Which is 3 purpose of the ‘plans! practice?

A.

To enable an event that requires project management consideration to be controlled

B.

To provide the standards against which the project products can be quality controlled

C.

To provide the basis of control against which a project's progress can be monitored

D.

To enable control of opportunities and threats, that could Impact on delivery of the business objectives

What should be recorded in a quality register?

1. Activities to ensure the products are fit for purpose

2. Identified threats and opportunities

3. Problems and concerns to be managed informally

4. Roles responsible for reviewing the project's products

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

A.

By providing a common understanding of the products required

B.

By providing the tolerances for the project manager’s objectives

C.

By providing roles descriptions for the project management team

D.

By providing the justification for the project

What is the change authority role permitted to authorize?

A.

Risks to the project

B.

Adjustments to the limits on the change budget

C.

Changes to stage tolerance

D.

Changes to the project that do not exceed a defined budget

Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?

A.

Each party may have their own business case for undertaking the project

B.

Both parties must apply the same external governance to the project

C.

The risk appetite should be collaboratively set before the project starts

D.

Management systems need to be unified for successful project delivery

What is a risk actionee responsible for?

A.

Identifying risks to the project that might occur in their department

B.

Owning and authorizing the use of the risk budget to fund risk responses

C.

Managing, monitoring and controlling of all aspects of an assigned risk

D.

Carrying out a risk response action to respond to a particular risk

What statement describes how the project manager should ensure effective communication within a project?

A.

Use a more structured approach to communication with co-located teams, then remote teams

B.

Rely on regular reporting by team managers to determine whether the work Is on track

C.

Involve 3 small group of key stakeholders when defining the project to reduce the amount of communication

D.

Focus on publishing standard messages to key influencers throughout the project

What must be produced to meet the minimum requirements when applying the change theme?

A.

A change budget for the analysis of change

B.

Records of the decisions made on all issues

C.

Documents recording the version of each product

D.

Status reports on all products being produced

Which is an objective of the 'controlling a stage' process?

A.

To review the business justification for the project

B.

To replan the current stage when directed

C.

To develop products to defined quality criteria

D.

To produce a learn plan for the work package

When is the 'managing a stage boundary' process used?

A.

Immediately alter the project board has authorized the previous stage

B.

Immediately after the project board has authorized the next stage

C.

Near the end of each stage

D.

Near the end of delivery stages