Cost and Budget

What function are available for period end-closing in the project System?

A.

Result analysis

B.

Progress analysis

C.

Milestone trend analysis

D.

Settl ement

E.

Confirmation

You want to create a reservation for a material component assigned to a network activity.

However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing

reservation?

Note: There are 2 correct answers to this question

A.

The availability check for material components indicates missing parts

B.

The material master is set to external procurement

C.

The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never"

D.

The material is assigned to the activity as a non-stock material

What are the prerequisites for resource-related billing? Note: There are 2 correct answers to this question

A.

A dynamic item processor (DIP) profile with the appropriate settings

B.

Released WBS elements, activities, and/or activity elements

C.

A header-account-assigned network that is assigned to a sales order item

D.

An activity-account-assigned network that is assigned to a sales order item