Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

During the project planning phase, the customer explained the importance of delivering the project results proposed in the scope as soon as possible. What should the project manager do first to address this?

A.

Assess the opportunities to deliver project value incrementally

B.

Gather all the requirements’ details and schedule a refinement meeting

C.

Prepare a project management plan for the full scope using an agile approach

D.

Approve a change request to change the project approach to agile

Throughout the project, the project manager consistently checks the work performance data and finds that two stakeholders are not engaged in the project as expected. In addition, another stakeholder always complains that they are often involved in irrelevant meetings. What should the project manager do first?

A.

Communicate regularly with stakeholders and address issues.

B.

Perform a root cause analysis using the Ishikawa method.

C.

Review and update the stakeholder engagement plan.

D.

Remove those stakeholders from unwanted meetings.

A project is in its fourth iteration out of eight with a delivery performance of 95%. A project stakeholder asks the project manager about the status of a specific deliverable not visible in the status report. What should the project manager do?

A.

Include the deliverable in the status report and resend it to the stakeholder

B.

Invite the stakeholder to the next iteration review

C.

Invite the stakeholder to the next daily meeting

D.

Schedule a meeting with the stakeholder to review the status report

In a fixed time and budget project, the customer wants development of a core component to be based on agile practices because the final scope has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact project profitability. Which two controls should the project manager incorporate into the contract to address development of the core component? (Choose 2)

A.

Establish a governance committee to review contract delivery

B.

Require that only internal resources be utilized for this project

C.

Provide alternatives to scope change at specific project phases within the contract

D.

Tier the contract for fixed and agile components

E.

Limit the number of iterations for development in the contract

Shipping problems are impacting the supply chain worldwide, and the project's primary vendor has indicated potential delays in supplying certain equipment that will be ordered later in the project. What should the project manager do with this information?

A.

Note the information but refrain from recording it as an issue because the project has not yet placed the order.

B.

Request the procurement team to find another vendor that has available stock of this equipment.

C.

Update the risk and continue to monitor developments by keeping in touch with the vendor.

D.

Request the vendor to provide specific information about the delivery delays before taking any action.

A new project manager is taking over a project to deliver a new payroll management system that is running behind schedule. In addition, costs are rising due to many late changes requested by the client. What should the project manager do first?

A.

Schedule a meeting with stakeholders and explain the situation.

B.

Discuss the situation with the sponsor and seek their guidance.

C.

Arrange a time to meet with the team to understand the parameters.

D.

Meet with the team to understand the areas of concern.

A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches The scope of the project contains a number of unclear requirements.

How should the project manager plan the delivery of the project?

A.

Wait for the requirements to be more clear before any further action is taken on the project

B.

Ignore the unclear requirements and focus on the delivery plan of the project

C.

Escalate the issue of unclear requirements to the management team and wait for final authorization

D.

Break down the requirements and prioritize the requirements into iterative work packages

A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed. What should the project manager do to deliver business value to the client?

A.

Use management reserve and crash the schedule

B.

Implement an agile project delivery approach

C.

Explain the need to follow the quality assurance (QA) schedule to the customer

D.

Adopt an incremental project delivery approach

A project lead accepted an assignment for a project that is still in the feasibility study phase. There are many uncertainties about project specifications, including poor alignment among the project sponsors on the final targets of the project. Which approach should the project lead choose to deliver business value?

A.

Subdivide project tasks to find the minimum viable product (MVP)

B.

Identify and communicate clear risk mitigation plans

C.

Recommend predictive project management to the sponsors

D.

Ensure commitment from sponsors on executing the project until it ends

A new stakeholder is unaware of the existence of the project a few weeks before the final deliverable and project completion. What should the project manager do first?

A.

Escalate this issue to the project sponsor.

B.

Communicate the full details of the project activities to the stakeholder and solicit input.

C.

Analyze this stakeholder’s interest and impact.

D.

Share the summary of the project activities with the stakeholder and conclude the project.

A team identifies a critical set of tasks that have not been included in the Kanban board, and there is not enough budget for the work hours needed to complete the activities. What solution should the agile project manager implement?

