Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exc65

A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team

members who are confused about the next steps and the final outcome of the project.

What should the new project manager do?

A.

Avoid conflict and let the team self-organize on how they want to work on the project tasks.

B.

Ask the project sponsor to provide team members with a project direction regarding outcomes.

C.

Set short-term goals in order to create a winning culture internally and praise team members for achieving them.

D.

Escalate the situation to the steering committee and request that more time be allotted to the project.

An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing

the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.

What should the project manager do?

A.

Recommend splitting the project into two smaller projects in order to work exclusively in an agile environment without interference from a predictive approach.

B.

Propose that the well-defined scope items be delivered using a predictive approach and use an agile approach to deal with the complex

items.

C.

Maintain stakeholder momentum in working on the scope definition until a full detailed scope is achieved prior to starting the project.

D.

Update the risk register and escalate the issue to the project management office (PMO), requesting more resources be added to help define

the project scope.

A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.

What should the project manager do in this situation?

A.

Assess the impact of the stakeholder and engage properly.

B.

Escalate the stakeholder issue to the project sponsor.

C.

Develop a specific communications strategy for this stakeholder.

D.

Use interpersonal skills to gain stakeholder engagement.

A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.

Which technique will best serve this purpose?

A.

Personas

B.

Power influence grid

C.

Power user grid

D.

Salience model

A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?

A.

Ask the project sponsor to replace the contractor since they do not have agile experience

B.

Issue a formal notice to the contractor to obtain an agile certification

C.

Consult the project team to understand the extent of the training needs for the contractor

D.

Instruct the contractor to receive agile training since the project has already started

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

A.

Submit the new response plan to the stakeholders for their review.

B.

Obtain management approval prior to implementing the new risk response.

C.

Use the management reserve to mitigate the risk.

D.

Implement the new response to address the risk.

A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?

A.

Use interpersonal skills to expedite the issue.

B.

Send a gentle reminder to the technical service team.

C.

Update the issue log with the status and priority.

D.

Issue a formal warning to the technical service team.

A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.

What should the project manager do to ensure value is delivered quickly?

A.

Plan the project to deliver value incrementally with regular releases.

B.

Request a budget increase to pay the subject matter experts (SMEs) more overtime

C.

Identify tasks that can run in parallel to deliver the project faster.

D.

Ask the project sponsor to provide additional resources to fast track the project.

In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain

What should the project manager do?

A.

Make sure the analyst has regular pairing meetings with the other team member throughout task execution

B.

Ask the analyst to use skills to develop the tool, then move development to another team member

C.

Enroll the analyst in a capacity-building program and keep this analyst assigned to the task

D.

Recognize the analyst's concerns and reassign the task to another team member

The project manager has recently received funding approval for a training program

for the entire project team but has not yet defined the most effective training course. One

team member submitted a request for specialized training that is required for the project.

How should the project manager handle this request?

A.

Send this change request to the change control board (CCB) for approval.

B.

Approve the request for the specialized training.

C.

Reject the request as it does not impact the project deliverables.

D.

Validate if the training is within scope and budget.

While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:

    Approved Work Package Cost Estimates: US$9,500

    Contingency reserves: $500 %

    Management reserves: 10% of contingency reserves

    Percent complete of the project: 50%

    Planned percent of the project: 40%

    Actual costs of the project: US$4,500

What is accurate about the project status?

A.

The actual work is 25% more than the planned work.

B.

The project cost is 10% lower than planned.

C.

The actual work is 25% less than the planned work.

D.

The project cost is 10% higher than planned.

During the execution of a financial project, a project manager met with the project team weekly to evaluate the project's progress. However, the sponsor requests that project performance be checked daily. The key team members disagree with this requirement and argue that they do not have enough time to go to daily meetings because they are at an executive level.

What should the project manager do first?

A.

Negotiate with the key team members to send a daily report and let the sponsor know that the project cost will increase. ty

B.

Recommend to the sponsor that performance of the project be reviewed once per week.

C.

Review the communications management plan and submit a change request if required.

D.

