Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exc65

Which risk response is applied on a pain/gain basis?

A.

Share

B.

Accept

C.

Exploit

D.

Enhance

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

A.

End Stage Report

B.

Team Plan

C.

Work Package

D.

Project Plan

Which is a responsibility of a risk owner?

A.

Identify risks to the project that might occur in their department

B.

Own and authorize the use of the risk budget to fund risk responses

C.

Manage, monitor and control all aspects of an assigned risk

D.

Determine project risk appetite

Which is an objective of the 'managing a product delivery' process?

A.

To ensure the business case is regularly reviewed

B.

To assess whether the stage products have been approved

C.

To deliver the planned specialist products within tolerance

D.

To request authorization to start the next stage

Which is a factor when deciding the duration of a management stage?

A.

The work packages to be delivered

B.

The level of risk in the project

C.

The cost of the stage

D.

The number of products to be produced in the project

Which is a minimum requirement for applying the 'change' theme?

A.

Specify in the change control approach the means by which project products will be protected

B.

Document the format and contents of the issue register

C.

Produce issue reports to document the impact assessment for requests for change

D.

Delegate the change authority to the senior supplier(s) for supplier off-specifications

Which management level should approve a course of action if project-level tolerance is exceeded?

A.

Corporate, programme management or the customer

B.

Project board

C.

Project manager

D.

Team manager

Which activity is part of the recommended risk management procedure?

A.

Allocating a budget to investigate issues

B.

Reviewing risk management practices to ensure that they are performing effectively

C.

Sending information to stakeholders about risks to the projects

D.

Resolving conflicts between the project and the programme board

How does the ‘managing product delivery’ process ensure that the team manager’s perspective is provided in a work package?

A.

The work packages are defined by the team manager and supported by a team plan

B.

the work packages provided by the project manager are agreed by the team manager

C.

The team plans are checked by project assurance against the work packages

D.

The stage plan covering the work packages is created with input from the team manager

How can the risk culture of 3n organization make decision-making less effective?

A.

By using statistical modelling be understand the Impact of risks and their likelihood

B.

By establishing a risk budget to make funding risk responses actions easier

C.

By Individuals adopting an attitude that leads them to ignore threats to objectives

D.

By Involving stakeholders in assessing the likelihood and impact of each risk