Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: exc65

An organization performs an annual strategies and initiatives workshop during which a strengths, weaknesses, opportunities, and threats (SWOT) analysis is being conducted. As part of this process the functional managers identify the opportunities and threats.

What should the risk manager do next?

A.

Add only the threats to the risk register

B.

Utilize different tools to identify the risks

C.

Plan risk responses to the threats

D.

Update the risk register with the identified risks

A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.

What should the risk manager advise the project manager?

A.

Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.

B.

Address these secondary risks as per the risk management plan

C.

Apply a risk acceptance strategy to the new risks as there is no risk response plan.

D.

Update the risk management plan with the new probabily/impact and change the response.

Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.

What should the project manager do next?

A.

Review assumptions and constraints around risks.

B.

Develop the risk response plans for identified risks.

C.

Determine the likelihood and impact of the risks.

D.

Apply an iterative approach to risk identification.

During project development, a risk manager notices that a major update in the country's regulations might be happening in the upcoming months. These changes will affect the materials used in building some of the components of the final product. The project team is unsure if this risk will affect the project negatively or positively.

Which tool should the project team use to determine this?

A.

Sensitivity analysis

B.

Threshold analysis

C.

Reserve analysis

D.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis 

The project manager wants to use an objective method to evaluate the key project risks and develop response plans.

What action should the risk manager propose?

A.

Ask the team to perform an earned value analysis.

B.

Review the lessons learned from other projects.

C.

Ask the team to prepare a Monte Carlo analysis.

D.

Ask the risk expert to perform a PESTLE evaluation.

A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.

After performing a detailed analysis, what should the risk manager do?

A.

Escalate the problem to the project sponsors.

B.

Execute the approved risk response plan.

C.

Negotiate with the supplier to resolve the problem.

D.

Assign a team member to update the issue leg.

A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.

What should the project manager do to avoid this risk?

A.

Record this risk and the clients preference in the risk register.

B.

Ask the sales person to lead the communication with the client

C.

Call the client and advise that online communication is easier and faster.

D.

Meet the client and plan tor critical milestone meetings.

A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.

What type of risk is this?

A.

Residual risk

B.

Primary risk

C.

Secondary risk

D.

Normal risk

A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?

A.

Review and update the project quality management plan.

B.

Conduct a risk assessment process for the critical stage.

C.

Create a more detailed work breakdown structure (WBS).

D.

Add additional time to the delivery plan to cover issues.  

 

During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.

Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)

A.

Compatibility

B.

Urgency

C.

Usability

D.

Proximity

E.

Detectability