A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline
What two actions should the project manager take'? (Choose two)
A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain
What should the project manager do now?
In a hybrid project, the customer decided on a major change for the project design. This change was approved and the impact on schedule and budget is known The software team leader, who is supposed to develop the software, refuses to commit to delivery dates claiming that they work using an agile approach and cannot commit to a final delivery date The hardware team depends on this software to develop their part of the product
What should the project manager do?
A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented
What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?
Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members
What should the project manager do?
A high-performing team member’s performance has been consistently increasing over the past year, leaving other peers behind The project manager has been reluctant to publicly recognize the team member’s contributions for fear of discouraging others The project manager is also concerned that the team member may leave if not rewarded for the contributions made.
What should the project manager do?
The project sponsor on an agile project informed the project lead that an executive would like an update on the project’s progress What should the project lead do?
After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)
A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint
What should the project manager have done to avoid this situation?
The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action
What two actions should the project manager take'? (Choose two)
Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated'?
During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?
A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts
What should the project manager do next?
A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed.
Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two)
The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members' performance The project manager wants to understand the situation and provide feedback to the team as soon as possible
What three actions should the project manager take to address this situation? (Choose three)
A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.
Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck

During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?
Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?
The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project.
What does that project manager need to do to make the team work in a collaborative way?
The project manager has observed that two team members have been arguing with each other openly at meetings To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members
What two actions should project manager take? (Choose two)
One of a project manager’s team members is continuously improving This team member has been a role model and mentor to others in the organization
How should the project manager acknowledge this team member’s commitment?
A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right

A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?
A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?
A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?
One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager's concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate
What interpersonal skill did the project manager use?
The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements
How should the project manager address this situation?
A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing
What should the project manager review?
A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year
Which project approach suits the scenario?
The customer's project manager changes during the final stage of a project How can the project manager avoid a project closure delay’
In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict
How should the project manager resolve the problem?
During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?
A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using
What should the project manager have done to avoid this issue?
After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session
What should the project manager do first?
To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations
What should the project manager do?
The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>
What should the project manager do?
A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks.
What should the project manager do?
Drag the to the correct scenario on the right

In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.
What should the project manager do next1?
A key stakeholder asks the project manager to complete all deliverables sooner than the agreed-upon schedule. The project is halfway complete and currently has a schedule performance index (SPI) of 0.9 and a cost performance index (CPI) of 1. What should the project manager do first before committing to the stakeholder?
A product owner asks a project manager for details about products that were added during the last iteration. What should the project manager do to gather this information and send it to the product owner?
A project manager is assigned to a large complex project with cross-functional dependencies. The project enters a new phase requiring new stakeholders to be added with conflicting priorities. How should the project manager ensure successful engagement with the stakeholders?
A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams
What should the project manager do?
A project team has deployed an email marketing campaign across different countries. In one country, the end users have been opting out of the campaign because they think the email is spam. What should the project manager do first?
How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?
A project manager finished reviewing the project deliverables for the current iteration with the customer A new key stakeholder who just joined the customer's team, complains that the results do not provide the capabilities the business anticipated
What should the project manager do to address this issue?
A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery
Which two actions should the project manager take to mitigate this risk? (Choose two)
A project manager is leading a highly visible project initiative. A few weeks after kickoff, the project manager starts receiving requests for updates from various stakeholders. What should the project manager do?
An ongoing project is facing a challenging situation where the customer is not satisfied. The team is new to agile development and frequently communicates with the customer and gives regular status reports. What should the project lead do to satisfy the customer?
A project manager is leading a project with a negative risk that has just become an issue. The risk was recorded and a response plan was set. However, a project team member proposes a response that differs from the response recorded in the risk management plan and believes it will be cheaper and equally effective. What should the project manager do?


