Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exc65

A project manager is assigned to an ongoing complex project. The team is delivering value each iteration However, the deliverables are internal and the customers are unaware of the deliverables.

Which action should the project manager take?

A.

Ask the internal sales team to keep the customer informed of the delivered value

B.

Evaluate various delivery options in order to immediately demonstrate value to the customer

C.

Inform the customer about the progress and update them on the final deliverables

D.

Wait for an important milestone to complete and then inform the customer of the progress

A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.

What should the project manager do?

A.

Use the agile approach in the new project and schedule agile training for those stakeholders who are new to this approach

B.

Continue to use the predictive approach m the new project since it is the approach the stakeholders are familiar with using

C.

Share the pros and cons of adopting an agile approach for the new project only with the team and ask them to decide which approach to use

D.

Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project

A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.

What should the project manager do in this situation?

A.

Explain to the management team that reporting and management dashboards are not effective agile practices

B.

Ask the management team to review the endorsed agile concepts to prove that the old information s not relevant

C.

Help the management team understand how the change to an agile approach impacts the relevance of certain reports and key performance indicators (KPls)

D.

Remind the management team that an agile approach empowers teams to be self-directed and therefore there is no need for reporting

On a recently completed prefect a project manager noticed that some of the subcontractors approached the client directly with questions. These subcontractors had a previous direct reporting relationship with the client. The project manager is now in the initial stage of a new project with the same subcontractors and client.

How should the project manager set up communications?

A.

Inform the client that all communications moving forward will go through the project manager

B.

Ensure that the communications management plan covers contractual obligations

C.

Consult the communications management plan from a recent project that has been closed

D.

Update the communications management plan to allow the subcontractors to communicate directly with the client

A transformation project that is composed of agile streams has come to an end.

How should the project manager collect the experience gained during this project?

A.

Organize a lessons learned session with the team.

B.

Create a document with the information from the last sprint retrospective.

C.

Ask for feedback during the next standup meeting.

D.

Conduct a session with the members of the project steering committee.

A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.

What should the project manager do to have a high-performing team?

A.

Set up regular project status meetings and invite all team members.

B.

Encourage the team to define the ground rules for performance.

C.

Set up individual calls to follow up on each team member's progress.

D.

Invite team members to an informal meeting to get to know one another.

A production team will soon begin their first agile project. No one in the team or management has agile knowledge. The training manager can only fund three enrollments.

Match the team role on the left to the correct training course on the right. (Use all three of the team roles.)

An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?

A.

Mitigate the risks that are applicable to the current and following iterations.

B.

Focus on the project deliverables rather than the documented risks.

C.

Agree that any issue can be handled when it becomes a problem.

D.

Acknowledge that the risks will be handled in the corresponding iteration.

A project is in the start-up phase of the project life cycle. The project team consists of 20 people from five different countries. The project team is scheduled to have quarterly face-to-face meetings. However, due to unforeseen circumstances, no face-to-face meetings can occur. The project manager is concerned that the team may not be able to fulfill their individual roles without face-to-face meetings.

What should the project manager do in this situation?

A.

Review the risk register for this unforeseen circumstance.

B.

Utilize virtual teams for meetings and deliverables.

C.

Use the contingency reserve and subcontract the work.

D.

Ask for an extension of time on the project deliverables.

After conducting a performance assessment, the project manager identified that some gaps still exist. What should the project manager ensure?

A.

Assessment results are kept private and not shared among team members.

B.

Performance improvement programs are organized for all team members who were assessed.

C.

All team members rotate their job schedules immediately to make them versatile.

D.

Awards are given to all team members for playing a role in the project and undertaking the assessment.

A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will

take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6

months.

What should the project manager do to align stakeholders’ needs and expectations?

A.

Work with the stakeholders to create a prioritized backlog and release a roadmap.

B.

Modify the requirements to those that can be completed in 6 months.

C.

Implement fast-tracking and crashing activities to complete the project in 6 months.

D.

Include all stakeholders in daily scrum meetings to keep them informed.

At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project manager mainly make reference to?

A.

Feedback from the project sponsor

B.

Agreed-upon key performance indicators (KPIs)

C.

Input from project stakeholders

D.

Competencies of team members

A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the

appropriate stakeholder participation and involvement level required for successful project delivery.

What should the project manager do?

A.

Communicate with the stakeholders to find a solution.

B.

Review the issue log with the project stakeholders.

C.

Evaluate the stakeholder engagement assessment matrix.

D.

Perform a stakeholder assumption and constraint analysis.

A project for a financial organization is in the proposal phase for the selection of a software tool. There have been conflicting opinions on the software that was ranked in the selection. After analyzing the issue, the project manager realizes that two out of the eight teams have concerns about the tool's scalability to support their business needs.

