Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exc65

In the past year, a company paid US$60,000 to an external subcontractor for an ongoing project. The project manager has been asked to

evaluate if the project can be delivered more cost effectively this year by using internal labor. The project manager used an optimistic term of 4

months, a pessimistic term of 6 months, and a most expected term of 5 months, and has concluded that the service can be delivered with the

following resources:

* Two engineers (monthly salary of US$700 each)

* One project manager (monthly salary of US$1,600)

* Additional estimated monthly expenses of US$2,000

The project manager used the program evaluation and review technique (PERT) to calculate the savings if the project is delivered with in-house

resources.

How much money will the project manager estimate the company can save?

A.

US$35,000

B.

US$20,000

C.

US$40,000

D.

US$30,000

A project with a hard timeline is starting its first iteration out of six. The project team is lacking the necessary skills to execute.

What should the project manager do?

A.

Allow the team to proceed as they attempt to meet the timeline.

B.

Add a subject matter expert (SME) to the project team.

C.

Invite stakeholders to discuss a mitigation plan to finish on time.

D.

Fill the skill gap personally to execute the project.

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

A.

Ask the project team to review and modify all of these reports.

B.

Ask the sponsor to meet with the stakeholder to diffuse the situation with the reports.

C.

Explain to the stakeholder that these are the approved templates for the reports.

D.

Ensure that the reports comply with the communications management plan.

A company is launching a new product that has to be ready before the summer season begins. After the discovery process, the team realizes that the requirements are very uncertain.

What should the project manager do?

A.

Invite stakeholders to discuss project requirements prioritization.

B.

Register a risk and define a contingency plan to finish the project on time.

C.

Ask to include some business subject matter experts (SMEs) in the team.

D.

Assist the team in proposing a minimum viable product (MVP).

A project manager is well informed on the industry standards of the organization and believes that they are not reflected in the project deliverables. What should the project manager review next?

A.

Quality process

B.

Quality management plan

C.

Organizational process assets (OPAs)

D.

Project charter

An organization is initiating a project that will be using new technology. The complexity of the project requires excellent technical skills. After reviewing the proposed project management plan, the project sponsor asks for options to reduce the labor cost without introducing risk to the project delivery.

What should the project manager do first?

A.

Review the risk register and assign functional managers as resources.

B.

Analyze the resource pool and assign internal resources who participated in past projects.

C.

Perform an analysis of the key cost drivers and present alternatives.

D.

Review the work breakdown structure (WBS) to ensure there are adequate resources.

A project manager is managing a project to deploy new software to 200 end users. During the implementation, there is a missed process that

caused some of the users to lose their computer data.

What should the project manager do first?

A.

Meet with the team to discuss the root cause and encourage the team to take note of it and continue to focus on the deployment.

B.

Record this case until the final lessons learned session is complete to prevent impacting the team's morale during implementation.

C.

Meet with the team members and request they conduct a review of the case by providing feedback as lessons learned.

D.

Invite a consultant to review the process in order not to repeat the same issue and share the results with the team.

A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

A.

Prioritize the item flagged as high business value and low complexity for this sprint.

B.

Support the team to move both items to the next sprint when the team will know more.

C.

Facilitate the discussion until the team reaches an agreement about the two items.

D.

Prioritize the item flagged as a dependency with low business value and high complexity.

A team is preparing the closing phase and building a plan for the next phase. One of the project sponsors is complaining that the last phase had some quality deliverable issues. However, the quality acceptance document was signed.

What should the project manager do?

A.

Reopen the quality acceptance documentation to add the sponsor's complaints.

B.

Schedule a quality review meeting and include the sponsor's complaints.

C.

Review best practices and lessons learned and apply them to the project plan.

D.

Postpone the next project phase until the impact of the quality issues is assessed.

A company that uses a predictive approach and operates in a highly regulated market is losing profitability because its product life cycle is taking longer than those of its

competitors. A new project manager has been hired to change this scenario.

What approach should the project manager propose?

A.

Change to an agile model, focusing primarily on the incremental life cycle, leaving the iterative approach as a next step.

B.

Maintain a predictive approach, but increase the focus on better planning and tracking to anticipate problems and avoid delays.

C.

Migrate to an agile model, focusing primarily on an iterative approach, leaving the incremental life cycle as a next step.

