Which is a key decision made during the 'directing a project' process?
Which describes risk probability?
Which statements about quality assurance and project assurance are CORRECT?
1. They are both independent of the project manager
2. They are both the responsibility of the project board
3. They are both independent from the project management team
4. They both assure that applicable standards are being used
Where should decisions regarding the tailoring of the project be recorded?
Which role is responsible for ensuring the project is justified in terms of cost?
Which are benefits of using PRINCE2?
1. It removes the need for activity-based planning
2. It promotes learning and continuous improvement
3. It can be applied to any type of project
4. It defines specific leadership and other interpersonal skills required
Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?
Which is a minimum requirement for applying the quality theme?
Which are objectives of the 'managing a stage boundary' process?
1. To control the link between the people managing the project and the people producing the products
2. To approve requests for change received during the completed stage
3. To provide information to the project board on the performance of the current stage
4. To review and, if necessary, update the project management team structure and role descriptions
Which is a purpose of a project brief?