A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

A.

Provide a project management template for the project manager to follow as a guide.

B.

Suggest using an agile approach since customer and team collaboration is critical for project success.

C.

Work with the project manager to develop a new approach that will bring benefits to the project.

D.

Establish a project management methodology that requires the customer to provide daily updates to the team.

A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?

A.

The project manager must ensure that the knowledge transfer occurred and that this is also included in the organizational process assets (OPAs),

B.

The project team members need to ensure they have supplied sufficient knowledge transfer.

C.

The project sponsor must ensure all knowledge transfer is completed before project closure.

D.

The stakeholders need to ensure they have received sufficient knowledge transfer for ongoing support after the project handover.

The project team is planning a schedule with limited information. The team |s having

issues identifying the detailed tasks and estimating task durations.

Which three techniques should the project manager use? (Choose three)

A.

Rolling wave planning and an adaptive approach

B.

Relative estimation to determine the task or deliverable sizes

C.

Iterations and reviews to continuously keep adapting the plan

D.

Bottom-up estimating based on a work breakdown structure (WBS)

E.

Gantt chart that includes milestones and deadlines https://www.projectmanager.com/blog/project-management/planning-techniques-for-projects

A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.

What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?

A.

Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.

B.

Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.

C.

Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.

D.

Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

A.

Resource management and lessons learned

B.

Time management and stakeholder engagement

C.

Cost management and risk management

D.

Stakeholder engagement and lessons learned

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,

What should the project manager do?

A.

Descope low-priority features that were not explicitly requested and add this feature as a high priority.

B.

Inform the senior manager that they will need a new project management plan for this feature,

C.

Complete the most current feature and release the resources for the new feature.

D.

Analyze the impact of this change and present the options to the senior manager.

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,

B.

Continue working with the predictive approach to deliver the value at the end of the project.

C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.

What should the project manager do next?

A.

Explore the minimum requirements of the product and their feasibility.

B.

Explain the resource constraints of the project to management.

C.

Outsource the management of the product to an external team.

D.

Conduct a detailed risk analysis to highlight the risks in the project.

A client comes to the company asking to copy a project that was executed 2 years ago

in the same city, with the expectation that the new project will have the same cost and duration.

While finalizing the project management plan, the project manager realizes that the baseline

costs are much higher than the original project.

What could the project manager have done to avoid this?

A.

Verified applicable budget inputs related to this project

B.

Assigned the same project resources to this project

C.

Estimated a budget for the project's quality management

D.

Determined a budget reserve for this project

A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.

How should the project manager handle this situation?

A.

Ask the product owner to create a new entry in the risk management plan regarding likelihood and imped

B.

Review the backlogs from similar projects and understand how change requests were implemented

C.

Ask the product owner to follow the change request process to formalize new requirements

D.

Make sure that the product and sprint backlogs have the required level of documentation and both are visible to the team

During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?

A.

Review and update the project schedule according to performance

B.

Review the schedule baseline and consider adopting a schedule performance indicator

C.

Develop a lime. cost, and scope tracking method exclusively for this project.

D.

Adopt a formal change management process for the project

A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.

What should the project manager do?

A.

Ask the client how the project will affect the client's organization and recommend that all impacted parties be involved.

B.

involve an executive-level stakeholder at the project manager's own company to speak with the client's executive sponsor.

C.

Perform an independent analysis to determine the stakeholders from the client's organization.

D.

Defer to the judgment of the client's executive sponsor since they will determine whether the project is a success.

A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team

What should the project manager do?

A.

Send a formal communication regarding the missed milestone

B.

Delay sending a formal communication until the project team catches up

C.

Ask for a meeting with the sponsor to decide whether to send the formal communication

D.

Forego the formal communication and have a conversation with the supervisor

A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.

What should the project manager do?

A.

Advise the teams to follow the company’s existing project management approach.

B.

Allow the teams to continue using their approaches and gradually adapt to a hybrid model.

C.

Let a senior team member select the approach that is appropriate.

D.

Insist the teams both follow either a predictive or agile approach.

A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.

What should the project manager do?

A.

Process a bank loan to pay the payroll of the third-party supplier.

B.

Reassign resources from other projects to pay the third-party supplier.

C.

Explain the third-party supplier situation to the client and request payment.

D.

Inform the client that the project must be delayed until payment is received.

One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority

What should the project manager do to mitigate the risk of not having the materials printed on time?

A.

Meet with the manager to set a high priority for printing the materials

B.

Create a change request to modify the print requirements

C.

