an accountability of a Tester on a Scrum Team?

(choose the best answer)

A.

Executing tests, finding defects, and reporting them to the Developers.

B.

Refreshing and communicating the Definition of Done to the Product Owner.

C.

Scrum has no Tester accountability. The Developers are accountable for quality.

D.

Verifying the work of the Developers.

E.

Tracking defect rates to ensure they improve each Sprint.

In order to achieve the benefits of Scrum, it is important to enact the value of commitment. What two actions demonstrate the commitment of Scrum Team members? (Choose two.)

A.

Always deliver the items in the Sprint forecast.

B.

Help the other Scrum Team members.

C.

Do your best

D.

Send out a daily status report.

E.

Work late.

Which of these may a Scrum Team deliver at the end of a Sprint?

(choose the best answer)

A.

A single document, if that is what management asked for.

B.

A valuable, useful Increment that meets the Definition of Done.

C.

Failing unit tests, to identify acceptance tests for the next Sprint.

D.

An Increment of software with minor known bugs in it.

What is the time-box for the Sprint Review?

A.

As long as needed.

B.

2 hours for a monthly Sprint.

C.

4 hours for a monthly Sprint.

D.

4 hours and longer as needed.

E.

1 day

How should a Development Team deal with non-functional requirements?

A.

Ensure every Increment meets them.

B.

Make sure the release department understands these requirements, but it is not the Development Team’s responsibility.

C.

Handle them during the Integration Sprint preceding the Release Sprint.

D.

Assign them to the lead developers on the team.

What happens if the Development Team cannot complete its work by the end of the Sprint?

A.

The Sprint is extended and future Sprints use this new duration.

B.

The Sprint length holds and the Development Team continuously learns what is actually possible to do within a Sprint of this length.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.

Which answer best describes the topics covered in Sprint Planning? (Choose the best answer.)

A.

What to do and who will do it.

B.

How conditions have changed and how the Product Backlog should evolve.

C.

What can be done and how to do it, and why to do it.

D.

What went wrong in the last Sprint and what to do differently this Sprint.

E.

Who is on the team and what team member roles will be.

Which of the following best describes an increment of working software?

A.

A decomposition of all Product Backlog items into tasks for future Sprint Backlog lists.

B.

Additional features in a usable state that complement those delivered in previous iterations.

C.

A new user interface design for functionality delivered in previous iterations.

D.

An automated test suite to verify functionality delivered in previous iterations.

E.

UML diagrams that describe how to deliver functionality in future iterations.

What enhances the transparency of an increment?

A.

Doing all work needed to meet the definition of “Done”

B.

Reporting Sprint progress to the stakeholders daily

C.

Keeping track of and estimating all undone work to be completed in a separate Sprint.

D.

Updating Sprint tasks properly in the electronic tracking tool.