The programme is in the ‘deliver the capabilities’ process in Tranche 3. Engineering staff have been installing the new water meters. As a result, fewer staff than planned have attended the first few training courses, delivered as part of the Training Project. If this trend continues, realization of the reduced costs could be delayed. The programme manager has asked the CEngO to schedule this routine work so that the engineers can attend training courses in the future.
Which theme is MOST relevant to this situation, and why?
As a result of the Training Project in Tranche 3, a new onboarding process is being piloted. When new employees join the organization, they will be partnered with an experienced member of staff for their first two weeks. This will enable them to learn their new roles through observation, conversation, and hands-on experience to ensure that the increased number of gas and electricity customers is achieved.
Is this an appropriate application of the 'embed the outcomes' process, and why?
Which of the below is not a critical organizational element?
The CFO has informed the programme board that the predicted increase in electricity and gas customer numbers is too optimistic. The BCM has produced new targets based on this new information. The programme manager has updated the target operating model to reflect this.
Is this an appropriate application of the ‘align with priorities' principle, and why?
In which MSP theme would you expect to find the POTI model?
Where in the transformational flow would the Benefits Map normally be created?
It has been agreed with the sponsoring group that a risk review should be held before any of the new customer processes and web-based portal services are used by call centre staff to consider any risks before transition. This risk review needs to be documented appropriately.
Which role should approve the inclusion of this risk review in the relevant programme control document?
Which of the following is an activity in Defining a Programme?
Which of following is not a principal control for managing the tranches?
Which of the following is not an Input to delivering the capability?