D.

Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company’s industry.

At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried

to contact the consultant but has been told that the consultant does not have the time to discuss the project.

What should the project manager do to move the project forward?

A.

Escalate the issues about the consultant to the functional manager so the consultant dedicates the necessary time to the project.

B.

Include a new project risk into the risk register and allocate the consultant as the risk owner as it is their responsibility to provide input.

C.

Discuss the request with the consultant and set up time with the business analyst and consultant to discuss the project requirements.

D.

Urge the business analyst to continue contacting the consultant to discuss the project since this is the responsibility of the business analyst.

A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.

What two things should the project manager do? (Choose two)

A.

Discuss the issue with the external supplier's authority.

B.

Review the lessons learned from similar past projects.

C.

Gather additional information and estimate the impact.

D.

Update the risk log and bring this up in the meeting with the client.

E.

Wait for the client to raise a concern and collect more information.

A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity.

What should the project manager do to address this situation?

A.

Discuss the issues with the sponsor to fully convey the problem of the unavailable resource and the amount of work being done. shared.

B.

Discuss this with the sponsor and hold a meeting with the stakeholders so all of the team challenges can be shared.

C.

Discuss this with the team so they can complete the work of the unavailable team member and aim for the release deadline.

D.

Discuss this with the team so they are able to reprioritize critical tasks and aim for the release deadline.

A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.

What should the project manager do next?

A.

Modify the PMO template to include the information.

B.

Contact the senior manager and discuss their needs.

C.

Give the senior manager access to the product backlog.

D.

Organize a review of the kanban board with the manager.

In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.

Match the project manager's goals on the left with the relevant risk parameter on the right.

A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle.

What should the project manager do next?

A.

Guide the team to determine alternatives.

B.

Move the dependent task to the next iteration.

C.

Escalate the issue to the company's IT manager.

D.

Escalate the issue to the project sponsor.

Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two

members are tense around each other and are taking everything personally.

What should the project manager do?

A.

Help the team members to resolve the conflict in a way that results in the best team performance.

B.

Offer a compromise that is acceptable to both team members, even if it may not be the best solution.

C.

Understand each team member's argument and select the one that results in less risk to the project.

D.

Send both team members to the human resources (HR) department for an acceptable resolution.

A vendor project manager and team are implementing a software solution across the organization. A customer stakeholder who was not present during the sales process is demanding that the team implement requirements that are out of scope without adding additional cost to the project.

What should the project manager do next?

A.

Escalate the issue of the additional requirements to the executive leadership team.

B.

Refer the stakeholder to the delivery specifications in the statement of work (SOW).

C.

Implement all the requirements the customer has requested.

D.

Adjust the scope baseline and schedule baseline accordingly.

A large multi-national company works on a project in an emerging-economy country. All business matters are conducted in local currency. During the course of the project,

the budget becomes the primary concern due to currency instability in the country.

What should the project manager do next?

A.

Evaluate the situation with the team

B.

Escalate the risk to the project sponsor

C.

Use the project's contingency reserve

D.

Ask for additional budget from the client

A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress

(WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.

What should the project manager have done to avoid this situation?

A.

Stored project documentation in a shared folder.

B.

Organized monthly meetings with the external stakeholders.

C.

Invited all of the stakeholders to daily standup meetings.

D.

Sent weekly status update reports to all of the stakeholders.

A project manager is assigned to deliver an innovative solution that is part of a

brand new offering. The project manager reviews the request for proposal (RFP) and realizes that key terms are restricted to technical resource assignments. There is also a gap in addressing compliance.

How should the project manager bridge the gap and ensure the project delivers the expected

business value?

A.

Determine the critical requirements.

B.

Document the risks and mitigations.

C.

Define the project schedule.

D.

Create a project scope statement.

A project manager is assigned to a project related to taxes, which will be managed

using an agile approach. By reviewing lessons learned from a previous project, the project

manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

A.

Recognize the stakeholder's skills are important for the project and evaluate the

possibility of the stakeholder supporting the project team.

B.

Request the functional manager to assign the team from the lessons learned project to

the current project to avoid a learning curve.

C.

Ask the project team to review the lessons learned and have the team contact the

stakeholder directly if there are any questions.

D.

Send a request to the project sponsor to hire the stakeholder and have them become

part of the project team.