Evaluate the capacity of each team member to attend daily meetings in person or virtually and reduce the time of each meeting.

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

A.

Accommodate the change request to serve the client's needs

B.

Consult with team members and allow them to make a decision

C.

Convince the client not to make changes to the project

D.

Make transactional decisions focusing on the project goals

A product owner has provided the team with a prioritized backlog for the initial

launch of a new product. After analysis, the team concludes that some work is missing to

support the initial launch and provides this information to the product owner. The product

owner acknowledges the missing work and adds it to the bottom of the backlog. The team is

not happy with the prioritization that the missing work received.

What should the project manager do in this situation?

A.

Let the project team pull the recommended work from the bottom of the backlog to

maximize value creation.

B.

Analyze and reprioritize the backlog and provide the decision to the product owner

and team.

C.

Recommend the product owner prioritize the missing work higher because it is

needed for the minimum viable product (MVP).

D.

Empower the product owner by supporting the decision and instructing the team to follow the prioritization as provided.

A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.

What should the project manager do?

A.

Schedule a meeting with the previous project manager

B.

Submit a change request to the change control board (CCB)

C.

Schedule training for project team members

D.

Conduct an earned value analysis (EVA)

The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.

What strategy should the project manager use in order to keep delivering value in a restricted environment?

A.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.

B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance.

C.

Restrict the project scope only to basic critical features, and run the project with the current staffing level until all of the budget is consumed.

D.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction

In a fixed time and budget project the customer wants the development of a core component to be based on agile practices, as the final scope of (he requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two)

A.

Limit the number of iterations for development in the contract.

B.

Establish a governance committee to review the contract delivery

C.

Tier the contract for fixed and agile components

D.

Provide alternatives to scope change at specific project phases within the contract.

E.

Require that only internal resources be utilized for this project

An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?

A.

Submit new user stories to the product owner in order to put documentation in the product backlog.

B.

Introduce a document management tool to support the agile teams in preparing the documentation.

C.

Check with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.

D.

Add an additional team member to take up the role of scribe for the required documentation.

The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.

What should the project manager do to ensure timely delivery?

A.

Ask the team leader to assign other resources.

B.

Update the issue log.

C.

Include this in the risk register.

D.

Escalate the issue to the functional manager.

A project manager for a building construction project is planning to go on vacation

midway through the project execution phase. What should the project manager do first to

ensure the team is empowered and deadlines are met?

A.

Allow the team to make decisions to stay on schedule.

B.

Postpone the vacation to a different time.

C.

Ask the project sponsor to make any necessary decisions.

D.

Analyze the impacts and create a plan for team decision making

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?

A.

Review the project scope statement

B.

Confirm ownership for ongoing value realization

C.

Escalate the issue to the project sponsor

D.

Appraise the stakeholders of value gain progress

A project manager prepared the base budget model to deliver a highly

customizable software solution. The solution will be delivered in multiple countries with

significantly different cultures and will be staged over phases.

What should the project manager do next?

A.

Review the base model with the team leaders in each country to establish an

independent budget for each phase.

B.

Overestimate costs and underestimate revenues to include the impacts of different

cultural elements.

C.

Apply the company's operational budgeting model.

D.

Ask the project management office (PMO) to review the draft budget.

A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.

What should the project manager do first?

A.

Organize a conference call with the internal expert and the client to estimate the amount of effort required to fix it.

B.

Decline the request politely since the issue, although critical, is not the responsibility of the project team.

C.

Allocate a task to the team member as a high priority and inform the customer that the issue will be resolved the next day.

D.

Inform the customer that they should contact the sales manager and submit a formal request for a quote.

Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.

What should the project manager do next?

A.

Schedule a meeting between the team members to find a solution.

B.

Refer the team members to the project charter to resolve the conflict.

C.

Issue a new change request to evaluate this situation and communicate the result.

D.

Document the facts explained by the team members in the issue log.

A highly skilled team resource received a job offer and is leaving the project soon What should the project manager do to maintain project performance while a new team member is being onboarded?

A.

Log a risk in the risk register and work with the new team member to mitigate it

B.

