Two project team members are updating the schedule but cannot reach an agreement on when two milestones are due. Each team member believes they are correct based on the documents they have available.
What should the project manager do first to finalize the schedule?
A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.
What should the project manager do?
A project manager has been assigned a project team with members in two different locations. The project manager noticed that the productivity of a senior team member in the other location is much lower than the local junior team members.
What should the project manager do to address the issue?
A project is late due to a large number of scope changes. This was raised as a risk in the risk register during the initiation phase. The team is afraid that they will be blamed in case of failure and recommends that the project manager ask for an extension.
What should the project manager do first?
A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause
analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.
What should the project manager do next?
During execution of a complex project, the project manager encounters numerous change requests from various teams. These changes may result in the project not meeting its objectives.
How should the project manager ensure that these changes are managed effectively?
An important project to build a new airport was suddenly stopped because of complaints from residents in the surrounding communities. The residents stated they were not consulted and that the project would cause ecological and pollution damage.
What should the project manager have done first to avoid this situation?
A project manager is leading a hybrid project and is collaborating with the client to develop the project contract.
Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked the project manager if the contract deadlines can be met.
What should the project manager do first?
A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more What should the project manager do next?
information to be shared.
A project is on its second iteration out of six. The team realizes that a key deliverable will depend on the acquisition of a new device.
What should the project manager do?
A project manager is leading a project team composed of members with varying levels of knowledge and
experience. Some are experts and some have less than 1 year of experience. The project schedule was approved by the steering committee.
What should the project manager do?
A project team needs to create artifacts for an upcoming steering committee.
What should the project manager do first?
A project is nearing the completion of a sprint when the product owner announces that a local regulator has banned part of the deliverable. What should the project manager do?
A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle.
What should the project manager do next?
A project manager who has been working on an ongoing volatile project is retiring. A new project manager is collaborating with the retiring project manager to ensure a smooth transition.
What should the new project manager first discuss, review, and clarify during the transition meetings?