A.

Review alternatives with the product owner and agile team.

B.

Involve stakeholders and ask them to descope some features.

C.

Ask the sponsor for additional resources to hold the schedule.

D.

Increase productivity and modify the schedule as needed.

A project manager has been tasked with developing a project schedule with fully detailed requirements. The project manager reaches out to subject matter experts (SMEs) for their initial thoughts on task duration. The project manager is concerned when these estimates appear to differ significantly. What should the project manager do to help with the estimate development?

A.

Ask the SMEs to hold up cards that show their estimate, discuss the highest and lowest estimates, and then estimate again.

B.

Recommend using an iterative approach, with a focus on estimates, that the SMEs agree with.

C.

Use historical information to help guide the estimates that were proposed by the SMEs.

D.

Escalate to the project sponsor and explain the differences in the estimations coming from the SMEs.

A project manager has been assigned to a project. The project deadline has been established but, based on the number of stakeholders to engage and interview, it will be difficult to complete the project within the timeline. How should the project manager address this challenge?

A.

Commit to completing the deliverables associated with only the engaged parties.

B.

Submit a change request to extend the time needed to engage all of the parties.

C.

Request that the product owner define which parties should be engaged first.

D.

Prioritize the engagement of parties who are most impacted to minimize project risk.

Two days before the end of a sprint, a team member updates the team lead that they will not be able to complete their tasks for the sprint due to a technical difficulty. What should the agile team lead do?

A.

Inform the product owner of the issue and request that they reprioritize the delayed task.

B.

Suggest the team member get more technical training in the next quarter.

C.

Update the risk register to reflect the possible risk of a schedule delay.

D.

Raise this issue during the daily meeting to determine a possible solution with the team.

A project manager is leading a complex project. The team is being challenged with frequent, incremental, and uncontrolled changes to the project. What should the project manager do?

A.

Establish a detailed quality management plan.

B.

Establish a detailed risk management plan.

C.

Establish a detailed scope management plan.

D.

Establish a detailed schedule management plan.

A project manager is leading a hybrid project. A project team member has not been delivering on time; as a result, the project is about to be delayed. What should the project manager do?

A.

Revise the project schedule with the customer

B.

Schedule a meeting with the project team to address timelines

C.

Negotiate revised timelines with the project sponsor

D.

Discuss the situation with the project team member

A new team member joins the project and fails to apply the project-specific quality assurance (QA) processes. What should the project manager have done to avoid this issue?

A.

Obtained external training in QA for the new team member

B.

Delegated QA tasks to the team lead

C.

Made sure the new team member understood all requirements

D.

Ensured the new team member had access to the quality management plan

A project sponsor is upset that a vital project might miss an agreed-upon delivery deadline. The sponsor asks the project manager to check whether the project team can do anything to deliver on time. What should the project manager do first?

A.

Increase project team resources to maintain the timeline

B.

Conduct simulations to determine the best way forward to ensure timely delivery

C.

Reduce scope to deliver on time

D.

Work with the team to ensure the project is delivered on time

An increment was delivered to the customer at the end of a sprint. The customer complains that the product does not meet the expected quality and will require some rework. What should the project manager do next?

A.

Review the evidence of the quality assurance (QA) activities performed.

B.

Perform an analysis of the impact caused by the required rework.

C.

Include time in the next increment for quality assurance (QA) inspections.

D.

Confirm with the customer the expected quality in the next increment.

A project manager is leading a complex project with stakeholders from different countries, cultures, and languages. What can the project manager do to manage this diverse group of stakeholders?

A.

Assign team members to deliverables according to their cultures and languages

B.

Ask the PMO to assign a cultural manager to oversee relations between diverse groups

C.

Perform an analysis to better understand the communication needs and preferences of each group

D.

Establish one language as the main language for communications and one official time zone for the project

An experienced project manager has recently joined a troubled project. The project is impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot switch vendors, and the project must be completed within a maximum of 90 days as agreed. What should the project manager do?

A.

Request the vendor to provide the servers on time as penalties may be applied

B.

