According to the guidance for effective quality management, when should the requirements for a product be captured?

A.

When the project team realizes that the product is needed

B.

When the project team needs to test the product

C.

When the project team needs to know whether the product has been approved

D.

When the project team needs to know how the product will be delivered

Which is a step in the recommended approach to 'defining and analyzing the products'?

A.

Preparing estimates

B.

Designing a plan

C.

Writing a project product description

D.

Identifying activities and dependencies

Identify the missing word in the following sentence.

The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.

A.

activities

B.

processes

C.

products

D.

quality

According to PRINCE2, why might there be more than one business case for a project?

A.

There may be more than one management stage in the project

B.

The project may be in a commercial environment with a number of suppliers

C.

There may be more than one work package being delivered in the project

D.

The project may be in a programme environment

Which describes a risk event?

A.

The area of uncertainty in terms of the threat or opportunity

B.

The derivation or sources of a potential risk to the project

C.

The achievement of a milestone on the project plan

D.

The sequence of events and actions that will be put in place if a risk occurs

Which describes a risk effect?

A.

The uncertainty expressed as a negative or favourable occurrence

B.

The issue which is affecting the project and has resulted in a risk

C.

The impact(s) on the project objectives should the threat or opportunity occur

D.

The change in the status of a risk in response to actions taken to control it

Which is a minimum requirement for applying the quality theme?

A.

To define the project's approach to quality control

B.

To undertake independent audits of the project throughout the project

C.

To apply the recommended quality review technique

D.

To define the project's approach to quality assurance

Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.

A.

Project Assurance

B.

Project Support

C.

the risk actionee

D.

the risk owner

Which is a purpose of a lessons log?

A.

To record any lessons that are raised in checkpoint reports

B.

To document that corrective action is being taken

C.

To escalate lessons to the project board

D.

To raise improvements with project assurance

Why is the 'learn from experience' principle applied to a project?

A.

To enable the project team to repeat successes from previous projects

B.

To enable the project team to develop a business case for the project

C.

To allow the project to be divided into management stages

D.

To enable the project team to use tolerances to delegate authority