Include a risk response in the resource management plan

D.

Purchase a high-volume printer specifically for this project.

A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water

What caused this situation to occur?

A.

The risk analysis was inadequate

B.

The project was completed behind schedule

C.

The requirements gathering was inadequate

D.

The project was delivered above budget

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project's change control board (CCB),

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

A.

Allow team members to resolve personal issues without involving the project manager

B.

Arrange and conduct team-building sessions to improve team effectiveness

C.

Obtain feedback from the isolated team member to understand the situation

D.

Get feedback from other team members to understand what led to this situation

E.

Identify the isolated team member as a risk and document the situation in the risk register.

A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline

What should the project manager do next?

A.

Select resources who are more experienced with the new technology

B.

Perform a root-cause analysis to measure how the new training will address the issue

C.

Include in the risk register a risk of unskilled resources for the new technology

D.

Elaborate and socialize the team charter as per the resource management plan

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

A.

Request for information

B.

Scope statement

C.

Issue log

D.

Risk register

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

A.

Work with the team to understand and solve the issues

B.

Provide testing training to all the project team members

C.

Increase the sprint duration so the testing can be completed

D.

Add a new resource with testing skills to the team

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.

Check with procurement to see if there is another previously used contractor who can develop the task.

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

A.

Analyze stakeholder diversity in the community.

B.

Assess the need to collaborate with the community

C.

Analyze the need to negotiate with the community.

D.

Assess the information requirements of the community

A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.

What should the project manager have done to avoid this?

A.

Planned all required training for the team during the onboarding process

B.

Identified all required skills after the kick-off of the project

C.

Identified all required skills during the planning of the project

D.

Asked the sponsor to identify all required skills during the planning of the project

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?

A.

Review organizational process assets (OPAs) for clarity.

B.

Document lessons learned before closing.

C.

Consult the project charter for next steps.

D.

Confirm the definition of done (DoD) has been met.

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

A.

Work with the product owner to evaluate and prioritize the requirements

B.

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list

C.

Determine the expected benefits of each requirement to maximize the overall business value

D.

Prioritize the requirements based on the hierarchical level of the requesting stakeholders

A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?

A.

Request action from the functional manager regarding the team members poor performance

B.

Avoid selecting the team member to the next project that has an iterative design stage

C.

Provide feedback and coach the team member during the iterative design stage

D.

Escalate the issue to the human resources manager and request that the team member be replaced

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

A.

Use a third-party instant messaging tool.

B.

Use a password-enabled audio/video product,

C.

Use a popular social media platform.

D.

Use a collaborative electronic whiteboard,

A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.

What should the project manager do?

A.

Meet with this team member.

B.

Review this method with the team.

C.

Accept this task-based estimation.

D.

Reject this task-based estimation.

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

A.

Organize a brainstorming session with the project team to address the issue.

B.

Advise the project team on the importance of team engagement,

C.

Invest in coaching and training for all project team members.

D.

Escalate the issue with the human resource (HR) department to take action,

A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?

A.

Schedule training courses to enhance team performance

B.

Add new team members to help the project finalization

C.

Initiate rewards and incentives according to assessment results

D.

Schedule working lunch meetings until the project is complete

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?

A.

Review the benefits management plan

B.

Refer to the lessons learned from the first phase

C.

Consult the project reports from the previous project manager

D.

Collect information from related departments

The project management office (PMO) has recently adopted some agile practices. During an iteration a key stakeholder in the business is concerned with the benefits management plan in the project document repository and mentions that some benefits have not been updated.

What should the project manager do first?

A.

Update the risk register in order to add the issue.

B.

Review the issue log regarding the concern

C.

Revise the benefits management plan

D.

Assess the repository to check for inconsistencies.

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

A.

Revise the project schedule and inform the stakeholders regarding any delays

B.

Revise the project estimates and meet with the project team to discuss delays

C.

Review the management reserve to identify any costs associated with the delays

D.

Review the contingency reserve to identify any delays to the project

Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.

What should the project manager do to engage the stakeholders?

A.

Ask the team to work on the complaint raised by the clients.

B.

Escalate the issue raised by the clients to the project sponsor,

C.

Develop a solution with the team to identify the inventory level.

D.

Work with the team and the product owner to define the next steps.

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important

milestone in a week.

What should the project manager do next?

A.

Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.

B.

Perform market research to find out if there are other vendors that can produce similar kinds of materials.

C.

Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.

D.

Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

A.

Fast tracking

B.

Resource leveling

C.

Critical chain method

D.

Schedule crashing