Wait until the project deadline is reached in order to use contingency funds

C.

Reach out to the vendor to determine a plan to get the project back on track

D.

Review lessons learned from previous projects and take action accordingly

During the requirements gathering and analysis stage for the project, the team members are debating some functionality issues that are expected to be included in the scope. Due to this discussion, the planning activity for the scope definition is running late. What should the project manager do?

A.

Timebox the team members’ debate to ensure the activity is completed on time.

B.

Review expectations with all team members who are working on this activity.

C.

Discuss the issue with the team members who are delaying the activity.

D.

Ask team members to document all points that will need to be refined later.

After a project review meeting, a key stakeholder tells another stakeholder they do not trust the project status report. The second stakeholder approaches the project manager and mentions the conversation. What should the project manager do?

A.

Request the sponsor ask the key stakeholder to be attentive during the project review meeting

B.

Schedule a meeting with the key stakeholder to address the issue and obtain direct feedback

C.

Email the status report to all stakeholders and ask them to review and provide feedback

D.

Present the status report in a chart and assume everyone understands the report

A project manager is in the beginning stages of delivering a project and is assessing and prioritizing identified risks. What should the project manager do next?

A.

Plan the risk responses and assign risk response owners.

B.

Start monitoring and controlling the identified risks.

C.

Proceed with executing the risk management plan.

D.

Spend the contingency budget on the identified risks.

A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received demanding the project be stopped. What should the project manager do first?

A.

Meet with project stakeholders to define a mitigation plan

B.

Register the issue and escalate it to the project sponsor

C.

Estimate the cost of changing the project location

D.

Execute the contingency plan defined in the risk management plan

A project manager has recently been assigned to a construction project. The project has hundreds of stakeholders and three stages. The project manager recognizes that many steps have already been started, including risk identification. The project sponsor asks the project manager to rank the risks contained in the register. How should the project manager respond to the request?

A.

Execute a qualitative analysis to provide identified risks prioritization.

B.

Inform that a quantitative risk prioritization was completed using Monte Carlo simulation.

C.

Inform that a qualitative analysis has already been completed.

D.

Perform a quantitative analysis to provide identified risks prioritization.

A project team completed sprint planning, but at the end of the session the project lead receives a message from a stakeholder about a legislative change that requires a new validation rule in one backlog item committed for the sprint. What should the project lead do?

A.

Remove the current backlog item from the sprint and replace it with defect fixing

B.

Remove the current backlog item from the sprint and replace it with a similar item

C.

Update the backlog and advise the team to add this to the acceptance criteria

D.

Update the product backlog and include the change as a high priority for the next iteration

A project is in its first of six iterations. The project team realizes that a key deliverable is dependent on the acquisition of a new device. The vendor is new to the organization and does not have a long history in the market. What should the project manager do first?

A.

Register the risk and provide appropriate response options.

B.

Register the risk and prioritize the implementation strategy.

C.

Register the risk and escalate it to the procurement team.

D.

Register the risk and escalate it to the project sponsor.

A company started a project to create a new product that will be delivered in iterations. The artwork development plan included extensive consultation and validation before the build. The company changed the focus of the project to speed to market because one of their competitors announced the launch of a similar product. What should the project lead do?

A.

Work with the product owner to assess the impact and reprioritize the product backlog.

B.

Schedule a meeting with the project sponsor to identify and allocate additional resources.

C.

Submit a formal change request and obtain approval from the change control board (CCB).

D.

Meet with the Scrum Master to determine if the development cycle can be reduced.

A project manager is struggling to provide timely updates to the project team due to team members being spread across multiple time zones. Which communications method should the project manager utilize in this situation?

A.

Interactive communication

B.

Public communication

C.

Pull communication

D.

Push communication

A project has a schedule performance index (SPI) of 0.75 and a cost performance index (CPI) of 1.1. As a result, the project manager is considering either fast-tracking or crashing the project schedule to bring the project back on track again. What could be a secondary result of these actions?

A.

A decrease in the project cost

B.

An increase in the project risk

C.

Additional project scope

D.

