The project manager needs to monitor the progress of the stage.

Which combination of management products should the project manager review?

A.

Checkpoint reports AND work package descriptions

B.

Project plan AND project log

C.

Project plan AND work package descriptions

D.

Highlight report AND checkpoint report

The project manager needs to document how risk management will be undertaken during the project.

In which step of the 'risk management’ technique should the project manager document this?

A.

Identify: define context and objectives

B.

Identify: identify threats and opportunities

C.

Assess: prioritize risks

D.

Assess: combine risk profile

Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

A.

Initiating a project

B.

Starting up a project

C.

Controlling a stage

D.

Managing product delivery

Which statement about the 'manage by stages’ principle is CORRECT?

A.

The project board should authorize multiple stages at the same time

B.

The end of a stage should provide a control point for the project board

C.

A project should have fewer, longer stages when the risk exposure is high

D.

A project should have separate stages to plan, deliver and close the project

The project manager needs to understand what makes the outputs acceptable to the users.

In which step of the 'planning' technique should this occur?

A.

Defining and analysing the products

B.

Organizing work packages

C.

Preparing estimates

D.

Preparing a schedule

According to the ‘manage by exception’ principle, which aspect of performance sets limits against the cost of aggregated threats?

A.

Risk

B.

Scope

C.

Quality

D.

Cost

Which describes user's quality expectations?

A.

They are documented in the project product description

B.

They are documented in the quality management approach

C.

They are documented in the stage plan

D.

They are documented in the product descriptions

When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?

A.

When a request for change is recorded on the issue register

B.

When a business opportunity has been recognized

C.

When the project manager receives a request for change

D.

When a change has been approved by the change authority

How do issue management and change control relate to each other?

A.

Change control and Issue management are separate processes

B.

Issue management is part of change control

C.

change control is part of issue management

D.

issue management and change control are identical

The project manager needs to record the impact assessment for a specific business opportunity.

In which management product should the project manager record this?

A.

Issue report

B.

Issue register

C.

Risk register

D.

Quality register