Spring Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

The programme is now in the ‘close the programme’ process. All the planned training from the Training Project has been completed. However, it is too early to tell how much impact the training will have on service to customers. This will need to be monitored during normal business operation.

Which theme is MOST relevant to this situation?

A.

Design

B.

Knowledge

C.

Organization

D.

Structure

Which of the following is NOT set out by the Programme Brief?

A.

Risks and issues

B.

Estimated cost

C.

Analysis of the options available

D.

Key resources needed

When it is found that an acceptable Business Case is not emerging, which of the following is NOT one of the normal options?

A.

Seek further funding for the programme

B.

Design a Blueprint that is less ambitious

C.

Close the Programme

D.

Find a different approach to delivering the Blueprint

The programme is in the ‘close the programme' process. All the projects have been successfully completed, and the capabilities have been delivered. However, some of the new sales roles are still to be recruited in order to deliver increased sales. The programme manager has passed the management of this remaining work to the HR Director.

Is this an appropriate action for the programme manager to take, and why?

A.

Yes, because the remaining recruitment should be handed to the HR Director to ensure that the benefits are realized

B.

Yes, because the impact of closure on the HR Director needs to be understood and managed well

C.

No, because programme information should be up-to-date and archived before the programme can be formally closed

D.

No, because the SRO should be responsible for disbanding the programme team and closing the programme

Here are three actions to be performed during the Smart Meter Programme. Which role has an area of focus associated with each statement?

The programme is in the ‘embed the outcomes’ process at the end of Tranche 2. As part of the adopt the capabilities activity, the BCM is concerned that many of the sales staff are continuing to use the old sales system alongside the new systems and processes. This is impacting on cost reductions and increased sales. The BCM has confirmed that the new system has all the functionality required.

As part of the ‘adopt the capabilities' activity what should the BCM do to resolve this situation?

A.

Start reporting on the reduced costs and increased sales compared to the baselines

B.

Confirm that the sales staff have transitioned successfully to the new sales system as It is being used by all staff

C.

Encourage those staff members who are using the new system effectively to share their knowledge and experiences

D.

Ensure that access to the old sales system is removed and provide support in the new ways of working

The following statement needs to be recorded:

"The vision statement will be developed and tested in a facilitated workshop with the senior officers from each department, before final approval by the CEO."

In which section of the programme strategy should this be recorded?

A.

Governance approach

B.

Stakeholder engagement approach

C.

Design approach

D.

Decision-making approach

Which of the following is a critical organizational element?

A.

Leading change

B.

Stakeholder engagement

C.

Quality management and assurance

D.

Delivery mechanisms for change

Which of following is a key attribute for a SRO?

A.

Good knowledge of project management approaches

B.

Should represent a relevant business area

C.

Have ongoing operational responsibilities

D.

Have access to and credibility with key stakeholders

The programme has successfully completed all projects and work according to the delivery plan and is in the ‘close the programme' process. All internal staff, who had worked on the programme, must now be transferred back into business as usual roles.

Which role should be responsible for managing these activities?

A.

Sponsoring group members

B.

Senior responsible owner

C.

Programme manager

D.

Business change manager