Halloween Special - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

Two project team members are updating the schedule but cannot reach an agreement on when two milestones are due. Each team member believes they are correct based on the documents they have available.

What should the project manager do first to finalize the schedule?

A.

Engage the two team members to investigate the reasons each believes that their documents are correct.

B.

Update the schedule so it is available for team members to continue the work and figure out the discrepancy later.

C.

Ask the two team members to meet to work the discrepancy out and let the project manager know the outcome.

D.

Ask the team members to send the documents and apply expert judgment to update the schedule.

A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.

What should the project manager do?

A.

Define a risk management plan (or the new approach, as needed.

B.

Review the benefits realization plan to include the cost of the change.

C.

Define a project management plan for the new approach, as needed.

D.

Review the communications management plan to identity new stakeholders.

A project manager has been assigned a project team with members in two different locations. The project manager noticed that the productivity of a senior team member in the other location is much lower than the local junior team members.

What should the project manager do to address the issue?

A.

Share a work performance report with the team member's supervisor.

B.

Assign a mentor to work with the senior team member.

C.

Speak with the senior team member to identify the difficulties.

D.

Collect feedback from all team members about team performance.

A project is late due to a large number of scope changes. This was raised as a risk in the risk register during the initiation phase. The team is afraid that they will be blamed in case of failure and recommends that the project manager ask for an extension.

What should the project manager do first?

A.

Ask the sponsor for their advice on the way forward.

B.

Ask the team to document the impact of the risk in detail.

C.

Refer to the risk register and follow the mitigation plan.

D.

Refer to the change log and ensure that changes are documented.

A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause

analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.

What should the project manager do next?

A.

Review the change control process to ensure quality management artifacts are updated as part of the change.

B.

Review the quality management process and perform a process audit as part of ongoing quality assurance.

C.

Review the communications management plan to ensure change requests are communicated to the affected team members.

D.

Review the quality management process with the project management office (PMO) to ensure compliance with best practices.

During execution of a complex project, the project manager encounters numerous change requests from various teams. These changes may result in the project not meeting its objectives.

How should the project manager ensure that these changes are managed effectively?

A.

Include the changes in the backlog and review priorities with the product owner.

B.

Record the changes using the risk register and continue monitoring.

C.

Deny the change requests and keep delivering the project as planned.

D.

Review the project and communications management plan with the main stakeholder.

An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.

What should the project manager have done first to avoid this situation?

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

A project manager is leading a hybrid project and is collaborating with the client to develop the project contract.

Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked the project manager if the contract deadlines can be met.

What should the project manager do first?

A.

Study the contract terms and deadlines to ensure they are not under risk and confirm them with the stakeholder.

B.

Clarify the current work progress, causes for delays, existing risks, and planned corrective actions.

C.

Submit a request for extra time and budget related to the dependencies and technical difficulties.

D.

Ask the stakeholder to remain calm and confirm that they are participating in all team meetings.

A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more What should the project manager do next?

information to be shared.

A.

Inform the stakeholder to wait for the annual stakeholder review meeting

B.

Schedule a meeting with the stakeholder to better understand their request

C.

Update the project communications management plan immediately

D.

Consult the scope baseline document to track project updates

A project is on its second iteration out of six. The team realizes that a key deliverable will depend on the acquisition of a new device.

What should the project manager do?

A.

Register a risk and escalate it to the project sponsor.

B.

Include the responsibility for acquisition with the core team.

C.

Detail the reason for the deliverable delay in the status report.

D.

Invite the stakeholders to discuss prioritization of a new deliverable.

A project manager is leading a project team composed of members with varying levels of knowledge and

experience. Some are experts and some have less than 1 year of experience. The project schedule was approved by the steering committee.

What should the project manager do?

A.

Ask the less-experienced members to perform tasks exactly as they are instructed by the experienced members.

B.

Ask each experienced member to be the mentor to one of the less-experienced members.

C.

Ask the more experienced members to review all of the tasks performed by the less-experienced members.

D.

Ask the resource manager to replace the less-experienced members with more experienced team members.

A project team needs to create artifacts for an upcoming steering committee.

What should the project manager do first?

A.

Use templates from an existing project.

B.

Ask the project management office (PMO) for guidance.

C.

Surveying peers to understand what templates they have used.

D.

Lead the project team in finding the best templates.

A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?

A.

Add more items to the sprint backlog that will add value.

B.

Complete the sprint and seek a waiver from the regulator.

C.

Complete the sprint, but do not release the deliverable.

D.

Perform a sprint risk assessment and analyze challenges.

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle.

What should the project manager do next?

A.

Escalate the obstacle to a servant leader for resolution.

B.

Make changes to reprioritize the backlog because of the obstacle.

C.

Reject the obstacle and present the partial solution to the customer.

D.

Focus on generating business value despite the obstacle.

A project manager who has been working on an ongoing volatile project is retiring. A new project manager is collaborating with the retiring project manager to ensure a smooth transition.

What should the new project manager first discuss, review, and clarify during the transition meetings?

A.

Resource management plan

B.

Change management plan

C.

Lessons learned log

D.

Risk register