Spring Sale Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager's organization is engaged in an internal project, project B, that is about to end.

What should the project manager do?

A.

Prioritize project A over project B since A is an external project and B is an internal project.

B.

Plan projectA in sprints, starting with the module that does not require machine learning skills.

C.

Engage the human resource manager to employ a machine learning expert for project A.

D.

Plan project A to start at the end of project B when the machine learning expert is available.

An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.

What should the project manager do?

A.

Provide feedback to the team and conduct a meeting to review the team rules.

B.

Provide feedback to the team and conduct a retrospective meeting to find a root cause.

C.

Provide feedback to the team and request agile training for the new member.

D.

Provide feedback to the team and coach the new team member in agile methodology.

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.

Review the operations manager's concerns and ensure these concerns are addressed

C.

Escalate the concerns to the project sponsor and discuss options to address them

D.

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.

During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?

A.

Stakeholders are satisfied with the current status.

B.

The project is under budget and on schedule

C.

The project is aligned with the project charter

D.

The protect is aligned with the benefits management plan

A project manager is working on a major construction project. Part of the

agreed-upon plan was to use a cloud-based system with a server that runs on high-speed

internet service since most of the team members work virtually. The company needs to

reduce operating costs as much as possible and management insists that the project will

now use a system running on a conventional dial-up service.

What should the project manager do next?

A.

Evaluate the impact of this decision and communicate with management.

B.

Agree with management and continue working the project management plan.

C.

Meet with management about their decision and ask them to get another project manager.

D.

Replace some of the team members that work virtually to help the company save money.

At the end of planning a new project, the project manager needs to schedule the

kick-off meeting but is having difficulty finding a common time slot when all necessary

stakeholders can be available onsite. How should the project manager proceed to

schedule the kick-off meeting?

A.

Email all stakeholders with the objectives of the project and ask for feedback.

B.

Wait for a date when all required attendees can be available onsite.

C.

Run separate meetings to accommodate everyone's schedule.

D.

Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.

In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.

What should the project manager do to handle this situation?

A.

Give team members more authority to make decisions.

B.

Perform team-building activities and enhance collaboration.

C.

Identify the team members who are impacting low morale.

D.

Coach the team members on agile processes and knowledge.

The portfolio management office wants to cut costs by suspending some ongoing

projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio

management office has not backed down on their plan.

What should the project manager do to continue the project?

A.

Meet with the project team and revise the project goals.

B.

Update the project charter to make it align with organizational strategy.

C.

Demonstrate the project alignment to the organizational strategy.

D.

Escalate the issue with the project sponsor to request support.

A project manager works for a large software development company that has multiple strategic business groups. The project manager has been assigned to develop maintenance planning software for a power plant. The project manager heard that a similar project that was executed by another business group in the company recently failed. The project manager is concerned about the project's performance and wants to take steps to help the project succeed. What should the project manager do?

A.

Evaluate the project risk and try to replace the project with another one within the organization.

B.

Inform the project sponsor about the risk and try to convince them to withdraw the project.

C.

Study and apply the lessons learned from the failed project so that this project does not follow the same pattern.

D.

Continue executing the project using the project manager's usual methods as all projects are unique.

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?

A.

Ask stakeholders to communicate with the project manager and not directly with the team

B.

Empower the team members to remove obstacles and blockers

C.

Address and remove obstacles and blockers for the team

D.

Add blockers to the issue log and risk management plan

A project manager is meeting with the project sponsor regarding a new project.

The project manager tells the sponsor that, as part of the communications management

plan, a weekly email will be sent with the status of the project, so the sponsor can be

informed of the progress. The sponsor indicates that the email is not necessary because

they will ask for a status update whenever it is needed.

What should the project manager do next?

A.

Advise the project sponsor to request a 15-minute meeting, whenever necessary, with prior notification.

B.

Agree to the project sponsor's request, but continue to copy them on the weekly email so they can be informed of progress in case it is needed.

C.

Tell the project sponsor that if they prefer to not receive the communication, there is no problem in removing them from the email distribution.

D.

Ask the project sponsor what sort of information is needed and agree on a frequency for the communication.

A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?

A.

The team with the higher velocity is performing better and should be rewarded.

B.

