Spring Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

During the sprint planning of a project, the team members have a disagreement

about the comparative size of the backlog items and if they would fit into the next sprint.

Considering a hybrid approach, what should the project manager do?

A.

Ask an external technical leader to provide input and plan the sprint.

B.

Remove the items from the product backlog since the size couldn't be estimated.

C.

Make the decision about the backlog items based on what makes more sense.

D.

Facilitate the discussion so that the team members can reach a consensus.

A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?

A.

Perform stakeholder engagement with the virtual team

B.

Add status reports to the communications management plan

C.

Convene an on-site meeting for both of the teams

D.

Add status report creation as a product backlog item

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

A.

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

A developer who has almost completed a required product feature for a prototype

leaves the company in the middle of an iteration. What should the project manager do?

A.

Review the backlog to reschedule the deliverable for a later iteration.

B.

Engage with stakeholders directly to review the iteration process.

C.

Determine whether other cross-functional team members are able to take over thework.

D.

Go to management and ask to hire a new external developer.

An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.

Which two project events will assist the project manager to ascertain if this is the case? (Choose two)

A.

Requirements analysis

B.

Retrospective

C.

Sprint planning

D.

Standup

E.

Backlog refinement

A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted

What should the project manager do?

A.

Request stakeholders who understand the technology.

B.

Recommend a change in technology to senior management.

C.

Plan to conduct informal sessions with the stakeholders.

D.

Include the issue in the Issue log and escalate to senior management.

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

A.

Update the project management plan in order to get back on track.

B.

Ensure the team receives continuous feedback from customers users.

C.

Submit a change request to adjust the project scope.

D.

Ensure the team understands all additional project requirements.

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

A.

Update the stakeholder register.

B.

Refer to the resource management plan.

C.

Consult the project sponsor.

D.

Modify the statement of work (SOV).

A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own

What should the project manager do?

A.

Improve the risk management strategy and risk monitoring

B.

Reach out to the project manager of the previous project for assistance

C.

Allow the team member to work through the issue as a training opportunity

D.

Share the lessons learned from the previous protect with the team member

An organization is adopting an agile mindset. On the first agile project, the project

manager faced an issue because the team was unable to make decisions on time.

What should the project manager do to address the problem?

A.

Define clear guidelines on how decisions should be made under the neworganizational policy and reinforce them with the team on every occasion.

B.

Invite senior leadership to a team-building workshop and restate the importance ofaccountability and leadership under the new company direction.

C.

Assess the situation to understand how the organization's culture impacts the decisionmaking process, and coach the team toward a new model.

D.

Adopt an autocratic leadership style and dictate all decisions in order to speed up theteam's velocity.

During a project kick-off meeting the project manager tells team members that they can attend a weekly progress meeting either from home or the office. Which intangible stakeholder engagement quality is the project manager embracing to manage relationships?

A.

Asking and listening

B.

Being collaborative

C.

Managing expectations

D.

Building trust

A retail company identifies that it is losing sales because customers are not promptly

informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.

Considering the objective to deploy customer value, which project life cycle approach should be chosen?

A protect manager is managing a project that will handle sensitive data for millions of users The sponsor mentioned that, lo their knowledge, the project does not seem to have any compliance requirements in their country.

What should the project manager do in this situation?

A.

Request expert advice from the compliance leader to confirm if there are any compliance requirements for the project.

B.

Check with The national compliance agency to determine if the project has any compliance requirements in this country

C.

Trust in the expertise of the sponsor and believe that there are no compliance requirements for this project.

D.

Conduct independent research regarding the data protection policy of the country for legal and regulatory compliance.

An agile leader is working on a complex project that is entering the final phase where solutions from different vendors are being integrated. This is the most critical delivery stage for the project

How should the agile leader ensure successful delivery?

A.

Ensure participation from all team members

B.

Ask the client to attend all daily calls.

C.

Ensure cross-departmental teams are colocated

D.

