Which principle ensures that people are empowered to self-manage and stay in control with the appropriate level of governance?

A.

Ensure continued business justification

B.

Tailor to suit the project

C.

Manage by exception

D.

Focus on products

Which TWO project board responsibilities are specifically assigned to the senior user?

1) Demonstrating the achievement of benefits.

2) Specifying the needs of those impacted by the outputs.

3) Balancing business, user and supplier demands.

4) Ensuring that the project delivers value for money.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Which of the following BEST describes stakeholders in a project?

A.

Those who have a formal role in the project team

B.

Those who will use project products

C.

Those who can affect or be affected by the project

D.

Those who can impact the project

What is used to address aspects of project and product development such as problem solving and release planning?

A.

Delegation matrix

B.

Project log

C.

Agilometer

D.

Agile workshops

In which step of the approach to issue management are options to resolve an issue evaluated?

A.

Capture

B.

Implement

C.

Decide

D.

Recommend

Which statement about the ‘initiating a project’ process is CORRECT?

A.

The initiation stage plan should form part of the project plan

B.

The impact of frequent releases on quality management should be assessed

C.

The process should take more time than usual for disruptive projects

D.

The project solution should be documented in detail in the project product description

Which statement about the ‘directing a project’ process is CORRECT?

A.

The project board should attend regular project progress meetings

B.

The project board should make decisions based on the Agilometer risks

C.

A project board member should fulfill the product owner role within a delivery team

D.

The project board should increase the stage-level time tolerance

What is essential to secure leadership buy-in for scaling up agile?

A.

Speaking the language of leadership

B.

Ensuring that all decisions are made by leadership

C.

Ensuring emphasis on doing agile

D.

Empowering teams to self-manage

Which of the following is used to monitor progress?

A.

Delegation matrix

B.

Swarming

C.

T-shirt sizing

D.

Burn-down chart

Which role is responsible for facilitating the Agilometer assessment?

A.

Project board

B.

Project manager

C.

Team manager

D.

Customer subject matter expert