A project manager assigned to an agile project realizes that after iteration demos, new user stories to fix issues reported by the product owner are not included in prioritization of the following sprint. This has led to a high number of unprioritized stories in the backlog and will lead to delay of the product release.
What should the project manager do?
A project team has difficulty understanding the relationship between functional requirements and their associated benefit to the business stakeholders.
How should the project manager improve the team's understanding?
In an organizational upper-level management meeting, the CEO shows interest in a project of which they were not previously aware. After the meeting, what should the project manager do to ensure the CEO's support?
A project team is struggling to meet the project deadline due to a reoccurring conflict between two team members. What should the project manager do?
A project team consisting of 13 people was set up three months ago. As part of the transition to agile, a scrum master was assigned to the project. The scrum master wants to know the status of the team's development stage. The project manager believes that the team has passed the "storming" stage.
Which indicators should be used to determine the team's development stage?
A project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.
What should the project manager do to address this concern?
During a meeting with the customer, it was observed that the features delivered during the last few iterations were not meeting the planned expectations.
What should the project manager do?
A functional team member often becomes disruptive during status meetings and attempts to derail progress with the key stakeholders. This team member often discusses why the project will not be successful.
What should the project manager do?
A global and complex project is in the execution phase. Recently, there were executive board changes, and the executive sponsor is transitioning to a new role. The outgoing sponsor asked the project manager to speed up project completion of the current phase to ensure successful onboarding of the new sponsor.
What should the project manager do?
An organization is implementing a solar power system at its production plant. During the execution phase, one of the key stakeholders noticed and communicated that authorities are developing solar power regulation, which might impact the overall feasibility of the project.
What should the project manager do first?
A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.
What should the project manager do first to get the team energized and performing efficiently?
A virtual product development team is working well together and is on schedule. One team member wants to take 1 week off to attend a training.
What should the project manager do?
A project manager's project relies on services from a department that has a new leader. Since the new leader was appointed, the services from their department have been slow which threatens the project's delivery deadline.
What should the project manager do?
A project manager of an infrastructure development project receives multiple issues from the customer validation team close to the product launch date.
What should the project manager do to manage such a situation for upcoming phases?
During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.
How should the project manager properly address this situation?
A project manager is in the middle of executing the construction of a high-rise plaza when the government regulatory agency announces an increase in the price of fuel. The project still has seven months left on the schedule.
What should the project manager do first?
A project team has not been meeting its deliverables because they are not receiving adequate resources to do their job. What should the project manager do for the team to meet the upcoming deliverables?
A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.
What should the project manager do next?
A multinational company is embarking on an ambitious organizational change project. The objectives of the project include the complete transformation of the organization's structure, role catalog, and global locations in which supporting services are to be delivered.
What should the project manager advise as an essential component of the project?
To ensure effective team communication and processes, a standard set of software including video conferencing is defined for a virtual scrum team. Several team members are reporting problems with their access and cannot adhere to team processes.
How should these issues be resolved?
A project is starting with a team that is located all over the world. None of the team members have worked together before. The project goal is ambitious with an aggressive timeline.
What should the project manager do?
A project feature from the development team was rejected due to low quality. Over the past few weeks, the testing team has become concerned because the development team has not yet responded to the rejection. As a result, the testing team has escalated the conflict to the project manager.
What should the project manager do?
A strategic project using international funds for a government agency is going through the execution phase. The government transition will take place in 1 month, and authorities will change. There is a risk that the project will be suspended or team members will be removed. The project manager wants to ensure that the project will continue despite these changes.
Which action should the project manager take to address this situation?
During a project's stakeholder identification stage, team members are struggling to identify the level of influence for two stakeholders. One is considered important, while the second is not quite as important as the first one. For this project, stakeholder engagement is a critical activity.
What should the project manager do?
During project planning activities, a project manager identifies potential delays in obtaining resources required for a project. This will significantly impact the construction timeline.
