Pre-Summer Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

An agile leader notices that one team member consistently fails to complete the deliverables on time The agile leader suspects that this team member does not have the proper training.

What should the agile leader do?

A.

Reassign the task to another team member and require the team member to complete training

B.

Use the retrospective meeting to remind the entire team that they must complete all deliverables in each sprint

C.

Review the definition of done (DoD) with the team so that everyone understands what the team must deliver in this sprint.

D.

Speak directly with the team member about improvements and commit to an agreed-upon time frame.

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?

A.

Held a touchpoint with marketing before the demo to discuss any impediments

B.

Scheduled a demo presentation of the product during the first reason

C.

Asked the marketing team to start working on the product immediately

D.

Confirmed marketing requirements and constraints when adding to the backlog

During the executing phase, a project manager is reviewing the issue log and finds

there are outstanding high-priority issues that are still open. Most of the open issues require

effort from external domain experts who are not on the project team.

What should the project manager do?

A.

Ask the issue reporter to close the issues, because there are no project team memberswho have the required domain knowledge.

B.

Review the open issues with the issue reporter and issue a change request to hire anexternal domain expert.

C.

Request that the project team members learn the required domain knowledge andresolve the open issues in a short time.

D.

Reduce the project scope to ensure that the project team has the knowledge to deliverthe system on schedule.

A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team's integration leads is a subject matter expert (SME) m this integration area. The other team's integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?

A.

Assign the resolution of the issue to the senior integration lead who has worked on the project longer

B.

Meet with both integration leads to understand the root cause and determine a resolution

C.

Escalate the issue to the program architect who developed the integration plan

D.

Assign the resolution of this issue to the integration lead who is a SME

A project team is executing a project to replace an existing system with a new one.

A new project manager has been hired and observes that the team consist of professionals

who have worked with the older system, and others who have little previous experience.

What should the project manager do to ensure project success?

A.

Request a performance assessment for the team from the functional manager.

B.

Evaluate the current effectiveness of the team and define development needs.

C.

Allow each team member to use their individual strengths for project success.

D.

Assign team member roles and responsibilities based on past experience.

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

A.

Communicate the task assignments to the team members in a clear manner.

B.

Verify that the product owner has made the task assignments clear.

C.

Confirm that the agile coach has made the task assignments clear.

D.

Verify that the team members have made the task assignments clear.

A new project manager is managing a hybrid project. The project manager wants to be

a servant leader to support the team by removing impediments but is not receiving feedback

from the team about the issues and risks they are facing.

What should the project manager do?

A.

Implement daily standups where the team can share their impediments, risks, andissues.

B.

Review the communications management plan and implement changes.

C.

Schedule weekly risk review meetings with the team to review project risks andconcerns.

D.

Distribute a copy of the communications management plan to the scrum master.

A project leader is assigned to a new project and is asked to assemble an effective

five-member agile team. If the project leader has no restrictions, which team should they

choose?

A.

A team whose members work independently and are the best subject matter experts(SMES)

B.

A team whose members have more general aptitudes but like to work individually

C.

A team whose members have different skill sets and are spread out geographically

D.

A team whose members have more general aptitudes and can collaborate on different tasks

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.

What should the project manager do first?

A.

Perform an impact analysis with subject matter experts (SMEs).

B.

Inform the government representative about the impact of the separate project.

C.

Implement a change request to increase the budget and schedule.

D.

Consult and update the risk register with the project stakeholders.

A newly appointed product owner is working with a project team that is using agile

for the first time. The product owner is constantly disrupting various team members throughout

the day to discuss progress. This has resulted in the team feeling micromanaged and

frustrated because of the constant disruptions.

How should the project manager proceed?

A.

Invite the product owner to attend daily standup meetings so they can assessprogress.

B.

Set up a feedback session with the product owner once a week so they can assessprogress.

C.

Instruct the team to refer the product owner to the project manager for information.

D.

Invite the product owner's functional manager to a feedback session to escalate theissue.

An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach What factor should the project manager consider when determining if the project is suitable for an agile approach?

A.

The project is an information technology project and has minimal impact to the organization

B.

The project scope can be decomposed into smaller parts, the first representing a minimum viable product (MVP).

