What is a purpose of the communication management approach?

A.

To define how the project team intends to obtain responses from stakeholders

B.

To describe the techniques required to make the project product acceptable to stakeholders

C.

To describe the target organizational state and how the business will move to that new state

D.

To describe the processes used to engage with stakeholders in identifying uncertainties

A new team member has joined the project team and wants to understand who else is on the project team, and who they report to.

Which management product should the team member review?

A.

Project plan

B.

Project management team structure

C.

Role descriptions

D.

Project log

Which TWO are objectives of the ‘controlling a stage process?

1. To focus attention on achieving Work Within) the agree tolerances

2. To create follow on action recommendations for all open issues and risks

3. To understand how the quality required will be achieved

4. To ensure that the stage’s products meet-agreed quality expectations

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Why is it necessary to apply the 'defined roles and responsibilities' principle?

A.

Because the people involved in a project should know what is expected of them

B.

Because the project management team should be cross-functional

C.

Because the user and supplier interests should be involved on a need-to-know basis

D.

Because the project manager should represent all the stakeholders of the project

What 15the purpose of the ‘progress! practice?

A.

To review whether the use of the products is likely to lead to the expected benefits

B.

To define the roles and responsibilities for monitoring progress

C.

To measure actual achievements against the planned time and cost targets for the project

D.

To control events that could have a positive or negative effect on project objectives

Identify the missing word(s) in the following sentence.

The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

A.

delivery step

B.

benefit

C.

delivery stage

D.

team plan

Which is a purpose of a quality register?

A.

To record cross-references to issues relating to the quality of the products

B.

To record the date a completed work package was received

C.

To provide the status of quality activities carried out for completed products

D.

To capture quality concerns about completed products

What is an advantage of dividing the project into stages?

A.

Detailed plans can be prepared closer to the time events will take place

B.

the project board can delegate management of the project to team managers

C.

The project can be authorized by the project manager on a stage by stage basis

D.

The project brief can be updated towards the end of each stage