A project to build a new energy plant was just completed. However, a few days before operation of the plant, the local community protested and closed access to the plant. They argue that an important natural reserve was impacted and prior consultation was not done by the project team.
What should the project manager verify first?
A company recently adopted agile to develop innovation projects. The project manager is experiencing problems with some team members who consider some agile ceremonies to be unnecessary.
What should the project manager have done before the beginning of the project?
A project team is using a vendor solution. The project team has been notified that the vendor solution will no longer be on the premises, but in the cloud. The cloud transition will require additional infrastructure resources and adherence to new security standards.
What should the project manager do first?
A project is delivered using a hybrid approach. In the daily meeting, one of the developers informs the team that the business that will implement the next version of the product has a new manager. There is one more sprint before the new version of the product enters the staging phase.
What should the project manager do?
A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.
What should the project lead do?
A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.
What should the project manager do to avoid these situations?
A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.
What should the project manager do to support the backlog prioritization?
A large matrix organization is adopting a new communications approach. This is necessary because their projects often require the resourcing of expert knowledge in the form of specialists from various departments and divisions.
What should the project manager do to set up effective communications?
A project manager has been asked by the human resources (HR) review team to share information about how the project team members interact, communicate, and conduct themselves to reduce the risk of conflicts and improve overall team performance.
What should the project manager do next?
In a global project, the main definitions were developed in country A, and the delivery of the project will be completed in phases in countries B, C, and D. Country B discovers that one of the legal requirements was not addressed.
What should the project manager have done to avoid this situation?
A project has progressed significantly and is getting close to completion. The project manager observed that team members are no longer focused and have started arriving to work late.
What should the project manager do?
Drag the items on left side to the matching term within the correct project approach on the right side.
In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.
What should the project manager do?
Update the issue log and refer to the resource management plan to address the situation.
Ask the team for extra work to fulfill the project commitment.
Reduce the scope of the project and inform stakeholders.
A project manager has been assigned to an existing infrastructure project. The current project manager, who is retiring, and the project sponsor have had a good working relationship for many years. The project sponsor has expressed dissatisfaction with having a new project manager assigned to the project.
What should the project manager do?
The sponsor calls the project manager and questions why the stakeholders have not received updates for over 1 month. The project recently implemented a project management information system (PMIS) that provides real-time access to various project status measurements and information. The project manager is certain that all stakeholders have the opportunity and permissions for status updates.
How should the project manager proceed?