When does the next Sprint begin?

A.

When the Product Owner is ready.

B.

Immediately after the conclusion of the previous Sprint.

C.

The Monday following the Sprint Review.

D.

Immediately following the next Sprint Planning.

When must the Product Owner participate in the Dairy Scrum? (choose the best answer)

A.

When the Product Owner is actively working on items on the Sprint Backlog; however, they participate as a Developer

B.

When the Product Owner needs to represent the stakeholders point of view to the Developers

C.

When there are impediments to discuss

D.

When the Scrum Master asks the Product Owner to attend

When is a Sprint over?

A.

When the Product Owner says it is done.

B.

When all Product Backlog items meet their definition of “Done”.

C.

When all the tasks are completed.

D.

When the time-box expires.

How much time is required after a Sprint to prepare for the next Sprint?

A.

The break between Sprints is time-boxed to 1 week for 30 day Sprints, and usually less for shorter sprints.

B.

Enough time for the requirements for the next Sprint to be determined and documented.

C.

Enough time for the Development team to finish the testing from the last Sprint.

D.

None. A new Sprint starts immediately following the end of the previous Sprint.

E.

All of the above are allowed depending on the situation.

Why is the Daily Scrum held at the same time and same place?

A.

The consistency reduces complexity.

B.

The place can be named.

C.

The Product Owner demands it.

D.

Rooms are hard to book and this lets it be booked in advance.

When a Development Team determines that it will not be able to finish the complete forecast, who has to be

present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

A.

The Development Team.

B.

The Product Owner and all stakeholders.

C.

The Product Owner and the Development Team.

D.

The Scrum Master, project manager and Development Team.

When is it most appropriate for a Scrum Team to change the definition of “Done”?

A.

During Spring Planning.

B.

Prior to starting a new Sprint.

C.

During the Sprint Retrospective.

D.

Prior to starting a new project.

What is the time-box for the Sprint Planning meeting?

A.

4 Hours for a monthly Sprint.

B.

8 Hours for a monthly Sprint.

C.

Monthly.

D.

Whenever it is done.

Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?

A.

It is a complete list of all work to be done in a Sprint.

B.

Every item has a designated owner.

C.

Each task is estimated in hours.

D.

It is the Development Team's plan for the Sprint.

E.

It is ordered by the Product Owner.

The CEO asks the Developers to add a "very important" item to a Sprint that is in progress.

What should the Developers do?

(choose the best answer)

A.

Add the item to the Sprint Backlog for the next Sprint.

B.

Add the item to the top of the Product Backlog.

C.

Add the item to the current Sprint Backlog and begin work immediately since the

request came from the CEO.

D.

Add the item to the current Sprint and drop an item of equal size.

E.

Discuss the item with the other members of the Scrum Team so the team can

decide what to do.