Motivate the new team member to perform.

C.

Share project documents with the new team member.

D.

Offer cross-training and mentoring to the new team member

A project manager has been assigned to take over an existing software project. The project manager inherited a lean team comprised of key stakeholders, subject matter experts

(SMEs), and senior developers. While reviewing the project status with the team, the project manager observes that the team seems to lack direction and enthusiasm.

What should the new project manager do?

A.

Ensure everyone performs their assigned tasks as planned.

B.

Organize frequent team building sessions and update the risk register.

C.

Meet with the project sponsor and propose a corrective action for the project.

D.

Encourage participation in decision making and empower the team.

A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards

What should the project manager do?

A.

Set up a structured, independent processes to determine if project activities followed the standards.

B.

Schedule training for the project team on the new regulations introduced by the government agency

C.

Evaluate the impact the new regulations will have on the project and submit a change request

D.

Update the lessons learned register and inform senior management of the new standards

A company has agreed to run a transformation project using agile approaches.

During the implementation, there is pushback from the functional groups that the project is moving too fast.

What should the project manager have done at the beginning of the project to prevent this from happening?

A.

Circulated the project charter

B.

Assessed the organizational culture

C.

Determined the level of maturity of the employees

D.

Communicated the project schedule

A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.

What immediate action should the project manager take to improve the situation?

A.

Communicate this issue to the human resources department.

B.

Provide additional training to the new hire.

C.

Increase team cohesiveness by sharing information and experiences openly.

D.

Update the issue log and define the mitigation strategy.

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

A.

Evaluate the impact to the users and create a plan to address it.

B.

Inform users about the new changes and ask for their collaboration.

C.

Ask all managers to collaborate implementing this change to users.

D.

Start implementing the change so that users will eventually get used to it.

During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?

A.

Call for a team meeting to identify the root cause for the declining performance

B.

Estimate the baseline impacts and submit a change request.

C.

Implement compression techniques to bring the project back on track.

D.

Review the resource management plan and organizational assets

A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is

frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.

What should the project manager do?

A.

Request that the team identifies, documents, and registers the issues to locate the source of the problems.

B.

Evaluate the cost and schedule variance in order to determine how much the project is off track.

C.

Ask the team to commit to a new date to fix all the problems and proceed with a change request to adjust the baseline.

D.

Request that a senior subject matter expert (SME) be hired to analyze and solve the problems.

A project manager is working on a major construction project. Part of the

agreed-upon plan was to use a cloud-based system with a server that runs on high-speed

internet service since most of the team members work virtually. The company needs to

reduce operating costs as much as possible and management insists that the project will

now use a system running on a conventional dial-up service.

What should the project manager do next?

A.

Evaluate the impact of this decision and communicate with management.

B.

Agree with management and continue working the project management plan.

C.

Meet with management about their decision and ask them to get another project manager.

D.

Replace some of the team members that work virtually to help the company save money.

An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.

What should the project manager have done to avoid this situation?

A.

Ensured the project repository is up to date.

B.

Updated the job descriptions for all team roles.

C.

Provided specialist training for all team members.

D.

Made an effort to reemploy the senior project team member.

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.

What should the project manager do?

A.

Create an entry in the impediment board and assign it.

B.

Invite the project team to a swarming session to define a solution

C.

Leverage the network of the former department and ask for help

D.

Escalate the issue to the product owner to define the next steps

A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?

A.

The team with the higher velocity is performing better and should be rewarded.

B.

The issue should be addressed as part of a retrospective in the next iteration.

C.

The velocity should not be compared as teams can size items differently.

D.

The velocity of both teams should be compared at the end of every iteration.

A project manager recently joined the company. At the interview, the project manager demonstrated experience with agile delivery, and the project management office (PMO) manager asked for assistance in implementing agile.

What should the project manager do to initiate the adoption of agile within the company?

A.

Organize agile workshops with the developers and testers to gain their support in using agile approaches for their projects.

B.

Request that all the project managers and business managers receive training in the agile framework used previously by the project manager.

C.