How should the project manager resolve this conflict and reach a consensus?

A.

Escalate this to senior management and ensure that the team's acceptance is achieved.

B.

Communicate to the two teams that the tool has won per the selection process and they need to accept the outcome.

C.

Ignore the conflict as the tool is selected per the proposal guidelines and the project is complete.

D.

Discuss the outcome of the proposal process and the ranking, then influence the team for acceptance.

In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums.

What should the project manager do next?

A.

Retrain all team members on daily scrum facilitation to ensure there is consistency in the approach.

B.

Ask the facilitators who are doing well to continue and recommend that the others stop facilitating.

C.

Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed.

D.

Return to using the scrum master as the facilitator for the daily scrums now that the trial period is over.

Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time.

What should the project manager do?

A.

Reschedule on-site training to online sessions.

B.

Create a risk and assign remediation actions.

C.

Cancel all of the on-site training sessions.

D.

Document the project issue and provide options.

Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.

What should the project manager do to obtain agreement from both companies and acceptance from marketing?

A.

Create a special release 4 weeks after the current release to deliver the new feature in its entirety.

B.

Stop the current release work for 4 weeks in order to work and deliver the new feature completely.

C.

Plan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value.

D.

Add the new feature to the list for the next release and continue working on the current release.

A project manager is implementing a project similar to a previous one that required strict adherence to occupational health and safety (OHS). Both projects are for the same client whose business environment is highly regulated. However, this time the client does not appear to be concerned about OHS requirements.

What should the project manager do first?

A.

Relax the OHS requirements as the client is not concerned.

B.

Discuss the OHS requirements with the client.

C.

Apply the same OHS requirements as the previous project.

D.

Discuss the OHS requirements with the regulatory organization.

A global program is being kicked off, and various distributed teams are involved in delivering the initiative. Besides planning and executing the scope for the initiative, team

interactions must be considered.

How should the project teams interact in their meetings?

A.

Phone conversations

B.

Video conferencing

C.

Encrypted emails

D.

Chat conversations

In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?

A.

Reach an agreement with the team on how to handle the situation.

B.

Reach out to the procurement team to hire a substitute for the team member.

C.

Allow senior management to decide how to proceed with the project.

D.

Convince the team member not to leave until the project is completed.

A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The

resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.

What should the project manager do?

A.

Use the remaining time and resources to add additional scope to the project without spending the project budget.

B.

Ensure product quality by spending the remaining resources and time on additional quality checks for the product.

C.

Acknowledge the project closure criteria has been met and release the remaining budget and resources.

D.

Obtain approval from the sponsor to add additional functionality to the project deliverables with the leftover budget.

Drag the items on left side to the matching term within the correct project approach on the right side.

A project manager is performing the scrum master role for a project team of developers. At the daily standup, a couple of developers complain about the noise from a neighboring team, the performance of their laptops, and the difficulty in booking meeting rooms.

What should the project manager do?

A.

Acknowledge the impediments and facilitate their resolutions.

B.

Note the impediments and escalate them to the product owner.

C.

Note the impediments and work on addressing them later.

D.

Assign actions to all stakeholders and oversee their implementation.

A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?

A.

Empower the team members to conduct their job activities and hold each person accountable to improve the schedule.

B.

Notify the project sponsor that the team is underperforming and request additional resources to compress the schedule,

C.

Contact each team member to inform them that further schedule slips will not be tolerated by the project sponsor.

D.

Begin holding daily meetings to assign each team member discrete tasks with specific due dates.

In a hybrid project, the project manager has identified a few stakeholders. According to the stakeholder matrix, the head of development has a high rating of power/influence and a high likelihood of conflict.

Which action should the project manager avoid?

A.

Escalating a conflict within the project

B.

Creating a new communication channel

C.

Giving special attention to this stakeholder

D.

Dismissing the stakeholder's opinions

An agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team's performance is not good, and some team members want to leave the team.

How should the project manager approach this situation?

A.

Measure the team's psychological safety.

B.

Reschedule the team's retrospective meeting.

C.

Coach the team to be more inclusive.

D.

Rotate the team's daily meeting roles frequently.

During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not convinced that the return on investment (ROI) can be achieved.

How should the project manager address this issue?

A.

Re-visit the project charter and seek other alternatives.

B.

Proceed and issue the purchase order as this project is important.

C.

Speak with the CEO and ask for their support to approve the offer.

D.

Analyze the bounds of negotiations for project agreements.

An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project

execution. The acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.

What should the project manager have done to prevent this from happening?

A.

Ensured the stakeholder anticipated obstacles to achieving financial closure on the remaining funds.

B.

Ensured the risk was adequately assessed and mitigated by the appropriate stakeholders.

C.