Additional resources

One of the main deliverables of a project is delayed due to a problem with a key provider. What should the project manager do?

A.

Create a change request to replace the provider with a more responsible one from the provider list

B.

Schedule a meeting with all relevant stakeholders to determine the best approach to resolve the issue

C.

Discuss with the sponsor and seek guidance to impose the penalty stipulated in the agreement

D.

Schedule a meeting with the provider to review impacts to the project timeline and deliverables

During a status meeting, a project manager reported that a project is on track. However, the project sponsor thinks the project is behind schedule because a few tasks have already passed their planned finish dates but are still in progress. How should the project manager revise the report and demonstrate the project is on schedule?

A.

Use a network diagram to show that the delayed tasks are not on the critical path.

B.

Use a network diagram to show the task duration and dependencies among tasks.

C.

Use a Gantt chart to compare the actual schedule with the planned project schedule.

D.

Use a resource histogram to show that the resources are adequate to complete all tasks on time.

A product is facing performance issues that will significantly decrease the manufacturing yield expected, increasing the cost. This will be an issue as it will limit one of the high-margin contracted goals. Because it is a breakthrough development, the speed to market is key. What should the project manager do?

A.

Negotiate with operations to absorb the cost while the product is launched and remediate the issue.

B.

Engage with the sales team to increase the sales price since it is a breakthrough product.

C.

Evaluate the most cost-effective containment action and use their influence to implement it.

D.

Assess what corrective action is appropriate and use their influence to implement it.

A new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company’s biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately. How should the project manager approach the software development life cycle with this customer?

A.

Assign a business analyst to build detailed requirements so the project manager can estimate the project duration

B.

Explain that the team will build a production prototype model to help the customer visualize how the features should work

C.

Add extra time and resources to the estimating phase to accommodate the lack of requirements

D.

Raise a risk that scoping and estimating will be delayed if the customer cannot approve requirements

After finishing the planning session for a new project, the team agrees that the project duration needs to be 12 months. However, the project sponsor asks to release the product before the end of the project. What should the project manager do first?

A.

Update the risk register and escalate it to the sponsor

B.

Assist the team in proposing a minimum viable product (MVP)

C.

Request the stakeholders to reduce the project backlog to finish on time

D.

Ask to increase the capacity of the team to deliver the project on time

A project to develop a new service is initiated by a telecommunications operator. The project management plan was developed, approved, and shared with respective stakeholders. What should the project manager do next?

A.

Define deliverables, activities, and scheduling information.

B.

Estimate activity durations and list resource requirements.

C.

Incorporate the project's scope baseline in the scope statement.

D.

Start execution of the work packages according to the plan.

A project is being planned with two hardware deliverables and one software deliverable that will be used to monitor the operation of the two hardware deliverables. When preparing the consolidated project schedule, what should be the top priority for the project manager?

A.

The interdependencies between the deliverables

B.

The business continuity plan of the deliverables

C.

The stakeholder engagement plan

D.

The user stories and story points

A project manager is leading a software development project with agile practices and has outsourced work to three well-qualified subcontractors. Over time, problems arise related to supply-chain management, and the project manager considers replacing the subcontractors with new suppliers. What should the project manager have done to avoid this problem?

A.

Hired more Scrum Masters so every Scrum Master manages one supplier.

B.

Escalated the issue to the product owner to seek possible solutions.

C.

Engaged the suppliers by category and validated the strategy with stakeholders.

D.

Created user stories for the suppliers and saved their qualification records to the backlog.

A project to develop an enterprise resource planning (ERP) system for a university is ongoing. The system should improve business processes through digitalization and elimination of human errors, and also provide end users with simplified and easily accessible services. What should the project manager do to ensure achievement of the intended business value?

A.

Evaluate each change request and review the business case each time

B.

Evaluate deliverables against the business case continuously

C.

Evaluate deliverables against the business case at the end of the life cycle

D.

Evaluate customer feedback and review the business case each time

During the initial phase of a construction project, the team is confused about the safety requirements it needs to consider during implementation. The project manager recently met with the client to define the project scope. How should the project manager share this information?