The issue should be addressed as part of a retrospective in the next iteration.

C.

The velocity should not be compared as teams can size items differently.

D.

The velocity of both teams should be compared at the end of every iteration.

A contractor delivering construction services to a company is using agile principles

to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design

changes or performing rework.

What should the project manager do to minimize the cost?

A.

Put the project on hold until all definitions are ready in order to avoid rework.

B.

Review the backlog with the product owner and prioritize the tasks that are least likely to be affected by a change in legislation.

C.

Capture the engineers' feedback at the daily meeting and communicate it to the product owner.

D.

Cancel the project release resources, then start again when all the definitions are ready.

A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.

How can the project manager convey these benefits to the stakeholders?

A.

Rebaseline the project schedule to show the current status of the project.

B.

Create a benefits management plan mapped to the organization's strategic objectives

C.

Perform a project cost-benefit analysis for the stakeholders

D.

Update the deliverables map against the agreed-upon project requirements

A team has been working together for several months and has successfully

delivered work. A new team member has joined the team but is having difficulty

contributing.

What should the project manager do to help the new team member integrate effectively?

A.

Give the new team member time to contribute until they ask for help and support.

B.

Assign the new team member tasks so that the team member knows on what to focus.

C.

Approach the team member to identify any issues and then plan a resolution accordingly.

D.

Review the project with the team member to ensure the project scope is understood

An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?

A.

Accept risks as they decrease over a period of time.

B.

Create a risk value profile to track the relative importance of risks.

C.

Log and track risks separately as only business value is important.

D.

Assess risks together with business value during prioritization.

A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?

A.

The communications management plan was not used by all stakeholders.

B.

Organizational assets were not available to back the rationale.

C.

Relative estimation by the team resulted in two estimates.

D.

The use of the Monte Carlo method can result in different estimations.

A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?

A.

Discuss with the product owner that the user story will not be completed this iteration.

B.

Meet with the team member's functional manager to try to remove the impediment.

C.

Tell the project team member not to work on the production issue and to inform their manager.

D.

Escalate the issue to the project sponsor to resolve and adjust the project burndown chart.

A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.

What is the first thing the project manager should do"?

A.

Include the requirement into the project and schedule it as soon as possible

B.

Inform the project sponsor about the situation and request assistance

C.

Evaluate the impact that the inclusion of this new requirement will have on project performance

D.

Inform the stakeholder that it is impossible to add new requirements to an approved project scope

A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.

What should the project manager do?

A.

Inform the stakeholder that the new requirement will be considered in the next release planning session.

B.

Inform the sponsor of the latest changes and ask the sponsor to prioritize the features.

C.

Ask the product owner to determine if this requirement needs to be treated as a top priority.

D.

Direct the development team to work on this requirement right away.

During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.

What should the project manager do first?

A.

Communicate the problem to the sponsor to force the key member to be maintained on the project.

B.

Initiate a change request and replace the key member as soon as possible.

C.

Explain to the company the importance of maintaining the key member on the project according to the vision of the project.

D.

Evaluate the impact of the key team member's removal from the project, look for alternatives, and submit a change request if required.

During an iteration demo, a customer noticed an enhancement they would like to make to the product. What should the team do next?

A.

Refine and estimate the enhancement so the size is known.

B.

Add it to the product backlog to be completed in the future.

C.

Start working on the enhancement for the customer immediately.

D.

Ask the product owner to prioritize the item with the customer.

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal andexternal resource requirements.

B.

Commit each team member's time and deliverables and aim for overall projectcompletion.

C.

Continue the project implementation without the site engineers to ensure the scheduleis maintained.

D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.

The project manager realizes that the product owner has a lot of potential but is lacking communication skills. How should the project manager help the product owner to develop these skills while executing the project?

A.

Ensure there are opportunities for the product owner to present project reviews to the stakeholders.

B.

Suggest that the product owner attend a training session about assertive communication.

C.

Suggest that the product owner shadow colleagues who are good presenters.

D.

Recommend a specialized article about delivering effective presentations to the product owner.

A project manager is working on a complex project and is unsure about planning, executing, monitoring and controlling the project. Match the phrase on the left with the correct statement on the right.

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?

A.

Engage the services of an interpreter who understands the project domain.