Ensured the stakeholder who was providing additional funds remained interested in the project.

D.

Ensured the project team monitored and reviewed the project risk register periodically.

A project manager is working on a project to transform the service delivery model in the organization. As part of the scope, this project includes diverse elements that have been well defined by the product owner. The team has expressed that the scope is not clearly defined.

How should the project manager address this situation?

A.

Distribute the release plan among the team members.

B.

Ask the team members to focus only on their assignments.

C.

Ask the product owner to clarify the project's vision with the team.

D.

Meet with the product owner to validate the backlog prioritization.

A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.

What is the first step the project manager should take?

A.

Meet with the project team to forecast the SPI trend to determine if there are funds available to pay the 30 team members.

B.

Quantify the cost for the 30 team members and determine if there is budget available to fund the expanded team.

C.

Inform the project team that since the CPI is trending downward, there are funds available to expand the team.

D.

Engage with the human resources (HR) representative to begin selecting candidates for the 30 open positions.

A project manager is planning the fifth sprint of a project when the sponsor requests a report on the business value gained to date. What should the project manager show to the sponsor?

A.

The cumulative flow diagram

B.

The data of the metrics defined to track benefits

C.

The metrics plan to track benefits

D.

The fifth sprint retrospective report

During a project iteration, half of the project team was reallocated to a new project. How should the project lead handle the situation?

A.

Raise the risk of having the velocity impacted for the current iteration and discuss it with the product owner.

B.

Raise the issue with the product owner to bring additional resources to the project team.

C.

Raise the risk with the project stakeholders and wait until the velocity for the current iteration is calculated.

D.

Raise the issue with the project stakeholders to analyze the project impact and take the proper actions.

A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?

A.

Follow the requirements management process.

B.

Follow the stakeholder engagement process.

C.

Follow the risk management process.

D.

Follow the change management process.

A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.

Which three actions should the project manager take? (Choose 3)

A.

Develop the project management plan based on the requirements requested by the customer.

B.

Develop the application as requested by the customer, based on the approved project requirements.

C.

Plan a minimum viable product (MVP) to get early feedback from the customer.

D.

Facilitate a focus group to assess the functionality before development.

E.

Use an agile approach to deliver the product based on sprints.

An organization is undergoing an agile transformation and migrating most of its projects from a predictive approach. The CFO expressed a concern that predictability on both costs and scope will be lost with the new agile approach.

What should the project manager do?

A.

Provide mentoring to the CFO, who is a key stakeholder in the project, and clarify the benefits of an agile approach.

B.

Ask the CEO to intervene by asking for support from the executive board to accelerate the company's transformation.

C.

Apply influence with other key stakeholders on the board to mitigate any risks that may be generated by the CFO's position on the matter.

D.

Submit a report to all key stakeholders on the cost-benefit analysis of the new approach and detail how the company will save money.

A construction company is executing a building contract that includes firm milestones for replacing certain components of the building. During execution, the client complains that the new components do not meet the requirements.

What should the project manager have done to prevent this from happening?

A.

Defined acceptance criteria in a quality checklist agreed upon before starting the build phase

B.

Approved a detailed change management process before starting the build phase

C.

Provided compensation for issues due to the variance in the agreed-upon requirements

D.

Continuously communicated the changes in the work plan and the agreement to the client

During a weekly status update meeting with the project management office (PMO), the assigned project manager notices some stakeholders raise concerns about the implementation plan even though the status was regularly communicated to all stakeholders.

What should the project manager do?

A.

Schedule a meeting with the stakeholders to assess the root cause and update the plan.

B.

Focus on the key stakeholders first and meet with them individually to resolve their doubts and concerns.

C.

Involve stakeholders in retrospective meetings to resolve stakeholder doubts and improve communication.

D.

Ask the team to improve the communications management plan with stakeholders and add more details to their updates.

A sales director is upset that progress has been slow on the delivery of critical features to the customer. After consulting with the team, the project manager learns that a subject matter expert (SME) on the customer side is not cooperative in providing the input needed to complete the definition of ready (DoR).

What should the project manager do to avoid the same problem in future projects?

A.

Review the responsibility matrix at the customer kick-off meeting.

B.

Rely on internal SMEs for expert input on implementing the user stories.

C.

Include a contractual penalty for delays created by the customer.

D.

Require customer SMEs to attend at least half of the daily meetings.

A project manager assembled a team of 10 developers. Because the organization did not have a development team for this project, contractors were hired. In the kick-off meeting, one of the developers recommended the use of development standards. The project manager's previous team in another organization had good development guidelines.

What should the project manager do?

A.

Recommend that the team use industry-accepted guidelines.

B.

Contact the chief information officer (CIO) and request the enterprise development guidelines.

