Which statement describes the Kanban approach?

A.

It is used to make system improvements using visualization and by controlling work in progress

B.

It is an iterative timeboxed approach that helps teams generate value

C.

It was originally focused in creating new companies and is now used to speed up product delivery

D.

It has defined processes, products and roles used to iteratively deliver outputs using timeboxing

Which is a reason for releasing a product into a staging area?

A.

It enables the faster delivery of changes

B.

It supports regulatory compliance checking

C.

It enables a phased Waterfall approach

D.

It supports management by exception

Which statement about the ‘keep teams stable’ target is CORRECT?

A.

It applies primarily to the long term, such as a project or a program

B.

It is the primary reason why the tolerance for cost is set to zero

C.

It prevents compromising the overall quality level of the product

D.

It results in the early delivery of a minimum viable product

How does the change theme regard change in PRINCE2 Agile?

A.

As disruptive

B.

As something to be avoided

C.

As a necessity

D.

As inevitable

Which statement about the ‘keep teams stable’ target is CORRECT?

A.

It ensures that the level of quality is protected

B.

It will lead to a lower cost of ownership

C.

It is required in order to allow the team to self-organize

D.

It results in the earth delivery of a minimum viable product

Which role is responsible for facilitating the Agilometer assessment?

A.

Project board

B.

Project manager

C.

Team manager

D.

Customer subject matter expert

Which TWO statements describe a purpose of the business case?

1) To define the acceptance criteria for what the project must deliver.

2) To transfer responsibility for the work to the appropriate delivery team.

3) To document how significant risks will affect the expected project benefits.

4) To outline how and when the anticipated benefits can be measured.

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

What term is used to describe boards that display what work needs to be completed for people working on a project?

A.

Work in progress limit

B.

Information radiator

C.

Highlight report

D.

Glad! Sad! Mad!

Which well-known agile method uses visualization, and controls work in progress?

A.

Scrum

B.

Lean Startup

C.

Lean

D.

Kanban

Why are team working agreement produced?

A.

To create structure so that the team manager can assess individual performance

B.

To evolve the effectiveness and behaviors of the self-organizing team by agreeing values

C.

To make the team rules visible to the project manager for monitoring purposes

D.

To ensure that the delivery team members comply with company policy