A.

Distribute the safety requirements during the project execution phase

B.

Modify the project charter by including the safety requirements

C.

Send an email to the team with the details of the safety requirements

D.

Meet with the team and present the scope of the safety requirements

A project manager is leading a project and is asked to negotiate on behalf of their organization. The organization requires that three quotes from different suppliers be acquired prior to submitting a purchase request to the finance department. What should the project manager do to align with this requirement?

A.

Perform a make-or-buy analysis

B.

Review the statement of work (SOW)

C.

Leverage the enterprise environmental factors (EEFs)

D.

Refer to the organizational process assets (OPAs)

A complex project is being developed in phases as per the original plan. Half of the systems have been handed over to the customer for operational use. There is no delay in the schedule. However, the customer is still not happy because some of the systems handed over are no longer useful due to changes in the environment. What should the project manager have done to avoid this?

A.

Asked the customer to participate in project status meetings to better understand the progress

B.

Informed the project team to closely monitor the deliverables and keep the customer informed

C.

Reviewed benefits realization with the customer regularly and constantly aligned expectations

D.

Explained to the customer that the project is in good shape as the system is operational

A project manager presents the project schedule to the customer, including the detailed phases for the whole project. The customer complains that the project timeline is longer than expected and does not want to wait until the end to see results. What should the project manager do first?

A.

Adjust the project schedule to include additional resources for all project tasks.

B.

Submit a change request to extend the project timeline.

C.

Evaluate the impact of changing the project framework to an incremental approach.

D.

Apply crashing techniques to all activities in the project schedule.

The execution stage of a construction project is beginning. There are many areas and phases to be built. The project team wants to review the relationships between the most important tasks to ensure that major items are executed properly during this stage. What project artifact should the project manager review with the team?

A.

Project milestone chart

B.

Project schedule management plan

C.

Project statement of work (SOW)

D.

Project program evaluation review technique (PERT)

A project manager is assigned to an IT project to deliver a new accounting system. Some managers at the company do not see the value of this project and say they will not use the new system. What two actions should the project manager take? (Choose 2)

A.

Review the list of stakeholders that will be affected by starting this business initiative.

B.

Continue with the project the way it was planned and validated by the sponsor.

C.

Describe the outcome of the project and business value to all company stakeholders.

D.

Add this issue to the risk register and monitor stakeholder engagement at the next milestone.

E.

Modify the project management plan and scope of work to avoid future difficulties.

An organization is about to start a time-critical project and has decided to use an agile approach for the first time. However, stakeholders are worried they will not be able to verify project status because they believe their usual governance model will not work for an agile project. What should the project manager do?

A.

Discuss using a hybrid governance structure with stakeholders

B.

Meet with stakeholders to discuss and review the governance structure

C.

Recommend following the existing governance structure with the project team

D.

Review the governance structure to reflect scope changes

An organization that is running several simultaneous projects suddenly experiences a surge of resignations, leading to a lack of talent. Consequently, some of the projects have been missing key milestones. What should the project manager do to recover from the delays?

A.

Reduce the projects’ scope to meet the upcoming target dates.

B.

Crash the schedule from the delayed projects to meet upcoming target dates.

C.

Fast-track the delayed projects so they can meet upcoming target dates.

D.

Ask for project sponsor approval to revise the upcoming target dates.

A project manager has been informed by a vendor that a shipment with supplies needed for the project will be delayed by six weeks. What should the project manager do first?

A.

Find another vendor to deliver the required supplies on time

B.

Ask the procurement manager to resolve the issue with the vendor

C.

Document this as a risk and define a risk response plan

D.

Treat the risk as an issue and launch the risk response plan

A project manager is leading a contract for a new market that was awarded to their company. The client has the desire to jump-start the market with informal sector traders. What should the project manager do?

A.

Plan the project in phases, starting with the informal sector, to deliver business value quickly

B.

Divide the project team into groups to execute as small parallel projects, including the informal sector

C.

Gather requirements and convert them into backlog items to quickly deliver value

D.

Execute the projects simultaneously following the project schedule and the communications management plan