B.

Check social media to determine if there are any common connections that use the new supplier.

C.

Request assistance from the procurement department on the next steps.

D.

Become aware of any cultural characteristics of the new supplier that could impactnegotiation.

At the end of a project, one of the suppliers is facing financial difficulties and is

pushing the project manager to obtain financial, legal, and administrative approval in order to

communicate formal project closure and ensure the transfer of liability. What should the

project manager do next?

A.

Compare the achieved results to the contract requirements.

B.

Make the final payment as the project is completed.

C.

Transfer the remaining variances and close the project.

D.

Escalate to higher management to expedite the approval.

A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory-How should the project manager support their claim to the vendor?

A.

Share unsuccessful results from previous projects with a similar scope

B.

Provide the failed test results along with the agreed-upon acceptance criteria

C.

Show that the acceptance criteria were changed by the vendor without approval.

D.

Document in the risk log that the issues in the system were already identified

A project manager has been assigned with initiating a large project to deliver

complex equipment. Part of the project will be the result of a long research process, but once

this is completed, the other part of the project must be incrementally delivered to the

customer.

Which approach should the project manager choose for this project?

A.

Agile

B.

Waterfall

C.

Predictive

D.

Hybrid

A project manager is developing a project baseline schedule and has started to

assign team members to the project activities according to their function. What should the

project manager do in this phase?

A.

Develop project onboarding guidelines for the team members assigned to the project.

B.

Ensure that a kick-off meeting is planned and invite relevant stakeholders toparticipate.

C.

Ensure that lessons learned are considered as part of the project scheduledecomposition.

D.

Confirm that no conflicts exist in resource calendars with assigned activities on otherprojects.

A company is conducting a digital transformation project that has a hard deadline.

The marketing team wants to combine this implementation with a new product, and the newly

assigned project manager is not aware of all the dependencies.

Using a hybrid approach, what should the project manager do to ensure the dependencies are

taken into consideration?

A.

Implement a project newsletter so the different team members can be informed aboutthe progress of each project.

B.

Combine all of the small projects into one big project so the team can collaboratebetter as one big team.

C.

Facilitate communication promoting a Scrum of Scrums so the different teams areaware of the dependencies and progress.

D.

Make sure that each individual project schedule is aligned with the common deadlines.

A team Is experiencing difficulties and has decided to use a spike. Please click on the portion of the burndown chart that corresponds to the spike.

A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder's presence has had a negative impact on the team's morale, while also impacting productivity

How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?

A.

Set up a meeting with the stakeholder to address their concerns directly

B.

Move to a predictive design-and-requirements gathering approach

C.

Talk to the team separately to address the stakeholder's concerns

D.

Schedule a team retrospective and invite the stakeholder

An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed

What action should the project manager take?

A.

Escalate the issue from the IT team to management and get the validation prioritized

B.

Work with the IT team to prioritize the validation and release of the new features

C.

Deliver the features when the IT team is able to validate them

D.

Request the IT team to immediately release the product and then validate the features

A project has been running for 2 months and now requires approval for a supplier to

begin some execution tasks. The project team has evaluated several suppliers and selected

their top two preferred suppliers. The project sponsor requested that another supplier who has

lower costs be added to the list. However, the project manager is aware that this supplier

does not always fulfill the project requirements.

What should the project manager do?

A.

Set up a requirements review session and obtain agreement for selection criteria.

B.

Recommend to the team to add the sponsor's preferred supplier to the list.

C.

Choose the sponsor's preferred supplier for the project to avoid conflict between theteam and sponsor.

D.

Recommend to the sponsor to review the results of the team's supplier evaluation.

A project manager has been assigned lo an important agile project During protect execution, a vendor was approved to produce the project deliverables. What should the project manager do to ensure project continuity between the vendor and the team?

A.

Request that the vendor provides a manual with all required knowledge

B.

Implement retrospectives with the vendor to gather the required knowledge

C.

Submit a change request to extend the vendor's contract to provide formal training for the team

D.

Conduct daily knowledge transfer standups to ensure that the team is properly trained

A project stakeholder has expressed concern that the established success criteria for

the project are not being met. What should the project manager do next?

A.

Review the established project benefits tracking metrics.

B.

