A costumer uses cross-company-code projects with a top billing element and an additional billing element underneath for each company code. Although the internal billing between the lower-level WBS elements has been performed

correctly, the results analysis summarizes all values to the highest billing elements.

How can we split the results to the different company codes? *

A.

Split the project into different projects according to each company code

B.

Settle the WBS elements to the highest billing element before you do the results analysis

C.

Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly

D.

Change the project structure so that it corresponds better to the company's organizational structure

In which of the following levels can you execute BOM transfer in the order browser?

There are 3 correct answers to this question.

Response:

A.

For multiple assemblies

B.

For the whole multi-level BOM for a sales order item

C.

For a sub-tree

D.

For an individual assembly

In which of the following ways Open PS allows you to exchange data directly with MS project?

There are 3 correct answers to this question.

Response:

A.

Create a project in MS project from an SAP PS project

B.

Transfer a project from MS project to SAP PS

C.

Download MS project and Upload to SAP PS

D.

Reconcile data from a project in Microsoft Project with a project in SAP PS

In which transactions can you specify whether networks are scheduled together with maintenance orders that have been assigned as sub networks?

There are 2 correct answers to this question.

Response:

A.

Project scheduling

B.

Overall network scheduling

C.

Network scheduling

D.

Forward scheduling

Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed?

Please choose the correct answer.

Response:

A.

Cost indicators

B.

Project cost indicators

C.

Operative indicators

D.

Billing indicators

What are the pre-requisites for distributing work to HR Resources?

There are 2 correct answers to this question.

Response:

A.

In Customizing for the Project System, you must have defined profiles for workforce planning in Resources.

B.

Assigned work centers to the internally processed activities.

C.

Assigned one or more labor capacity to a work center.

Which item category do you choose if you do not want to include the components in inventory management but want to use them immediately in the network?

Please choose the correct answer.

Response:

A.

Stock item

B.

Network item

C.

Non-stock item

D.

Procurement item

Which of the following cannot be entered when using service activities in networks for planned and unplanned services?

Please choose the correct answer.

Response:

A.

Goods receipt

B.

Goods issue

C.

Service entry

D.

Service acceptance

In your project, you choose internal activities to confirm actual dates. After you partially confirmed an internal activity, you want that the actual start will be considered for the calculation of the earliest scheduled dates.How can you implement this?

Please choose the correct answer.

Response:

A.

Deactivate actual date consider indicator in Parameters for Network Scheduling.

B.

Deactivate the shift order indicator in Parameters for Network Scheduling.

C.

Activate the actual date consider indicator in Parameters for Network

Scheduling.

D.

Activate the shift order indicator in Parameters for Network Scheduling.

How can you determine the degree of control yourself if you are managing material in plant stock or according to individual WBS element where you have no control over procurement or fully responsible for procurement?

Please choose the correct answer.

Response:

A.

Requirements controlling

B.

Requirements grouping

C.

WBS grouping

D.

Project grouping