What should the project manager do?
A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.
What should the project manager do?
Following an investment decision-making meeting for a project, a change to the organizational structure takes place in a multinational company. Due to the organizational change, internal stakeholders are referring the project manager to various other personnel for approval of the project budget.
What should the project manager do to obtain approval of the project budget?
A project manager is leading a large-scale project to be deployed in another country, for an external company. After working with the project team, the project manager learns there are many stakeholders from the project manager's organization, the client organization, and the local community.
What should the project manager do after identifying the stakeholders?
A project manager was appointed to lead an already approved project. While reviewing the benefits management plan, the project manager finds out that the information about the forecasted value of the project may not be accurate.
What should the project manager do?
Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.
Which three actions should the project manager do? (Choose 3)
A project leader is preparing to facilitate a sprint retrospective. The sales manager sends the project leader an email asking how a feature planned for the next shipment is being implemented.
What should the project leader do next?
A new project manager has been assigned to an ongoing project because of the promotion of their predecessor. The new project manager needs to understand the levels of decision-making authority on the team.
Which document should the incoming project manager review?
A project team has experienced deliverable delays in the last few iterations. During the retrospective, the team realizes that the quality issues identified are because the quality process is outdated.
Who should the project manager ask to update the process?
Due to scope changes, some of the risks identified during the initiation phase have materialized into issues. What should the project manager do next?
A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.
What should the project manager of the contracting company do?
A project manager is facilitating an iteration retrospective. The iteration did not go well and the committed functionality was not delivered to users. The project involves a vendor team for the build and an internal quality assurance (QA) team. In the past, there were tensions between the vendor and the internal team.
What should the project manager do?
A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.
Which tool should the project manager use for this purpose?
A project manager has developed a communications management plan. A junior team member asks why they are duplicating efforts by producing different versions of the same newsletter.
How should the project manager respond?
A newly assigned team member immediately begins questioning operating procedures. This new team member wants the team to follow operating procedures that the team member had used previously. During assignments, the new team member begins using some of those processes and procedures and suggests these practices to other team members.
What action should the project manager take?
A project manager with agile experience is part of an organization that is transitioning to agile. The project manager was assigned to the first agile project by the project management office (PMO). The PMO manager asked the project manager if an existing governance from a previous project would be suitable to use in the current agile project.
How should the project manager respond?
A project manager is managing a project that will engage resources from multiple countries in different time zones. What should the project manager do to ensure that team members are effective?
A project team needs to create artifacts for an upcoming steering committee.
What should the project manager do first?
The project team members have finalized the technical specifications after their discussion with the machine manufacturers. However, it has been identified that the specifications are not aligned with the project management office (PMO). The project team members are confident about their choice of specifications.
What should the project manager do in this situation?
A new project manager took over a project that has been ongoing for a while. Some project team members are not clear on when the project will end and feel the project has already transitioned into business as usual.
What should the new project manager do first?
An agile project is completing its second sprint and products are being finished. However, two groups with different levels of expertise disagree on the backlog priority.
What should the project manager do first to resolve this dispute?
A project manager leads an agile development project. During the sprint planning meeting, the development team expresses concerns that the proposed scope of the next sprint is much larger than expected given the current resource allocation. The project manager believes the scope is essential to meet the project milestones.
How should the project manager approach negotiating an agreement with the team to ensure the project remains on track?
A project lead with a strong technical background oversees a project using agile delivery. The product owner asked the project lead to assist with ensuring the benefits of functionality that are built in the sprint are tracked.
What should the project lead advise?
A project manager has been assigned to a new project. The project sponsor has requested a detailed time line, but the project includes some deliverables that are not yet clearly defined.
Which project management approach should the project manager advise using?
A virtual project team has members located on four continents. The project director is concerned about the declining motivational levels of team members and feelings of noninclusion by other team members. The project director has tasked the project manager with finding a solution.
What should the project manager do?
The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?