A team member is openly criticized by others during a standup meeting for failing to

complete yesterday's tasks. What should the agile coach do first to address the situation?

A.

Emphasize the ground rules and then focus on today's activities and impediments.

B.

Let the discussion go on as it is important that the team is clear on priorities for the

day.

C.

Address the team members involved during the next sprint retrospective.

D.

Avoid the discussion by referring to the team charter.

A project has been running successfully for 2 months. At a regular project meeting,

the team raises several potential obstacles to future progress. The obstacles include vendor

delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?

A.

Work with the team and others in the network to assess and prioritize the obstacles.

B.

Engage with the external stakeholders and the other division of the organization to

resolve the issues.

C.

Escalate the obstacles to the project sponsor for assistance with resolution.

D.

Determine a change response to identify and resolve the obstacles to move the project

forward.

In a software project using an agile approach, there have recently been work

overruns. After assessing the situation, the project manager concluded that the overruns are

occurring because of insufficiently refined product backlog items.

What should the project manager do to correct this issue?

A.

Work with the sponsor to revise the product vision.

B.

Create a definition of ready (DoR) for the backlog items.

C.

Discuss the issue with the service request manager.

D.

Refine the product backlog items with the stakeholders.

A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority. What should the new project manager do next?

A.

Refer to the project charter

B.

Review the project resource matrix

C.

Assess the stakeholder register

D.

Update the communications management plan

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

A.

Manage the scope baseline to influence the factors that drive change.

B.

Follow the proper change control process and evaluate the change for further impact.

C.

Work with the customer to ensure the feature adds value.

D.

Perform frequent reviews with the customer to ensure that the product is working as

expected.

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?

A.

Meet with the stakeholder to discuss the impact of the deliverable

B.

Consider the stakeholder as a risk and evaluate possible solutions with the project team

C.

Improve communication with the stakeholder to obtain their assistance in the future

D.

Escalate to the project sponsor due to the political nature of the issue

A team lead has been highly engaged and involved in a project and is operating without a chain of command or authority levels What is the team lead dang1?

A.

Modeling directive leadership

B.

Modeling commanding leadership

C.

Modeling adaptive leadership

D.

Modeling servant leadership

Throughout an entire project, the project manager took notes at every meeting with

team members. These notes provided useful insights from key stakeholders, which later

resulted in increased value to the project. The project manager thought it would be helpful to

keep these notes as a future reference for other project managers within the organization.

Where should the notes be located?

A.

Lessons learned

B.

Organizational process assets (OPAs)

C.

Enterprise environmental factors (EEFs)

D.

Project management plan

A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.

What should the project manager do?

A.

Use the agile approach in the new project and schedule agile training for those stakeholders who are new to this approach

B.

Continue to use the predictive approach m the new project since it is the approach the stakeholders are familiar with using

C.

Share the pros and cons of adopting an agile approach for the new project only with the team and ask them to decide which approach to use

D.

Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project

A project manager is assigned to an ongoing complex project. The team is delivering value each iteration However, the deliverables are internal and the customers are unaware of the deliverables.

Which action should the project manager take?

A.

Ask the internal sales team to keep the customer informed of the delivered value

B.

Evaluate various delivery options in order to immediately demonstrate value to the customer

C.

Inform the customer about the progress and update them on the final deliverables

D.

Wait for an important milestone to complete and then inform the customer of the progress

An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed

What action should the project manager take?

A.

Escalate the issue from the IT team to management and get the validation prioritized

B.

Work with the IT team to prioritize the validation and release of the new features

C.

Deliver the features when the IT team is able to validate them

D.

Request the IT team to immediately release the product and then validate the features

During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?

A.

Add the stakeholder details into the periodic reports and update the project management plan

B.

Invite the stakeholder to all future project review meetings and update the project management plan

C.

Update the project management plan with the new information and inform all of the relevant stakeholders

D.

Meet with the stakeholder to better understand their expectations and update the stakeholder engagement plan

A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.

Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)

A.

Organizational process assets (OPAs)

B.

Lesson learned registers from past projects

C.

Historical issue logs

D.

Project scope statement

E.

Project management plan

A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies

When should the risks be reviewed to ensure alignment between the project team and the stakeholders'?

A.

During the risk register update

B.

