For a production version to be valid and consistent, what requirements must be fulfilled? Note:There are 3 correct answers to this question.

A.

The deletion flag must NOT be set for the bill of material (BOM) or the routing

B.

The lot size range must be within the lot size range of the assigned routing.

C.

The assigned routing and bill of material (BOM) must be valid in the entirevalidity period.

D.

The assigned routing must be a rate routing.

E.

The assigned routing must NOT have alternative sequences

Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA?

Note: There are 2 correct answers to this question.

A.

Order (pool) chart

B.

Capacity requirements chart

C.

Work center capacities chart

D.

Orders (dispatched) chart

Generic Parent » Generic 1 pt

What is the purpose of collective orders?

A.

To manage production orders for an entire finished product on multiple levels

B.

To combine order management of co-products and by-products with the main product

C.

To post production costs on a cost collector instead of the production order

D.

To post any component withdrawal as single backflush with order confirmation

You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

A.

Kanban

B.

Material requirements planning

C.

Backflushing

D.

Production order release