A project manager is assigned to an ongoing complex project. The team is delivering value each iteration However, the deliverables are internal and the customers are unaware of the deliverables.
Which action should the project manager take?
A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.
What should the project manager do?
A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.
What should the project manager do in this situation?
On a recently completed prefect a project manager noticed that some of the subcontractors approached the client directly with questions. These subcontractors had a previous direct reporting relationship with the client. The project manager is now in the initial stage of a new project with the same subcontractors and client.
How should the project manager set up communications?
A transformation project that is composed of agile streams has come to an end.
How should the project manager collect the experience gained during this project?
A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.
What should the project manager do to have a high-performing team?
A production team will soon begin their first agile project. No one in the team or management has agile knowledge. The training manager can only fund three enrollments.
Match the team role on the left to the correct training course on the right. (Use all three of the team roles.)
An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?
A project is in the start-up phase of the project life cycle. The project team consists of 20 people from five different countries. The project team is scheduled to have quarterly face-to-face meetings. However, due to unforeseen circumstances, no face-to-face meetings can occur. The project manager is concerned that the team may not be able to fulfill their individual roles without face-to-face meetings.
What should the project manager do in this situation?
After conducting a performance assessment, the project manager identified that some gaps still exist. What should the project manager ensure?
A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will
take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6
months.
What should the project manager do to align stakeholders’ needs and expectations?
At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project manager mainly make reference to?
A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the
appropriate stakeholder participation and involvement level required for successful project delivery.
What should the project manager do?
A project for a financial organization is in the proposal phase for the selection of a software tool. There have been conflicting opinions on the software that was ranked in the selection. After analyzing the issue, the project manager realizes that two out of the eight teams have concerns about the tool's scalability to support their business needs.
How should the project manager resolve this conflict and reach a consensus?
In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums.
What should the project manager do next?
Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time.
What should the project manager do?
Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.
What should the project manager do to obtain agreement from both companies and acceptance from marketing?
A project manager is implementing a project similar to a previous one that required strict adherence to occupational health and safety (OHS). Both projects are for the same client whose business environment is highly regulated. However, this time the client does not appear to be concerned about OHS requirements.
What should the project manager do first?
A global program is being kicked off, and various distributed teams are involved in delivering the initiative. Besides planning and executing the scope for the initiative, team
interactions must be considered.
How should the project teams interact in their meetings?
In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?
A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The
resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.
What should the project manager do?
Drag the items on left side to the matching term within the correct project approach on the right side.
A project manager is performing the scrum master role for a project team of developers. At the daily standup, a couple of developers complain about the noise from a neighboring team, the performance of their laptops, and the difficulty in booking meeting rooms.
What should the project manager do?
A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?
In a hybrid project, the project manager has identified a few stakeholders. According to the stakeholder matrix, the head of development has a high rating of power/influence and a high likelihood of conflict.
Which action should the project manager avoid?
An agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team's performance is not good, and some team members want to leave the team.
How should the project manager approach this situation?
During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not convinced that the return on investment (ROI) can be achieved.
How should the project manager address this issue?
An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project
execution. The acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.
What should the project manager have done to prevent this from happening?
A project manager is working on a project to transform the service delivery model in the organization. As part of the scope, this project includes diverse elements that have been well defined by the product owner. The team has expressed that the scope is not clearly defined.
How should the project manager address this situation?
A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.
What is the first step the project manager should take?
A project manager is planning the fifth sprint of a project when the sponsor requests a report on the business value gained to date. What should the project manager show to the sponsor?
During a project iteration, half of the project team was reallocated to a new project. How should the project lead handle the situation?
A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?
A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.
Which three actions should the project manager take? (Choose 3)
An organization is undergoing an agile transformation and migrating most of its projects from a predictive approach. The CFO expressed a concern that predictability on both costs and scope will be lost with the new agile approach.
What should the project manager do?
A construction company is executing a building contract that includes firm milestones for replacing certain components of the building. During execution, the client complains that the new components do not meet the requirements.
What should the project manager have done to prevent this from happening?
During a weekly status update meeting with the project management office (PMO), the assigned project manager notices some stakeholders raise concerns about the implementation plan even though the status was regularly communicated to all stakeholders.
What should the project manager do?
A sales director is upset that progress has been slow on the delivery of critical features to the customer. After consulting with the team, the project manager learns that a subject matter expert (SME) on the customer side is not cooperative in providing the input needed to complete the definition of ready (DoR).
What should the project manager do to avoid the same problem in future projects?
A project manager assembled a team of 10 developers. Because the organization did not have a development team for this project, contractors were hired. In the kick-off meeting, one of the developers recommended the use of development standards. The project manager's previous team in another organization had good development guidelines.
What should the project manager do?
Due to an anticipated expansion, a company procured new technology. The project team responsible for using this technology does not have experience with it.
What should the project manager do?
In the execution phase of a project, the development team is informed by the IT security department that one of the external platforms that the team is using will be uninstalled for the whole organization.
What should the project manager do first?
A project is near completion but it is behind schedule. The contingency budget has already being used, although the remaining budget should be
enough to complete the project. The only subject matter expert (SME) assigned to the project has been asked by their manager to solve a
problem in the operations department.
What should the project manager do?
Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.
What should the project manager do next?
A mandatory compliance requirement that will impact the project software is introduced during the execution phase of an iterative project. The team is aware of the compliance requirement.
What should the project manager do next?
A company faces challenges and decides to cut a few product features from the main project due to market conditions. During a status meeting, a new stakeholder expresses concern about the discrepancies between the current deliverables and the deliverables agreed upon in the project charter.
What should the project manager do first?
A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project
manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project
schedule. When the project manager returns, a detailed schedule is almost complete.
What should the project manager do?
A project manager just completed a successful deployment and is preparing to transition the project to an operational state before starting closeout actions. What should the project manager do to ensure that the project is ready to move to an operational state?
A project manager is leading a project with strict time constraints. In team meetings, one of the team members is always silent. The project manager determines that this team member is not knowledgeable about the technology solution. The project manager is concerned that this problem will impact productivity.
What should the project manager do?
At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried
to contact the consultant but has been told that the consultant does not have the time to discuss the project.
What should the project manager do to move the project forward?
A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.
What should the project manager do first to get the team energized and performing efficiently?