During the retrospectives

C.

During each steering committee meeting

D.

During each iteration and review

A contract has fust been awarded for an automation project that was supported by the local community. The project manager was warned by the elected officials that the project cannot proceed.

Why did this action occur?

A.

Inadequate funds for the automation project

B.

Inadequate engagement of the political stakeholders

C.

Lack of competence to manage the automation project

D.

Lack of a proper legal framework in place

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

A.

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

A project manager who Is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder's current role, previous and current projects in which they participated, and their level of organizational influence.

In what type of analysis should the project manager use this information?

A.

Regression analysis

B.

Stakeholder analysis

C.

Qualitative risk analysis

D.

Decision tree analysis

A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment. The project manager started communication with the team to move the project forward

What should the project manager do first at this pomp

A.

Meet with the quality planning manager to identify the reason why the quality plan was not created yet

B.

Meet with the hardware design engineers to identify the minimum performance required to establish a market for the machine

C.

Meet with the sales and marketing teams to identify the requirements that were collected during the interview sessions with potential customers

D.

Meet with the key stakeholders to identify the proper product concept for the development team

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

A.

Remove the items no longer applicable from the backlog and present the backlog to the project team

B.

Continue working on the defined scope and review the risk matrix

C.

Have a discussion with the project sponsor and cancel the project

D.

Have a discussion with the sponsor and recommend the project business value be reassessed

A project manager is assigned to a digital transformation project for a bank. The company culture is conservative and resistant to transformation or innovation. What should the project manager do first to support the transformation''

A.

Provide a digital transformation guide and explain that the change is unavoidable

B.

Ask the bank executives to officially announce that the project manager is leading the project

C.

Provide proper training sessions to the stakeholders so they understand the purpose of the change

D.

Hire an expert in digital transformation and assign that person as the champion for the change

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

A.

Instruct the team to accommodate the changes to the project

B.

Review the project charter to identify the agreed scope

C.

Negotiate the impact of these changes with the client

D.

Escalate the issue to senior management

An agile project manager is evaluating the method that will be used to display the

value of the work performed to date. Which method will they select to display to the project stakeholder?

A project manager is working with a team that is new to agile. One of the more

influential stakeholders struggles with the nature of agile. The project manager knows that this

stakeholder is needed as an advocate and wants to do everything possible to make the

stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project's

performance?

A.

Results of the MoSCoW assessment

B.

Cost-benefit analysis

C.

Return on investment (ROI) analysis

D.

Earned value analysis (EVA)

A project manager has been hired to help coordinate an ongoing project Historically the biggest problem as reported by the company's CEO is that the change request process has been handled by managers who did not have dear information on the project schedule and budget. This information has been inconsistent and handled by finance, risk. and functional subject matter experts (SMEs)

What should the project manager do to control this situation?

A.

Redefine the communications management plan

B.

Develop an integrated change management plan

C.

Document the risk in the project risk register

D.

Review the scope defined in the project charter

A project manager has been assigned with initiating a large project to deliver complex equipment Part of the project will be the result of a long research process, but once this is completed, the other part of the project must be incrementally delivered to the customer.

Which approach should the project manager choose for this project?

A.

Agile

B.

Waterfall

C.

Hybrid

D.

Predictive

Due to a recent company merger, a project manager from company B has been

assigned to a team that is comprised of team members from company A. At the start of the

project, conflicts arise due to a lack of clarity on processes and the project manager's

relationship with company B.

What should the project manager do to resolve this conflict?

A.

Avoid the conflict as the customer feels comfortable with using processes from

company A.

B.

Review the historical information and make the decision based on the return on

investment (ROI).

C.

Ask the team to use company B's processes since they are more familiar with these

processes.

D.

Work with the team to analyze which processes are suitable to use and define them in

the ground rules.

A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.

What should the project manager do?

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk

B.

agile tools and techniques used m the defined hybrid methodology for consistent application by all team members

C.

Use the predictive approach tor team members who are not knowledgeable m agile project delivery practices

D.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update

A project stakeholder has expressed concern that the established success criteria for

the project are not being met. What should the project manager do next?

A.

Review the established project benefits tracking metrics.

B.

Update the project business case document.

C.

Document the agreed-upon ownership of benefits realization.

D.

Create a project benefits management plan.