UU has partnered with a supplier who has expertise in training and change management. The supplier will provide a virtual change office function, helping staff in the business prepare for the significant transformation ahead and ensuring that the benefits will be realized. However, these change management services are very costly.

Is this an appropriate application of the ‘justification’ theme, and why?

A.

Yes, because the costs are justified by the support provided to staff members and the benefits to be delivered

B.

Yes, because the money saved by having a single call centre will provide contingency to pay for the change office

C.

No, because the BCM should use a network of internal change agents to support the changes in order to save money

D.

No, because defining the need for additional supporting offices is part of tailoring the ’organization’ theme

The ‘identify the programme’ process has started. The programme manager organized a meeting to discuss the work being planned for the ‘design the outcomes’ process. It was agreed that the Call Centre Manager and the CEngO should be included in future planning meetings.

Which theme is being applied?

A.

Organization

B.

Design

C.

Justification

D.

Structure

Which of the following is not correct about 'Leading change'?

A.

Appoint right people at right time

B.

Actively engage stakeholder

C.

Create novel solutions to problems

D.

Get approval from sponsoring group

Which of the following is Not one of MSP defined levels of stakeholder engagement?

A.

Maintain Interest

B.

Formally Approve

C.

Active Consultation

D.

Keep informed

Significant changes to the customer processes have been delivered and Tranche 2 is now complete. Many engineering staff do not believe that the Training Project is needed in Tranche 3 as they feel the changes to the new customer processes are minor. The programme manager is concerned that the engineering staff may have misunderstood the extent of the changes. As a result, the programme manager noted in the end-of-tranche report for Tranche 2, that there needs to be more engagement with engineering staff during subsequent tranches.

Is this recommendation an appropriate application of the 'evaluate new information' process, and why?

A.

Yes, because the end-of-tranche report should include a list of risks to the next tranche

B.

Yes, because the end-of-tranche report should report on the effectiveness of communications

C.

No, because the end-of-tranche report should focus on the programme’s financial performance

D.

No, because the end-of-tranche report should focus on progress towards the target operating model

Halfway through Tranche 2, North City local government announced a new incentive programme to support green initiatives that help residents reduce their carbon footprint. UU is applying for this funding, claiming that its water smart meters and leak detection systems qualify as eco-friendly mechanisms aligned to the new government scheme. The cost of the application process will be more than paid for if UU is approved as part of the incentive programme.

Is this an appropriate application of the justification' theme, and why?

A.

Yes, because the programme budget should include financial contingency to deal with identified opportunities

B.

Yes, because the sponsoring group should pursue valuable opportunities and make them more likely to occur

C.

No, because the funding approach for this programme should ensure that the programme is self-funded by this point

D.

No, because the programme should consider the ‘do nothing’ option, plus at least two other options, before pursuing the opportunity

At the start of the programme, the programme manager listed some design-related actions to be completed. Which role is MOST focused on each task?

Which of following Best defines capital cost?

A.

Costs associated to roles for programme management

B.

Costs of activities associated in realizing the benefits

C.

Cost of BCM and change team

D.

Cost of fixed assets

At the end of Tranche 2, the programme office lead reported that the overall programme cost would exceed the current budget. The SRO has recommended to the sponsoring group that the programme budget be increased, to enable the programme to deliver the full target operating model, as originally planned.

Which theme is being applied to the ‘evaluate new information' process?

A.

Design

B.

Justification

C.

Knowledge

D.

Assurance