Halloween Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

A product owner has indicated there is strong customer interest in adding a new set of functionalities to a product. Using agile approaches, the project manager evaluates the new functionalities of the product.

What should the project manager do?

A.

Negotiate with the product owner to determine which functionality should be pushed out of the scope of the project.

B.

Discuss with the team how this change in scope impacts development at the next retrospective to determine next steps.

C.

Negotiate with the product owner to determine what might be removed from the backlog that is of similar size.

D.

Add the functionality to the product backlog for inclusion once a change request is created and approved.

A project manager is performing the scrum master role for a project team of developers. At the daily standup, a couple of developers complain about the noise from a neighboring team, the performance of their laptops, and the difficulty in booking meeting rooms.

What should the project manager do?

A.

Acknowledge the impediments and facilitate their resolutions.

B.

Note the impediments and escalate them to the product owner.

C.

Note the impediments and work on addressing them later.

D.

Assign actions to all stakeholders and oversee their implementation.

A project manager just completed a successful deployment and is preparing to transition the project to an operational state before starting closeout actions. What should the project manager do to ensure that the project is ready to move to an operational state?

A.

Meet with the project team to review the work breakdown structure (WBS) and confirm deliverables have been delivered.

B.

Develop a plan to repay the technical debt incurred during the project and ensure that the project sponsor agrees with the plan.

C.

Review the project approval requirements in the project charter and confirm who will be approving the project.

D.

Refer to the project’s work in progress (WIP) reports to ensure that there is no additional work in the backlog.

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.

What should the project manager ask the team to do next?

A.

Execute the smaller estimated activities.

B.

Resize the story points.

C.

Negotiate the estimation so it gets smaller.

D.

Break down the larger activities into smaller ones.

An organization is transitioning to an agile delivery approach. There is only one project that is being used as a pilot for the new approach. The project management office (PMO) manager has asked the project lead how communications with the project team and the stakeholders will be managed.

What should the project lead recommend?

A.

Send the weekly report to the PMO and the product owner, and use a kanban board for the project team.

B.

Send weekly reports to the PMO, and use a kanban board for the product owner and the project team.

C.

Invite the PMO manager to the daily standup with the project team and product owner.

D.

Send weekly reports to all stakeholders, including the project team and the product owner.

A new project team consists of team members from different departments who have varying levels of experience and different areas of expertise.

Which three approaches should the project manager take in order to facilitate knowledge sharing? (Choose 3)

A.

Arrange a daily learning session for project team members during lunch to facilitate knowledge transfer.

B.

Allow each team member time in the retrospective sessions to share a little bit about their role and areas of knowledge.

C.

Assess the gaps and assign an expert resource for respective areas of knowledge.

D.

Identify external subject matter experts (SMEs) and plan training sessions to conduct knowledge transfer.

E.

Schedule shadowing sessions among team members to facilitate team learning.

During the execution of a construction project, one of the neighboring businesses is complaining that the current building height does not agree with the initial project plans. What should the project manager do first?

A.

Ask the neighbor to leave the site immediately because the site is on private property.

B.

Inform the neighbor that all of the project documentation has been approved.

C.

Inform the neighbor that the complaint will be escalated to the project sponsor.

D.

Ask the neighbor to submit a formal complaint about their concerns.

Four new teams have been formed to develop a new product. Several team members ask the project manager who will integrate the different work streams into one backlog.

What should the project manager do?

A.

Create integration tasks and schedule an additional team meeting following the standup meeting to plan the integration.

B.

Advise the teams to work individually and organize an integration iteration every four development sprints.

C.

Instruct the team to use the kanban board daily to facilitate alignment of their work item list, allowing them to do their best work.

D.

Advise the teams to collaborate with the product owner in prioritizing the stories, considering dependencies and preventing overlap.

A project manager is looking for ways to keep the budget on track throughout the project life cycle.

What should the project manager do to ensure that happens?

A.

Evaluate and test all budget variances.

B.

Baseline the project budget and schedule.

C.

Prioritize high-cost tasks and monitor them.

D.

Use metrics to track the cost performance.

A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager. This change to the process implies longer processing. The project urgently needs new resources.

What should the project manager do?

A.

Adapt the resource management plan and ask for financial approval before sending it to the customer.

B.

Assess the impact of the change and review the project management plan for next steps.

C.

Ask the financial manager to delay implementation due to potential project delays and penalties.

D.

Review the project schedule to determine which technique will reduce impact on project duration.

An organization is undergoing an agile transformation and migrating most of its projects from a predictive approach. The CFO expressed a concern that predictability on both costs and scope will be lost with the new agile approach.

What should the project manager do?

A.

Provide mentoring to the CFO, who is a key stakeholder in the project, and clarify the benefits of an agile approach.

B.

Ask the CEO to intervene by asking for support from the executive board to accelerate the company's transformation.

C.

Apply influence with other key stakeholders on the board to mitigate any risks that may be generated by the CFO's position on the matter.

D.

Submit a report to all key stakeholders on the cost-benefit analysis of the new approach and detail how the company will save money.

A company hired a new project lead to incorporate some agile practices.

Which three changes should the project lead incorporate in the existing team meetings? (Choose 3)

A.

Add sprints and sprint reviews as necessary.

B.

Agree with the team on some ground rules.

C.

Avoid extended discussions during daily meetings.

D.

Select a team member to lead the daily meetings.

E.

Encourage everyone to participate in the daily meetings.

A team has been working for some time on a project with incremental deliveries. The project manager noticed that one of the team members is less engaged in team meetings, yet delivers promptly. While discussing the source of demotivation, the team member informed the project manager that this is due to a feeling of lack of skills in dealing with new tasks.

How should the project manager address the issue?

A.

Create a self-paced learning plan with the team member during working hours, with checkpoints on learning progress.

B.

Review which tasks the team member would feel more motivated to work on, then assign those tasks to the team member.

C.

Replace the team member with a resource from another team who already has the requisite training and skills needed.

D.

Discuss growth and development needs with the team member and provide learning opportunities accordingly.

A project manager is facilitating an iteration retrospective. The iteration did not go well and the committed functionality was not delivered to users. The project involves a vendor team for the build and an internal quality assurance (QA) team. In the past, there were tensions between the vendor and the internal team.

What should the project manager do?

A.

Hold separate retrospective meetings for both the vendor team and the internal team.

B.

Schedule a preliminary meeting with the account manager from the vendor and the test manager.

C.

Establish a clear agenda for the meeting and remind the vendor and internal teams that the scope is to improve the process.

D.

Invite the procurement manager and a representative from the vendor to manage the current tense relationship.

The key stakeholders of a project would like to be actively involved in the review of product increments.

What should the project manager do?

A.

Analyze their interest and influence to manage expectations.

B.

Update the communications management plan for key stakeholders.

C.

Identify the needs and expectations of key stakeholders.

D.

Encourage their participation in release and sprint reviews.