C.

Contact the previous team and ask for a copy of their guidelines.

D.

Recommend that the team develop their own guidelines.

Due to an anticipated expansion, a company procured new technology. The project team responsible for using this technology does not have experience with it.

What should the project manager do?

A.

Assess the benefit of using new technology versus old technology.

B.

Hire project resources with experience using the new technology.

C.

Propose training for the project team in batches on the new technology.

D.

Request incentives for the team to use the new technology.

In the execution phase of a project, the development team is informed by the IT security department that one of the external platforms that the team is using will be uninstalled for the whole organization.

What should the project manager do first?

A.

Escalate the issue to the change control board (CCB).

B.

Ask the project team to analyze the impact.

C.

Register the risk and document the contingency plan.

D.

Have the project team brainstorm alternatives.

A project is near completion but it is behind schedule. The contingency budget has already being used, although the remaining budget should be

enough to complete the project. The only subject matter expert (SME) assigned to the project has been asked by their manager to solve a

problem in the operations department.

What should the project manager do?

A.

Escalate the situation to the project sponsor.

B.

Free the resource to handle the operations priority.

C.

Ask the manager to submit a change request.

D.

Design a negotiation strategy for this situation.

Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.

What should the project manager do next?

A.

Discuss the topic with the team members in a team meeting.

B.

Replace the two team members with other resources.

C.

Contact the functional managers of each team member.

D.

Schedule a meeting with both team members.

A mandatory compliance requirement that will impact the project software is introduced during the execution phase of an iterative project. The team is aware of the compliance requirement.

What should the project manager do next?

A.

Update the product backlog item with this new requirement.

B.

Escalate the issue of project impact to the project sponsor.

C.

Escalate the issue of project impact to the product owner.

D.

Update the stakeholder register to include the requirement owner.

A company faces challenges and decides to cut a few product features from the main project due to market conditions. During a status meeting, a new stakeholder expresses concern about the discrepancies between the current deliverables and the deliverables agreed upon in the project charter.

What should the project manager do first?

A.

Ask the project team to increase the number of updates provided to the stakeholder.

B.

Determine the root cause of the discrepancy with the project team and agree on the project scope.

C.

Ask the new stakeholder to submit a change request to the change control board (CCB).

D.

Review the project objectives for alignment with the intended corresponding business value.

A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project

manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project

schedule. When the project manager returns, a detailed schedule is almost complete.

What should the project manager do?

A.

Ensure that the schedule is aligned with the vision and objectives.

B.

Escalate the compliance issue to the project management office (PMO).

C.

Congratulate the team and move on to the execution phase.

D.

Develop a new detailed schedule with the team and project sponsor.

A project manager just completed a successful deployment and is preparing to transition the project to an operational state before starting closeout actions. What should the project manager do to ensure that the project is ready to move to an operational state?

A.

Meet with the project team to review the work breakdown structure (WBS) and confirm deliverables have been delivered.

B.

Develop a plan to repay the technical debt incurred during the project and ensure that the project sponsor agrees with the plan.

C.

Review the project approval requirements in the project charter and confirm who will be approving the project.

D.

Refer to the project’s work in progress (WIP) reports to ensure that there is no additional work in the backlog.

A project manager is leading a project with strict time constraints. In team meetings, one of the team members is always silent. The project manager determines that this team member is not knowledgeable about the technology solution. The project manager is concerned that this problem will impact productivity.

What should the project manager do?

A.

Assign an experienced team member to work with this member on a daily basis in order to become knowledgeable about the technology.

B.

Arrange formal training for this member to gain sufficient knowledge to reduce the impact on team performance.

C.

Let this team member understand the urgency and encourage them to spend extra time to become knowledgeable about the technology.

D.

Let the team lead the meeting discussions so that every member has a chance to prepare and speak up.

At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried

to contact the consultant but has been told that the consultant does not have the time to discuss the project.

What should the project manager do to move the project forward?

A.

Escalate the issues about the consultant to the functional manager so the consultant dedicates the necessary time to the project.

B.

Include a new project risk into the risk register and allocate the consultant as the risk owner as it is their responsibility to provide input.

C.

Discuss the request with the consultant and set up time with the business analyst and consultant to discuss the project requirements.

D.

Urge the business analyst to continue contacting the consultant to discuss the project since this is the responsibility of the business analyst.

A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.

What should the project manager do first to get the team energized and performing efficiently?

A.

Seek to understand the sentiments of each team member and then work with them to address their concerns.

B.

Bring the team together on a phone call to explain the criticality of the project and the impact of schedule delays.

C.

Contact the functional manager to request a replacement for team members who are not able to meet the schedule.

D.

Begin holding daily meetings and ask each team member to share their status and demand that they remain on schedule.