A project manager is leading a long-term project, executed in stages, to set up a complex communications network in many rural areas. The project is being executed in stages.
What should the project manager do to ensure that monetized business value is generated as planned?
During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not convinced that the return on investment (ROI) can be achieved.
How should the project manager address this issue?
A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone.
How should the project manager continually evaluate the effectiveness of the virtual team's engagement?
A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.
What should the project manager do?
A project manager has received feedback from stakeholders regarding poor communication about project progress. Weekly status reports were provided to the project management office (PMO), and the standard communications management plan was followed.
What should the project manager do?
A project manager leads an agile development project. During the sprint planning meeting, the development team expresses concerns that the proposed scope of the next sprint is much larger than expected given the current resource allocation. The project manager believes the scope is essential to meet the project milestones.
How should the project manager approach negotiating an agreement with the team to ensure the project remains on track?
Due to scope changes, some of the risks identified during the initiation phase have materialized into issues. What should the project manager do next?
In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?
A project manager is in the middle of executing the construction of a high-rise plaza when the government regulatory agency announces an increase in the price of fuel. The project still has seven months left on the schedule.
What should the project manager do first?
During a project iteration, half of the project team was reallocated to a new project. How should the project lead handle the situation?
A project manager is confused when the operational results from previous iteration solutions have not been acceptable to the client. Team members have already delivered all previous solutions, which were accepted by the client as complete.
What should the project manager do?
A project manager's team has been working very hard to meet a critical deadline. Some project team members are experiencing burnout due to the high workload.
What should the project manager do first to manage the team's workload effectively?
A project manager was appointed to lead an already approved project. While reviewing the benefits management plan, the project manager finds out that the information about the forecasted value of the project may not be accurate.
What should the project manager do?
A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.
What should the project manager have done to avoid this setback?
A customer complains that a software update project is failing to deliver value according to the original scope. What should the project manager do to resolve the problem?