Request additional project resources

A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.

A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.

What should the project manager do?

A.

Include the new requirement in the next iteration of the software without informing the sponsor.

B.

Inform the team that the sponsor decided to reject any changes and release the software as is.

C.

Release the software as is and start a new project to deliver the new requirements.

D.

Collect the requirements of the regulation and follow the change control process.

An agile project has a documented list or requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.

What should the project manager recommend?

A.

Ensure the product owner determines the priority based on a product roadmap. release plan, and iteration plan.

B.

Ask the team to prioritize the high-priority items based on what they feel is a logical sequence to build.

C.

Ask the team to prioritize the high-priority Items based on the release plan and what allows tor testing most effectively.

D.

Discard the current categorization of requirements as high, medium, and low and prioritize numerically.

A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype

What should the project manager do to accelerate this solution?

A.

Contact the other project team and ask them to organize a demo of the prototype

B.

Perform iterative planning with the team to use the prototype

C.

Check the burnup charts to see what progress has been made to integrate the solution

D.

Prioritize the backlog with the customer to remove the feature

A project manager is leading the first agile project for the organization. During the

kick-off meeting, the project manager notices that the team does not have the same

understanding about agile approaches. The project manager is concerned about the impact of that confusion.

What should the project manager do to address this situation?

A.

Evaluate the possibility of managing this project using a predictive approach.

B.

Submit a change request for a new team that has agile experience.

C.

Mentor the team to explain agile principles and create a shared understanding.

D.

Hire a functional manager who is familiar with agile methodologies.

A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.

Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)

A.

Organizational process assets (OPAs)

B.

Lesson learned registers from past projects

C.

Historical issue logs

D.

Project scope statement

E.

Project management plan

A project manager recognizes that a key stakeholder is not engaged in the project and does not seem interested in the project status. The project manager is concerned that the project may go off track if the stakeholder expectations are not met

How should the project manager approach the stakeholder?

A.

Analyze the stakeholder's expectations and emphasize the topics of interest that may influence the project's success

B.

Post regular updates to the project teams board and email the stakeholder when they are posted so the stakeholder can review at their convenience

C.

Schedule regular review sessions with the stakeholder and the project team so the stakeholder can understand the status and engage with team members

D.

Continue to send status reports by email and schedule one-on-one sessions with the stakeholder so they are regularly debriefed on the project status

A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies

When should the risks be reviewed to ensure alignment between the project team and the stakeholders'?

A.

During the risk register update

B.

During the retrospectives

C.

During each steering committee meeting

D.

During each iteration and review

us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

A.

Review project cost because the project is over budget and ahead of schedule

B.

Review project schedule and cost because the project is over budget and behind schedule

C.

Review project schedule because the project is under budget and behind schedule

D.

Review project scope because the project is under budget and ahead of schedule

A project manager is establishing a project management office (PMO) for a

company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.

Which activity should the project manager use to help train the stakeholders?

A.

Contract negotiation

B.

Team assessment

C.

Mentoring and coaching

D.

On-the-job training

A project sponsor has requested a trend analysis of all risks that the project has

monitored over the past 12 months. What should the agile project manager do?

A.

Share the annual report with the sponsor.

B.

Organize a stakeholder meeting to brainstorm on general project risks.

C.

Extract this from the project risk register tracking tool and issues log.

D.

Refer the sponsor to the contract document.

A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members The project manager tells the new team member to align with the team's principles and arrive on time

What kind of conflict resolution did the project manager apply in this situation?

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Collaborate/problem solve

D.

Force/direct

During project execution, an important stakeholder threatens to withdraw support

for the project, citing a lack of transparency and accountability in the way the project is being

executed. What should the project manager do to handle this situation?

A.

Approach the stakeholder to address the concerns.

B.

Consult the risk management plan.

C.

Escalate the issue to the project management office (PMO).

D.

Refer the stakeholder to the project sponsor.

