Halloween Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

A project manager is preparing a large and complex international project. In order for the team to work well together in a virtual environment, the project manager needs to set up ground rules for good communication.

What should the project manager do first?

A.

Establish a communication channel.

B.

Create a communication protocol.

C.

Develop the stakeholder analysis.

D.

Distribute the risk register.

During a sprint, the team is experiencing conflict because the customer asks for additional features that increase the complexity. The scrum master is trying to resolve the conflict.

Which approach should the scrum master use?

A.

Discuss the definition of done (DoD) with the customer.

B.

Approach the product owner to determine the next course of action and update the backlog.

C.

Discuss the acceptance criteria with customer.

D.

Perform backlog prioritization to ensure that everyone is working on the highest value features.

A project manager is working on a project to develop a new watch at a matrix organization.

Which two key items should the project manager include in their feedback to external stakeholders? (Choose 2)

A.

Schedule performance index (SPI) for the portfolio

B.

Earned value in terms of resources

C.

Expected return on investment (ROI) for portfolio projects

D.

Earned value in terms of schedule

E.

Earned value in terms of cost

A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time.

How should the project manager handle this situation?

A.

Remind the contractor to join the meetings and submit their report as this is their commitment.

B.

File a claim for not fulfilling the contract terms in accordance with alternative dispute resolution.

C.

Compromise with the contractor to only attend the weekly meetings without submitting the reports.

D.

Assess the situation as a risk and reach out to the contractor to check the origin of this resistance.

A project team is concluding the final sprint to deliver two work packages. However, the scrum master has not scheduled sprints for three packages on the critical path, which is going to cause the schedule performance index (SPI) to trend toward 0.90 the following month.

What should the project manager do first?

A.

Evaluate the schedule performance index (SPI) trend for slack to enable all five sprints while maintaining the cost performance index (CPI).

B.

Instruct the scrum master to suspend the current sprints and initiate the critical sprints immediately.

C.

Ask the scrum master to identify why sprints are in process for work that is not on the critical path.

D.

Contact the project sponsor to request adjustment to the completion date and to enable the current workflow.

A project manager is planning the fifth sprint of a project when the sponsor requests a report on the business value gained to date. What should the project manager show to the sponsor?

A.

The cumulative flow diagram

B.

The data of the metrics defined to track benefits

C.

The metrics plan to track benefits

D.

The fifth sprint retrospective report

A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.

What should the project manager do next?

A.

Agree with the project team to modify and delete some of the stories in the current sprint backlog

B.

Obtain approval from the project team and add the new story to the product backlog

C.

Receive an agreement from the product owner and add the new story to the product backlog

D.

Negotiate with the scrum master before adding the new story to the sprint backlog

A project manager is leading a project team that consists of five team members. One of the team members, a senior technical staff member, always criticizes the ideas of other members during team meetings. However, this senior technical member is not performing well on their own daily tasks. Other team members are frustrated and have become silent in meetings.

What should the project manager do?

A.

Reduce the team meeting frequency and seek input separately from team members.

B.

Ask human resources (HR) to reassign the senior technical staff member.

C.

Encourage other team members to provide one another with their valuable ideas.

D.

Provide feedback to bring the team members' focus back to the performance of their daily tasks.

During a sprint, the product owner requested a change in the features to be delivered in the same sprint. According to the product owner, the request from the customer is due to regulatory reasons and they have a deadline to meet.

What should the project manager do?

A.

Perform the change only if it has a higher or equivalent priority of the current remaining features.

B.

Submit the feature changes to the change control board (CCB) so they can evaluate and approve.

C.

Follow the plan by delivering the features and handle the change later in the project.

D.

Discuss with the stakeholders about the possibility of accommodating the feature changes.

A major public-transportation construction project is aimed at significantly reducing emissions. The project has been severely delayed due to noncompliance with environmental codes and bylaws.

What should the project manager have done to prevent this?

A.

Incorporated sufficient schedule reserves based on similar delays in past projects.

B.

Appointed a senior environmental compliance officer to report directly to the project manager.

C.

Mapped environmental compliance requirements, identified risks to achieving them, and prepared mitigations.

D.

Approached the regulator for a partial waiver in light of the environmental importance of the project.

A project manager was assigned to lead a global project with a virtual team that is globally dispersed. The project manager has difficulties communicating with the team members and there seems to be frequent misunderstandings and conflicts.

What should the project manager do?

A.

Ask the team members to refamiliarize themselves with the communications management plan.

B.

Organize effective communication training for team members.

C.

Listen to team members actively and change the communication practices accordingly.

D.

Model servant leadership by adapting to team requirements.

A project has obtained all of the necessary legal requirements and policies from the local government. During the execution phase, the product owner is informed that a new law impacting the project deliverables will be published within two weeks.

What should the project lead do?

A.

Review the product backlog items to evaluate the impact on scope and prioritize accordingly.

B.

Develop a change request for more resources and update the project budget and schedule.

C.

Ask the internal legal department to evaluate if the regulatory law could be managed internally.

D.

Work with the team to develop an alternative solution with no additional effect on the project's budget.

A project is near completion but it is behind schedule. The contingency budget has already being used, although the remaining budget should be

enough to complete the project. The only subject matter expert (SME) assigned to the project has been asked by their manager to solve a

problem in the operations department.

What should the project manager do?

A.

Escalate the situation to the project sponsor.

B.

Free the resource to handle the operations priority.

C.

Ask the manager to submit a change request.

D.

Design a negotiation strategy for this situation.

A key project stakeholder recently joined the project and is questioning some of the previously made decisions. This starts to impact project execution.

What should the project manager do?

A.

Reach out to the stakeholder via phone to explain that all decisions have been agreed upon with their predecessor.

B.

Provide the stakeholder with a link to a file-sharing site where the supporting documents for decisions are filed.

C.

Schedule a meeting with the stakeholder to provide an overview of the project, including the agreed-upon decisions.

D.

Update the risk register with a new risk of potential project changes as a result of stakeholder misalignment.

A project manager is leading a diverse project team that includes new and experienced team members. A conflict has occurred between two team members. One team member prefers using digital tools for project communication. The other team member prefers in-person meetings and phone calls for communication.

What should the project manager do to manage this conflict?

A.

Arrange a team-building activity to foster understanding and open communication among the team members.

B.

Allow the team members to continue using their preferred communication tools and methods.

C.

Initiate a conversation with the team members individually to understand their situations regarding communication.

D.

Instruct the team members to adapt to the project's communication tools and methods.