Why is change management important in a project?
The project manager needs to confirm that operational teams are responsible for the running of the outputs.
During which step of the ‘organizational design and development’ technique should the project manager ensure this?
When is a work breakdown structure MOST useful?
What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?
Which term is defined as a product that will not meet is quality specifications?
Identify the missing word in the following sentence:
[ ?] is a prediction made by studying historical data and past patterns.
The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.
In which step of the ‘issue management technique should the change authority request this information?
Which common project context relates to the need to engage with external suppliers to deliver part of the project?
Which plan should only be produced if the project is large and complex enough?
How does product-based planning help to determine the project approach?