Advise the PMO manager to continue with the company's current predictive approaches until all the projects in execution are closed.

D.

Assess the organization's culture to determine if agile can be used in project delivery and determine the practices to be used.

A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?

A.

Request the project sponsor prioritize and if necessary, allocate additional budget so the team can work on a single project

B.

Provide an incentive plan so the team members will work more unaccounted hours on multiple projects

C.

Brainstorm with the team members on how they can deliver on multiple projects within the given budget

D.

Instruct the team members to spread evenly across projects so mistakes will not occur within the current budget.

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

A.

Continue with the sprint as the progress shows buffers for potential interruptions.

B.

Ask the product owner if some low-priority stories could be cut from the sprint.

C.

Continue with the sprint work as planned and keep monitoring.

D.

Ask the project team to select any additional stories as they have additional capacity than planned.

While developing a new product, a key stakeholder expresses concern about

insufficient information on product feature requirements. The product team disagrees and

mentions that detailed requirements have been provided.

What should the project manager do to handle this situation?

A.

Organize a discussion with the product team to clarify the missing information.

B.

Redirect the stakeholder to discuss this request with the functional manager.

C.

Record the new requirements and ask the product team to develop them.

D.

Conduct new risk and scope analyses, identifying the missing information.

A project manager is managing a megaproject. The project stakeholders are from different geographical areas and have diverse cultural and social backgrounds. The project manager wants to improve team productivity to realize more effective and efficient results.

Which action should the project manager take?

A.

Empower team members to participate in decision-making and take ownership of actions.

B.

Implement a flexible work schedule policy to eliminate the time zone problems among stakeholders.

C.

Encourage team members to network so that they know each other's cultural backgrounds.

D.

Provide a relaxed work schedule policy and encourage team members to work from home.

A project manager is managing a hybrid project A stakeholder has directly contacted a team member and has requested a change Due to the request, the team member was distracted from their work, which caused a loss in productivity.

What should the team member do?

A.

Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the project manager.

B.

Inform the scrum master regarding the stakeholder's request for a change and the impact this has had on productivity.

C.

Inform the stakeholder that the correct procedure for new requirements is to provide it directly to the change control board (CCB).

D.

Inform the scrum master so that the change can be discussed directly with the stakeholder.

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

% What should the project manager do next?

A.

Update the assumptions log and change log, and implement the change control process.

B.

Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.

C.

Inform the client that the project cannot meet the project timeline and additional costs will be incurred.

D.

Deliver what was planned in the project management document according to the specifications.

A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

A.

Focus on remediation not merely on correcting symptoms

B.

Compare the team's performance against other project teams

C.

Identify potential failure points based on the iteration workload

D.

Motivate the team to perform better

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

A.

Escalate the issue to the project sponsor.

B.

Review the stakeholder engagement plan.

C.

Update the issue log.

D.

Neutralize the negative stakeholders.

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.

What should the project manager have done to avoid this situation?

A.

Initiated requirements planning to analyze, document, and manage requirements

B.

Applied requirements elicitation to involve engaging stakeholders consistently in the requirements process

C.

Implemented the change request process to harness change to the stakeholders’ advantage

D.

Used progressive elaboration to enhance the scope management plan with additional details

A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders

What document should the project manager use to communicate these requests?

A.

Risk log

B.

Change log

C.

Backlog

D.

Issue log

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

A.

Meet with the team to reinforce their responsibilities and the consequences if the

project deliverables are not completed on time.

B.

Apply additional controls to the project deliverables to ensure that all milestones

are achieved on time.

C.

Contact the functional manager to ensure that team motivation remains high until

the end of the project.

D.

Schedule a team event with the project sponsor to highlight the importance of the

project and recognize the work of the team.

A few developers have submitted their resignation after completing their annual review and receiving their annual bonus. The project manager cannot find replacements for all of the developers in time to meet the project's deadline.

What should the project manager do?

A.

Request additional budget to recruit more developers.

B.

Lower the recruitment criteria.

C.

Log the issue in the issue log.

D.

Analyze the impact and inform the stakeholders.