A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.
Which response should the risk manager recommend for these risk items?
The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.
What should the project manager do?
In the early stages of a manufacturing project, a risk manager has identified a risk with a component provided by an external supplier that might be delayed. The delay may or may not be significant to the project.
What should the risk manager do?
A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.
What should the risk manager do first?
A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company's business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk owners that the exposure from two high-impact risks are hitting the risk thresholds.
What should the project manager do next?
While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?
A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.
What should the risk manager do to mitigate the chance of the same issues reoccurring?
A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.
How should the risk manager address this concern?
Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project's budget.
What should the project manager do next?
A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.
What should the risk manager do next to find out the correct limit?