C.

The project scope is well defined and the requirements are prioritized

D.

The project team has a colocated space and is capable of working together

A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages. This difficulty leads to missed deadlines.

What should the project manager do to enhance project team effectiveness?

A.

Implement team colocation to improve communication.

B.

Identify the root cause of communication issues

C.

Initiate daily communication of project progress

D.

Schedule a communications control board meeting

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

A.

Instruct the team to work as planned and Ignore the stakeholder's requests.

B.

Escalate the situation to upper management.

C.

Add more team members to make up for any project delays.

D.

Address the issue with the stakeholder and explain the situation.

A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project

How should the project manager report this cost?

A.

Estimate user story points and forecast a budget for that deliverable

B.

Determine the control accounts and use a top bottom estimate

C.

Consider the cost performance index (CPl) based on earned value (EV) divided by costs

D.

Calculate the budget at completion (BAC) based on the completed and planned features

A hybrid project team is working on an upgraded version of software for their

product owner. The team is also responsible for supporting the existing product and

customers. For the last three sprints, the team had to stop their project work and focus on

major support items for the product owner. The testers are struggling to cope with the

constant changes to the plan, which has resulted in a number of emotional outbursts.

How should the project manager proceed?

A.

Request a replacement for those team members who are unhappy with this way ofworking.

B.

Schedule a session with the product owner to explain that no support items can betaken into the sprints going forward.

C.

Ask human resources (HR) to send the team members to a change managementworkshop.

D.

Schedule a session with the team to discuss the issues and work with them to define aplan to manage the sprints going forward.

During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.

What should the project manager do next in this situation?

A.

Review the project scope and negotiate with the contractor

B.

Refuse the offer as it is included in the initial project scope

C.

Review the project costs and communicate this to the project sponsor

D.

Submit a change request to approve the offer

During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.

What should the project manager do next?

A.

Discuss approval of the change request in the next project meeting

B.

Perform a risk assessment on the required change request.

C.

Evaluate the change request against the project scope statement

D.

Ask the sponsor for more funds to cover the change request

A project manager is working on a large event and developing budgets for sign-off. The stakeholders and project sponsor are all working remotely using various tools to ensure that all documentation is tracked and handled discretely and appropriately. The primary stakeholder has missed several deadlines for the milestone sign-offs, resulting in the project manager being forced to find alternative suppliers for items, now at higher costs. When questioned regarding the delays, the stakeholder says the notifications hadn’t appeared in their email inbox. How should the project manager proceed?

A.

Escalate the issue to the IT department and request they check the software on the stakeholder's computer.

B.

Request human resources (HR) intervene and send the stakeholder to appropriate technical training.

C.

Assess whether the communications channels are appropriate for the primary stakeholder and amend accordingly.

D.

Request the primary stakeholder be replaced to avoid any more delays and budget issues.

A project lead conducted coordination meetings to estimate the budget and confirm the timeframe for a new project. Due to internal resource challenges, outsourcing some activities could be implemented during execution. What should the project lead ensure before submitting the project for a stage gate review to receive the needed investment?

A.

Add a percentage for management reserve

B.

Conduct a retrospective with all involved stakeholders

C.

Initiate a recruitment plan to explore the market situation

D.

Align with relevant stakeholders on the procurement strategy

A project manager is having difficulty acquiring final acceptance of some deliverables from a stakeholder for reasons that seem to be outside of the project acceptance criteria. What should the project manager do?

A.

Persuade this stakeholder using emotional intelligence skills to obtain acceptance.

B.

Obtain final acceptance from another stakeholder who is also familiar with the project

C.

Escalate this issue to the project sponsor and ask for support in obtaining final stakeholder acceptance.

D.

Create a project acceptance waiver noting the stakeholder’s concerns so they can be addressed later

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)

A.

Ask the stakeholders about the priority of this change

B.

Ask the product owner to review the product backlog

C.

Ask the team members to analyze the impact of this change

D.

Ask the sponsor to approve the change request

E.

Ask the team members to include the change in the next iteration

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control

How should the project manager report the project status to key stakeholders?

A.

Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results

B.

Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget.

C.

Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control.

D.

Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away

An organization is transitioning to agile and a project has been chosen as a pilot The assigned project manager only has experience using predictive approaches but the project manager is now required to use agile approaches with the help of an agile coach During the retrospective of the fifth sprint, the project team complains that many obstacles exist with the organization that are creating project delays and rework

What should the project manager do in this situation?

A.

Include impediment resolutions during daily standup meetings

B.

Perform a root cause analysis during the standup meetings

C.

Create a dedicated sprint to solve the obstacles with the team

D.

Promote collaboration to help remove the obstacles for the team

A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors.

Which two documents should the project manager update as soon as possible? (Choose two)

A.

Issue log

B.

Risk register

C.

Stakeholder register

D.

Change log

E.

Backlog register

During daily calls team members share task progress One team member does not usually communicate many details and has critical tasks to be completed All team members are located in different countries and critical work is about to start Which two options will help the project manager in this situation? (Choose two)

A.

Encourage all team members to use a virtual workspace

B.

Ask the team to send emails with detailed task progress

C.

Talk to the team member about their engagement and take appropriate action.

D.

Reassign the work to a resource who participates in the daily calls

E.

Report the team member’s poor performance to the functional manager

A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.

What should the project manager do to address this issued

A.

Schedule a meeting with critical stakeholders to review the issue and decide on the next steps

B.

Put the project on hold and release the resources until the issue is resolved

C.

Inform the product owner and log the issue in the risk register to monitor closely for next steps.

D.

Contact the company that owns the patent of the similar tool to compare the similarities and differences with the current project.

A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25% The project manager updated the risk register and kept the project running as normal The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.

What should the project manager have done to avoid this?

A.

Ensured the risk tolerance of the company was property updated

B.

Implemented the communications management plan properly

C.

Implemented the stakeholder engagement plan correctly.

D.

Provided a proper risk response

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval

How should the project manager approach this problem?

A.

Plan to address the issues through backlog grooming and incorporate them into the next sprint

B.

Refer the product owner to the change management plan, then escalate to the steering committee

C.

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes

D.

Tell the product owner the issues will be addressed in the second version of the software

The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.

What does the project manager need to do first?

A.

Raise a change request to immediately implement the printing module component.

B.

Escalate this issue to the project sponsor immediately

C.

Ask the project team to conduct a quality audit of the printing module components.

D.

Meet with the project team to understand the issue and define actions.

The project manager just started leading a project team from which the previous project manager resigned After a quick evaluation of the project it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule

What should the project manager do?

A.

Conduct a meeting with the project team to discuss and address the sources of disagreement

B.

Inform the stakeholders that the project will be delayed due to previous team management

C.

Crash the project timeline to ensure the project is back on schedule

D.

Issue a change request to extend the project schedule based on identified delays

A research and development department is planning to develop a product that will introduce a new line of business for the organization What should the project manager do to increase the project's chances of success?

A.

Plan a working session focusing on the scope, vision, and mission of the initiative

B.

Start developing the project management plan based on a previous project template from the project management office (PMO).

C.

Conduct benchmarking to determine the business viability of the initiative

D.

Conduct an impact analysis of the new initiative to determine how the project should be rolled out

A project manager has been assigned to a project and receives the project charter from the project management office (PMO) The document is very clear about customer requests During Project Scope Management some requirements seem to be different from the ones specified within the project charter

What should the project manager do?

A.

Modify the baseline of the project for minor impact changes to the project scope

B.

Use a focus group and brainstorming sessions to gather more details about the project scope

C.

Register the changes in the configuration management plan and send it to the change control board (CCB).

D.

Explain to the sponsor that these requests could endanger the schedule and cost of the project

After the project charter's approval the project manager needs to work on detailed project requirements, constraints and assumptions with stakeholders However, not all of the stakeholders are immediately available for a meeting in the short term.

What should the project manager do in order to gather the information needed from stakeholders?

A.

Email, call, or meet with each stakeholder separately to obtain their input

B.

Conduct a meeting to build the project management plan with the stakeholders who are available

C.

Escalate to the project sponsor that not all stakeholders are available for a meeting

D.

Meet with the project management team to build the project management plan before consulting stakeholders

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.

