The programme is now in the ‘close the programme’ process. All the planned training from the Training Project has been completed. However, it is too early to tell how much impact the training will have on service to customers. This will need to be monitored during normal business operation.
Which theme is MOST relevant to this situation?
Which of the following is NOT set out by the Programme Brief?
When it is found that an acceptable Business Case is not emerging, which of the following is NOT one of the normal options?
The programme is in the ‘close the programme' process. All the projects have been successfully completed, and the capabilities have been delivered. However, some of the new sales roles are still to be recruited in order to deliver increased sales. The programme manager has passed the management of this remaining work to the HR Director.
Is this an appropriate action for the programme manager to take, and why?
Here are three actions to be performed during the Smart Meter Programme. Which role has an area of focus associated with each statement?

The programme is in the ‘embed the outcomes’ process at the end of Tranche 2. As part of the adopt the capabilities activity, the BCM is concerned that many of the sales staff are continuing to use the old sales system alongside the new systems and processes. This is impacting on cost reductions and increased sales. The BCM has confirmed that the new system has all the functionality required.
As part of the ‘adopt the capabilities' activity what should the BCM do to resolve this situation?
The following statement needs to be recorded:
"The vision statement will be developed and tested in a facilitated workshop with the senior officers from each department, before final approval by the CEO."
In which section of the programme strategy should this be recorded?
Which of the following is a critical organizational element?
Which of following is a key attribute for a SRO?
The programme has successfully completed all projects and work according to the delivery plan and is in the ‘close the programme' process. All internal staff, who had worked on the programme, must now be transferred back into business as usual roles.
Which role should be responsible for managing these activities?
