When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?

A.

Preferable

B.

Typical

C.

Effective

Which TWO statements about the supplier subject matter expert are CORRECT?

1) They provide a wider picture of the customer view.

2) They prioritize requirements at the detailed level.

3) They should be focused on the customer.

4) They ensure that the work is compliant with project standards.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

How is the ‘learn from experience’ principle applied in an agile context?

A.

By ensuring control through lots of short stages during innovative projects

B.

By using the Agilometer to assess risks associated with the agile way of working

C.

By continual customer involvement to obtain feedback during the project

D.

By prioritizing quality criteria to focus the project on the delivery of value

How does PRINCE2 Agile describe Scrum?

A.

Scrum is an IT method

B.

Scrum is agile and agile is Scrum

C.

Scrum is the most well-known agile framework

D.

Scrum is a project management framework

What should be emphasized when tailoring the PRINCE2 Progress theme?

A.

Monitoring what is being delivered

B.

Tracking time and cost

C.

Planning resources

D.

Assessing the impact of risks

Which statement describes how the PRINCE2 ‘starting up a project’ process can be applied in an agile environment?

A.

PRINCE2 is predictive, but not emergent

B.

PRINCE2 is predictive and can be emergent

C.

PRINCE2 requires a lengthy start to a project

D.

PRINCE2 requires a disruptive start to a project

What should be decided when configuring PRINCE2 effectively?

A.

What to remove and where to add guidance

B.

Where to put the emphasis and where to add guidance

C.

What to significantly change to create the right blend

D.

Which areas are not enabled to work with agile

How is the ‘tailor to suit the project’ principle applied in an agile context?

A.

By flexing what is produced to stay in control and deliver value

B.

By emphasizing tolerances on what is being delivered

C.

By using the Agilometer to assess the project environment

D.

By fitting releases into planned management stages

Which statement about the ‘directing a project’ process is CORRECT?

A.

The project board should attend regular project progress meetings

B.

The project board should make decisions based on the Agilometer risks

C.

A project board member should fulfill the product owner role within a delivery team

D.

The project board should increase the stage-level time tolerance

Which is a key objective of running a workshop?

A.

To make daily progress visible to the delivery team and key stakeholders

B.

To encourage collaboration and create the defined outputs from the event

C.

To communicate decisions to the wider stakeholder community

D.

To make day-to-day decisions on behalf of the delivery team within a sprint