Spring Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

A.

Request a reserve analysis and update the risk management plan

B.

Update the risk response plan to include the needed reserve

C.

Perform a schedule network analysis to avoid any critical path delays

D.

Review the risk response plan to verify inclusion of the needed reserve

The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.

Which two things should the project manager do? (Choose two)

A.

Inform the customer that moving the milestone has a very high impact on project cost.

B.

Escalate the Issue to senior management so they can impose a solution on the customer.

C.

Convince the customer to keep the requirements as is and not move the milestone.

D.

Review the customer's priorities regarding the desired requirements for the milestones.

E.

Discuss which requirements can be delivered faster with the project team.

A project team is facing challenges understanding how to deliver a project's scope.

A senior subject matter expert (SME) from the organization's global office is in town for 1 week.

What should the project manager do to benefit from the SME's presence?

A.

Ask the SME to review the scope for alignment with the project charter.

B.

Organize a mentoring session with the team and the SME.

C.

Meet with the SME to discuss the current challenges the team is facing.

D.

Review the project scope statement with the SME.

A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?

A.

Advise the team to adjust their work habits and behaviors to allow for better conflict resolution

B.

Call a team meeting to discuss team members' strengths and weaknesses

C.

Establish rules and regulations for team members with consequences if the goals are not reached

D.

Establish team behavior and develop an understating of how to work together

A project manager receives a serious complaint from a functional manager about a

team member. What should the project manager do?

A.

Replace the team member immediately to maintain a good relationship with thefunctional manager.

B.

Discuss the issue with the functional manager to understand the reason for thecomplaint.

C.

Support the team member and provide documentation to the functional managerproving their performance.

D.

Protect the team member and ask the project sponsor to minimize any externalinterruptions.

The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?

A.

Analyze the problem with both teams to figure out If pan of the work must be redone.

B.

Select new team members in an effort to obtain fresh ideas to solve the impasse.

C.

Demand that the business team stop wasting time and define final requirements for the product.

D.

Tell the business team and Scrum team to continue following the initial plan.

A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification

What should the project manager do?

A.

Report the issue during the next status meeting at the end of the week

B.

Escalate the issue to the project sponsor and upper management

C.

Close out the project and tell the manager to open a service desk ticket

D.

Log the issue and assign it to the project team member(s).

During a meeting with a customer, it was determined that participants of the meeting

had different draft versions of an important design document. What should the project

manager do first to ensure that this does not happen again?

A.

Revisit the communication process control.

B.

Ensure only the approved version is shared.

C.

Investigate how draft versions were shared.

D.

Ensure only the latest version is shared.