A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.

What should the project manager do?

A.

Provide a software for instant messaging.

B.

Document all information on the team wiki.

C.

Promote the use of remote site syndication.

D.

Facilitate regular conference calls.

Throughout an entire project, the project manager took notes at every meeting with

team members. These notes provided useful insights from key stakeholders, which later

resulted in increased value to the project. The project manager thought it would be helpful to

keep these notes as a future reference for other project managers within the organization.

Where should the notes be located?

A.

Lessons learned

B.

Organizational process assets (OPAs)

C.

Enterprise environmental factors (EEFs)

D.

Project management plan

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

A.

Instruct the team to accommodate the changes to the project

B.

Review the project charter to identify the agreed scope

C.

Negotiate the impact of these changes with the client

D.

Escalate the issue to senior management

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?

A.

Send an email update to existing team members about the addition of the new teammembers.

B.

Set up a weekly meeting with the new team members for a couple of months.

C.

Request the transfer of the new members to another project, citing a risk of confusion.

D.

Update and share the guideline document dealing with team communication.

A key resource is newly assigned to a project. The project manager and the resource

did not get along well in a previous project. This resource is needed to ensure the completion

of a major component for the project.

What should the project manager do?

A.

Work on resolving the differences with the key resource and building a good workingrelationship to ensure project success.

B.

Monitor the key resource closely throughout the project, but do not let the projectsponsor know about the conflict.

C.

Request that the key resource's functional manager work directly with the resourceduring the project.

D.

Discuss this with the project sponsor and request that this key resource be replaced onthe project.

A project to implement a new process is still in development. When implemented,

the company will benefit by a reduction in utility costs. The project financial evaluation

indicates a payback of 3 years.

What should the project manager do to expedite the project delivery?

A.

Increase resources on the technical design to enable a decision to proceed as this is aquick return project.

B.

Increase the time spent on project development to improve the level of confidence tovalidate the financial evaluation.

C.

Conduct a stakeholder survey with the plant operators to establish the probability ofthis project reducing the cost of utilities.

D.

Stop any further project development and commence with the implementation as thereis no need to seek further approval.

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?

A.

Document the risk register in the project charter.

B.

Speak to the customer and add the issue to the issue log.

C.

Review user roles and update the team charter.

D.

Involve the product owner to rewrite the user stories.

A project manager is executing a project where an external vendor will provide some deliverables Alter awarding the contract to the vendor the project manager is informed that the vendor is running behind schedule on a separate project Finding another vendor will exceed the budget

What should the project manager update first?

A.

Issue log

B.

Lessons learned register

C.

Stakeholder engagement plan

D.

Risk register

A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?

A.

Stakeholder analysis

B.

Resource needs analysis

C.

Accommodations assessment

D.

Team member assessment

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

A.

Instruct the team to work as planned and Ignore the stakeholder's requests.

B.

Escalate the situation to upper management.

C.

Add more team members to make up for any project delays.

D.

Address the issue with the stakeholder and explain the situation.

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

A.

Seek the sponsor's approval to extend the project schedule.

B.

Set up a meeting to perform a root cause analysis.

C.

Update the issue log and communicate it to the team.

D.

Permanently colocate the team for better performance.

A project manager is in the process of creating a strengths-based team and is

organizing a series of workshops to identify and document the strengths of each project team

member. During this session, there are multiple team members who are not actively

participating. These meetings are becoming futile due to a lack of participation.

What should the project manager do?

A.

Have a one-on-one discussion with each team member to emphasize their individualtalents.

B.

Document the behavior of the team members and highlight it during their performancereviews.

C.

Identify the team members who are not participating and reprimand them.

D.

Explain the benefits of the approach and the effects of positive psychology.

A project team that is very experienced in enterprise resource planning (ERP)

systems implementation is currently planning the delivery of a new ERP project. There is a

requirement to reuse the client's security subsystem developed by a third party. The client

states that integration with the security subsystem must be done by the client's team. The

project manager does not want to have such an external dependency.