Refer to the stakeholder register from the previous project as it was similar to the current project

D.

Document in the risk register that the current project may have differentstakeholders than the previous project

A project manager for a maintenance project has a contract that is renewed annually The project started 6 years ago After contract renewal this year the auditors reported that this version of the contract violates a new law that was passed last year

What has happened in this situation?

A.

The contract has not been appropriately reviewed by the project team

B.

The stakeholder engagement plan has not been correctly implemented

C.

The legal department has not disseminated the law correctly to all staff.

D.

The project manager does not have enough knowledge on this legal matter

A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.

What should the project manager do to support the business analyst?

A.

Assign resources to coach the business analyst

B.

Ask the business analyst to focus on their work allocation for the needs of the project

C.

Create reports to inform the business analyst about the schedule and project cost

D.

Provide the business analyst with access to the financial and scheduling information

A company's new communication system will include online dashboard reporting. The executive board might receive bi-weekly performance reports through the online dashboard What should the project manager do?

A.

Review the project management plan

B.

Update the stakeholder engagement plan.

C.

Update the communications management plan

D.

Review the configuration management plan.

An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

A.

Support the team as necessary to find the minimum viable product (MVP).

B.

Amend the project budget to include MVP testing

C.

Submit a change request to the project sponsor for accelerated testing.

D.

Develop the product as per the schedule to perform integration and testing

For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available

Why is an attendance list important?

A.

It is standard practice on projects to conduct risk review meetings which should have records on meeting attendance

B.

The attendance list is evidence that risk review meetings were held with the appropriate project team members

C.

It is a record that shows the number of attendees in the meeting

D.

It is a document that is registered within the lessons learned register

A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required

How should the project manager assist the product owner?

A.

Coach the product owner on how to create a product backlog

B.

Encourage the team to subdivide the project tasks

C.

Create a work breakdown structure (WBS) and explain the deliverables to the product owner

D.

Discuss the product owner's responsibilities within the project team

After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.

Which technique will help the project manager to accelerate the deliverable?

A.

Impact mapping

B.

Rolling wave planning

C.

Collective code ownership

D.

Scrum of Scrums

A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.

How should the project manager respond'?

A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance

B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework

C.

Record the issue in the issue log and escalate the conflict to the project sponsor for assistance

D.

Explain to the stakeholder that the stakeholder engagement plan requires theirattendance at all reviews

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

A.

Instruct the team to accommodate the changes to the project

B.

Review the project charter to identify the agreed scope

C.

Negotiate the impact of these changes with the client

D.

Escalate the issue to senior management

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?

A.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones

B.

Create a reward system granting incentives to the team members who are able to catch more defects

C.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

D.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems

A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease. What should the project manager do to address this issue?

A.

Force the team members to work from one location.

B.

Develop protocols for resolving conflicts between team members

C.

Obtain special expertise to advise the team members

D.

Set up face-to-face meetings with project team members

Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them

What strategy should the project manager use to resolve this conflict in the meeting?

A.

Explain to the managers that the contradicting requirements are being considered for implementation in the project

B.

Explain to the managers that only one of the two requirements can be implemented, and submit a change request,

C.

Ensure that both managers understand the requirements and search for a solution that best satisfies this deliverable

D.

Request that the managers explain why each requirement must be implemented and decide by considering the cost and benefits

A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information

What should the project manager do first to resolve this situation?

A.

Update the issue log and escalate to the project sponsor

B.

Identify the lack of information as a risk and update the risk register

C.

Schedule more frequent meetings with the technical manager.

D.

Review and update the stakeholder engagement plan

During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.

What should the project manager do?

A.

Guide the team to revert back to the forming and storming stages

B.

Escalate the issue to the project sponsor.

C.

Convene a team building event to address key performance indicators (KPIs).

D.

Discuss the decrease in productivity with human resources

During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time The subcontractor was not prepared for it and asked the project manager for additional budget What should the project manager do first?

A.

Ask upper management for more funds and update the project budget

B.

Revise the project scope accordingly to cope with the budget changes

C.

Update the risk register and project log. and manage the budget closely.

D.

Submit a change request to accelerate the project as requested