Which outcome is expected as Scrum Teams mature?

A.

They will improve their definition of “Done” to include more stringent criteria.

B.

The Sprint Retrospectives will grow to be longer than 4 hours.

C.

There is no need for a time-boxed Sprint, since time-boxes are only for new Scrum Teams.

D.

Sprint Reviews will no longer be needed.

E.

A Scrum Master is no longer needed since they are a mature team now.

For which of the following is the Scrum Master responsible?

(choose the best answer)

A.

Properly adopting and using the Scrum framework.

B.

Keeping track of resource allocation.

C.

Managing the performance of the Scrum Team.

D.

The meetings and the objectives that a Scrum Team sets for itself.

When does a Developer become accountable for an item in the sprint Backlog?

(choose the best answer)

A.

During the Daily Scrum

B.

Never am Developers on the Scrum Team share accountability tor items in the

C.

As soon as a Developer on the Scrum Team can accommodate more work

D.

At Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers

A Scrum Master is introducing Scrum to a new Team. The Team has decided that a Sprint

Retrospective is unnecessary. What action should the Scrum Master take?

(choose the best answer)

A.

Comply with the decision of the self-managing team.

B.

Begin facilitating productive and useful Sprint Retrospectives.

C.

Call a meeting between the ScrumTeam and senior management

D.

Consult with the Product Owner to see how they feel about the situation.

A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items “Done” by the end of the Sprint. Which three phrases best describe the purpose of a definition of “Done”? (Choose three.)

A.

It controls whether the developers have performed their tasks.

B.

It provides a template for elements that need to be included in the technical documentation.

C.

It creates transparency over the work inspected at the Sprint Review.

D.

It trucks the percent completeness of a Product Backlog item.

E.

It guides the Development Team is creating a forecast at the Sprint Planning.

F.

It defines what it takes for an Increment to be ready for release.

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

A.

The Scrum Team with the highest velocity pulls Product Backlog items first.

B.

The Development Teams pull in work in agreement with the Product Owner.

C.

The Product Owner should provide each team with its own Product Backlog.

D.

Each Scrum Team takes an equal numbers of items.

E.

The Product Owner decides.

When many Development Teams are working on a single product, what best describes the definition of “Done”? (Choose the best answer.)

A.

Each Development Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.

B.

It depends.

C.

Each Development Team uses its own but must make their definition clear to all other teams so the differences are known.

D.

All Development Teams must have a definition of “Done” that makes their combined work potentially releasable.

Which Scrum Values are exhibited by not building Product Backlog items that have low business value? (Choose three.)

A.

Economic Value Added.

B.

Respect.

C.

Focus.

D.

Earned Value.

E.

Courage.

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What factors likely led to this? (Choose two.)

A.

The Project Management Office (PMO) has not been engaged adequately.

B.

The Product Owner has not been keeping the stakeholders aware of the progress of the project.

C.

The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.

D.

The stakeholders were not allowed to enter the development area.

What is the recommended size for a Development Team?

A.

7 plus or minus 3.

B.

At least 7.

C.

9.

D.

3 to 9.