Month End Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.

Which response should the risk manager recommend for these risk items?

A.

Mitigate

B.

Accept

C.

Enhance

D.

Exploit

The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.

What should the project manager do?

A.

Implement the risk response strategies into the risk plan.

B.

Inform the sponsor that these risks should be added according to experience.

C.

Add the risks to the risk register and determine a contingency.

D.

Discuss and evaluate the identified risks with the project team.

In the early stages of a manufacturing project, a risk manager has identified a risk with a component provided by an external supplier that might be delayed. The delay may or may not be significant to the project.

What should the risk manager do?

A.

Agree with the external supplier on the timeline.

B.

Register the risk with a medium impact.

C.

Align with stakeholders on the risk threshold.

D.

Engage another supplier with shorter delivery times.

A project team has just completed a project plan, which includes extra days for most of the critical activities to cover any possible issues. Stakeholders want to remove these additional days, because the end date is longer than expected.

What should the risk manager do first?

A.

Remove the activity padding.

B.

Review the risk response plan.

C.

Update the risk contingency plan.

D.

Update the schedule constraints. 

A project manager works on a long-term and high visibility project at an organization that has a low risk appetite towards this project due to its impact on the company's business. The project sponsors follow up weekly with the project manager, who was just informed by one of the risk owners that the exposure from two high-impact risks are hitting the risk thresholds.

What should the project manager do next?

A.

Update the project management plan to add contingency.

B.

Perform an assumptions and constraints analysis.

C.

Complete an assessment and confirm the response with the sponsors.

D.

Implement mitigation measures for those risks.

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team 

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

A.

Ensure that all project stakeholders have a copy of and understand the project's risk management plan.

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register. 

A project to deploy a new technology in field offices across the country has just been initiated. Some stakeholders are not supportive of this project because their teams will potentially be impacted by staff reductions once the technology is implemented.

How should the risk manager address this concern?

A.

Invite these stakeholders to regular meetings to engage them in the definition of project assumptions.

B.

Identify new stakeholders who might replace those involved thus far and are more closely aligned to the project goals.

C.

Review the risk thresholds to potentially accommodate the concerns raised by these stakeholders.

D.

Perform a stakeholder analysis to determine their interests and how they should be taken into account. 

Stakeholder deliverable reviews will start soon and additional work is expected to resolve any issues or required adjustments. Budget overruns during execution have put serious constraints on the remainder of the project's budget.

What should the project manager do next?

A.

Request a budget relief using the management reserve.

B.

Conduct a risk reassessment and reserve analysis.

C.

Review the consequences of potential changes.

D.

Coach stakeholders on risk identification practices.

A risk manager manages risks in a construction project. A stakeholder mentions that if there is less than a 50% chance of rain, construction should continue. Another stakeholder says that if there is less than a 60% chance of rain, construction should continue.

What should the risk manager do next to find out the correct limit?

A.

Review the agreed-upon risk tolerance

B.

Perform a sensitivity analysis of the risk

C.

Find out the stakeholders’ risk appetite

D.

Use industry standard risk thresholds