What should the business case state about the minimum viable product (MVP)?

A.

When the MVP will be defined

B.

That the MVP must go into operational use

C.

What the MVP is

D.

That the MVP is the same as project viability

Which statement about the ‘keep teams stable’ target is CORRECT?

A.

It ensures that the level of quality is protected

B.

It will lead to a lower cost of ownership

C.

It is required in order to allow the team to self-organize

D.

It results in the earth delivery of a minimum viable product

Which statement about the ‘embrace change’ target is CORRECT?

A.

It minimizes the time needed to train a new team member

B.

It reduces the planning of dependencies between projects

C.

It reduces testing in order to meet deadlines

D.

It encourages the customer to raise new ideas

Which is a purpose of the ‘controlling stage’ process?

A.

To execute and deliver the project product

B.

To establish whether the project is complete

C.

To report stage progress to the project board

D.

To draft the plan for the next stage’s work

Which of the following describes shared attitudes, values, and goals?

A.

Culture

B.

Leadership

C.

Co-creation

D.

Management

How should product-based planning be used as part of PRINCE2 Agile?

A.

To track progress against the team plan

B.

To create the project plan using empiricism

C.

To enable team planning to be predictive

D.

To plan by focusing on the features required

What is the definition of a timebox?

A.

A tool to write a requirement in the form of who, what and why

B.

A regular event that looks at how processes can be improved

C.

A description of the rate of progress a team is making

D.

A period where work is carried out to achieve a goal

Which statement about the waterfall methodology definition is CORRECT?

A.

It states that deadlines should not be moved

B.

It has distinct goals for each stage of development

C.

It is a behavior that involves making things transparent

D.

It promotes the use of experiments carried out in a scientific way

Which workshop reflects on lessons learned?

A.

Team planning workshop

B.

Agile enablement workshop

C.

Project kickoff workshop

D.

Project closure workshop

What is an epic?

A.

A detailed user story with high business value

B.

The set of products handed over to the users

C.

A high-level user story that is quite broad or vague

D.

A prioritized list of requirements to be delivered in a sprint