Externally processed activities give rise to planned costs that are equivalent to the prices of the following?

There are 2 correct answers to this question.

Response:

A.

Purchasing Info records

B.

Price in the activity

C.

Services costs

D.

Actual costs

In which type of project stock costs from external procurement are posted directly to the stock-keeping WBS element when the goods or invoice are received?

Please choose the correct answer.

Response:

A.

No project stock

B.

Valuated project stock

C.

Non-valuated project stock

D.

Sales order project stock

What does ā€˜E’ determine in account assignment while using consumption posting indicator to determine the controlling object for the sales item?

Please choose the correct answer.

Response:

A.

E determines that the sales order is a controlling object

B.

E determines that the sales order is a project is a controlling object

C.

E determines that the sales order items are relevant for delivery through sales and distribution

D.

E determines that the sales order is a cost object

Which indicator is set for assemblies that need to be ordered well in advance of consumption and are allocated as stock items?

Please choose the correct answer.

Response:

A.

Preliminary purchase requisition

B.

Planned independent requirement

C.

Planned purchase requisition

D.

Third party purchase requisition

If the material is not assigned to any sales order or project and are available for use by general plant requirements. We consider this under which type of stock?

There are 2 correct answers to this question.

Response:

A.

Plant stock

B.

Project stock

C.

General stock

D.

Sales order stock

Which SAP standard item category always leads to direct procurement and a purchase requisition generated by the network?

Please choose the correct answer.

Response:

A.

Non-stock item

B.

Stock item

C.

Billing item

D.

Non-billing item

Which of the following allows you to view project objects with key performance data for quick analysis and update the percentage complete for earned value calculations?

Please choose the correct answer.

Response:

A.

Project reporting

B.

Progress analysis work bench

C.

Project analysis Team View

D.

Project progress analysis

Which account assignment category is important for non-valuated project stock with WBS and sales order item?

Please choose the correct answer.

Response:

A.

E = quantities and values managed in the sales order item

B.

D = quantities managed using sales order item and values managed in projects

C.

G = plant stock, values managed using projects

D.

Q = quantities and values managed in projects

When you create service activity in your network, what data can be entered? (3)

A.

Vendor

B.

Service Specifications

C.

Service purchase order number

D.

Overall Limit (maximum value of all unplanned services)