Which is a key decision made during the 'directing a project' process?

A.

Select and appoint the project executive

B.

Approve the project manager role description

C.

Confirm that the benefits management approach addresses all expected benefits

D.

Approve the proposed project mandate

Which describes risk probability?

A.

Level of risks which the project can tolerate before escalating to the Project Board

B.

Probable effect on the project delivering its objectives

C.

Timeframe within which the risk may occur

D.

A measure of the likelihood of the risk occurring

Which statements about quality assurance and project assurance are CORRECT?

1. They are both independent of the project manager

2. They are both the responsibility of the project board

3. They are both independent from the project management team

4. They both assure that applicable standards are being used

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Where should decisions regarding the tailoring of the project be recorded?

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Stage plan

Which role is responsible for ensuring the project is justified in terms of cost?

A.

Project manager

B.

Executive

C.

Senior user

D.

Senior supplier

Which are benefits of using PRINCE2?

1. It removes the need for activity-based planning

2. It promotes learning and continuous improvement

3. It can be applied to any type of project

4. It defines specific leadership and other interpersonal skills required

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?

A.

Manage by exception

B.

Learn from experience

C.

Tailor to suit the project environment

D.

Defined roles and responsibilities

Which is a minimum requirement for applying the quality theme?

A.

To use lessons to inform quality planning

B.

To use the prescribed approach to quality management

C.

To use external quality standards for quality control

D.

To use user stories to inform the project product description

Which are objectives of the 'managing a stage boundary' process?

1. To control the link between the people managing the project and the people producing the products

2. To approve requests for change received during the completed stage

3. To provide information to the project board on the performance of the current stage

4. To review and, if necessary, update the project management team structure and role descriptions

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Which is a purpose of a project brief?

A.

To act as a base document which enables the project board to assess progress

B.

To provide a sound basis for project initiation

C.

To define how the achievement of the project's benefits can be measured

D.

To provide a description of the means and frequency of communication