What should the project manager do first?

A.

Plan the implementation of this integration in the first iteration to help reduce risks.

B.

Record the issue in the issue log and closely manage this dependency.

C.

Inform the client that the project team will take care of the integration.

D.

Document the client's responsibility for the integration with the security subsystem.

A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority. What should the new project manager do next?

A.

Refer to the project charter

B.

Review the project resource matrix

C.

Assess the stakeholder register

D.

Update the communications management plan

An issue reoccurs six months after a project's go-live date despite being resolved

during the project life cycle. What should the project manager have done in the previous

phase to avoid this issue?

A.

Ensured the project team documented lessons learned about the issue

B.

Ensured the project team applied a long-term solution for the issue

C.

Asked the project team to conduct more testing with users

D.

Discussed the issue with the stakeholders

A project manager is assigned to a new water treatment plant project that has been

delayed for many years. It is revealed in the project charter that the sponsors of this project

are from three different business units. This is the first time the sponsors have ever

implemented such a project.

What should the project manager do?

A.

Establish mentoring and coaching sessions.

B.

Review the knowledge repository for similar projects.

C.

Schedule the project kick-off meeting immediately.

D.

Meet with the project sponsors to align expectations

An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives

What should the project manager do?

A.

Schedule team-building activities to encourage collaboration among the team

B.

Coach the team members to resolve the gaps in understanding

C.

Conduct a kick-off meeting and communicate the goals and objectives of the project

D.

Continue the meetings and communicate the goals and objectives to resolve the gaps

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

A.

Motivate the team and deploy the necessary resources.

B.

Find a way to maintain the project schedule.

C.

Impose authority on the project.

D.

Request additional resources from the sponsor and motivate the team.

A project requires testing of the final product to be done at another department's

testing facility, which is known for having low availability. This situation could potentially

impact the project schedule.

What should the project manager do next?

A.

Update the risk register.

B.

Update the issue log.

C.

Update the lessons learned register.

D.

Update the project schedule.

During the executing phase, a project manager is reviewing the issue log and finds

there are outstanding high-priority issues that are still open. Most of the open issues require

effort from external domain experts who are not on the project team.

What should the project manager do?

A.

Ask the issue reporter to close the issues, because there are no project team memberswho have the required domain knowledge.

B.

Review the open issues with the issue reporter and issue a change request to hire anexternal domain expert.

C.

Request that the project team members learn the required domain knowledge andresolve the open issues in a short time.

D.

Reduce the project scope to ensure that the project team has the knowledge to deliverthe system on schedule.

An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time

What should the project manager have done to avoid this delay?

A.

Updated the stakeholder engagement plan to reflect a change in the product owner

B.

Communicated the status of the project more frequently with the product owner

C.

Updated the communications management plan to reflect a change in the communication needs

D.

Reevaluated the new product owner's needs for better engagement

A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office's (PMO's) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO's status reports have sufficient enough information

How should the new project manager proceed*?

A.

Continue using the outgoing project manager's status reports as well as their approach for schedule reporting

B.

Explain to the PMO that the hybrid project team needs to keep an agile approach for reporting and will not be complying with the organizational standard

C.

Change the status reports according to the template supplied by the PMO and proceed with scheduled reporting

D.

Meet with the project stakeholders to explain the need to comply with the PMO standards and update the status report format accordingly

A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.

What should the previous project manager have done to prevent this issue?

A.

Built a pair-engineering environment so that experienced engineers always work with junior engineers to assist in knowledge transfer

B.

Contracted with a third-party test lab to outsource all testing processes and required that they produce all test reports

C.

Led a technical benchmark workshop every month to share state-of-the-art technology trends and ask all team members to attend the workshop

D.

Built a shared repository for the project in the internal server and asked the team to create record and save all project deliverables to the server