Update the project business case document.

C.

Document the agreed-upon ownership of benefits realization.

D.

Create a project benefits management plan.

A project manager is working on a highly complex project. During the execution of

the project, the local government changed certain environmental regulations, which could

potentially delay the project.

What immediate action should the project manager take?

A.

Update the issue log.

B.

Update the project baseline.

C.

Update the risk management plan.

D.

Update the change request log.

A project is in the execution phase During a few planning sessions the team brought up dependencies and risks based on their knowledge of other project. The project manager also received questions from the company in terms of how and when the team planned to perform acceptance testing and training activities

What should the project manager do next?

A.

Document the project management plans and share them with the company and all team members via email for review

B.

Create a log to track risks assumptions issues and dependencies and establish a periodic review with the stakeholders

C.

Add contingency m the schedule to account for dependencies and risks then review rt with the team

D.

Engage with the company and the project team to determine the best course of action

An organization started the process of a digital transformation and is trying to change

its culture from a predictive to a more agile approach. The project manager leading the

change management process identified some knowledge gaps of key team members, which

could prevent the transformation from happening as planned.

What should the project manager do?

A.

Provide mentoring for the key team members on agile practices and support the teamwith training and encouragement.

B.

Create an agile conduct guideline and ensure that all team members follow the rulesstated in the document.

C.

Replace the key team members with new resources who are already aware of the agilemindset.

D.

Provide directions to the team members on how to accelerate the company'stransformation, bringing the project back on track.

A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days

What should the project manager do first to maintain the project team's performance level?

A.

Initiate a performance-based bonus for the team members to provide them with a monetary incentive

B.

Remind the team frequently that the project must be delivered on time and within budget

C.

Invite the team to a team-building event to alleviate their stress while strengthening teamwork

D.

Provide routine mentoring and coaching to the team members to identify any demotivating issues

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?

A.

Become a servant leader by supporting team collaboration and removing impediments

B.

Delegate coordination activities to the product owner so the project manager can locus on managing collaboration

C.

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination

D.

introduce new communication tools to the project team members

A project manager has been assigned to a new project. There is one team member

who never says anything during meetings. After meetings, however, the team member sends

detailed emails with very good suggestions that help with project execution.

How should the project manager guide the team members?

A.

Review the communications management plan with the team members.

B.

Remind the team members to follow the team charter.

C.

Motivate the team members to speak freely in the meeting.

D.

Arrange a team-building activity to involve all team members.

An agile team has started a new project. When should the project manager organize their first team retrospective?

A.

When the team completes a release of a monumental increment

B.

When the team reaches a major milestone

C.

When more than a few weeks have passed

D.

When the work is progressing well through the team

During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?

A.

Let the product go to market and wait for customer feedback regarding quality

B.

Ask the quality manager to include the final user tests in the quality management plan.

C.

Submit a change request to analyze a new set of quality tests

D.

Ask the product manager to include the final user tests in the quality management plan

A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.

What should the project manager do?

A.

Use the agile approach in the new project and schedule agile training for those stakeholders who are new to this approach

B.

Continue to use the predictive approach m the new project since it is the approach the stakeholders are familiar with using

C.

Share the pros and cons of adopting an agile approach for the new project only with the team and ask them to decide which approach to use

D.

Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project

When a project manager is trying to determine a leadership style to use on a project what should they consider?

A.

Number of tasks on the protect

B.

Culture of the organization

C.

Project timeline

D.

Experience of the project manager

A hybrid project is experiencing several issues with both the agile delivery of the

product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?

A.

Refer to the stakeholder engagement plan.

B.

Set up a conference call for all stakeholders.

C.

Refer to the communications management plan.

D.

Send an email to all stakeholders.

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

A.

Remove the items no longer applicable from the backlog and present the backlog to the project team

B.

Continue working on the defined scope and review the risk matrix

C.

Have a discussion with the project sponsor and cancel the project

D.

Have a discussion with the sponsor and recommend the project business value be reassessed

After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?

A.

Perform a qualitative risk analysis and update the risk register.

B.

Submit a change request through the Integrated change control process.

C.

Update the issue log and discuss It in the next steering committee meeting.

D.

Estimate the associated costs and increase the project budget accordingly.