Month End Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

A project manager for a large product development project assigned a risk manager to perform the risk management. The project sponsor questions why this project requires a risk manager as it is similar to a previous project with a developed risk strategy.

How should the risk manager explain the need for a risk strategy specific to this project?

A.

A risk strategy is a best practice and ensures quality in the project planning.

B.

A project specific risk strategy includes enough information to respond to audits and compliance requirements.

C.

A risk strategy ensures alignment of the organizational structure to the specific project.

D.

A risk strategy aligns individual project risk thresholds with organizational risk appetite. 

An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges.

What should the risk owner do?

A.

Develop an efficient network protection solution quickly to mitigate the risk.

B.

Escalate the case to the risk manager and wait for their instructions.

C.

Conduct an analysis to determine the root cause of the failed response.

D.

Apply a work around to eliminate or mitigate the impact of the threat.

A project manager has finished the project charter for a project and has now moved into the planning phase. In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project's key stakeholders.

What is the first resource the project manager should reference?

A.

Benefits management plan

B.

Enterprise environmental factors (EEFs)

C.

Project charter

D.

Requirements management plan

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

A.

Evaluate any new risks that are introduced due to the change in scope.

B.

Update the risk management plan to reflect the scope change.

C.

Reassess the identified risks that impact the project scope.

D.

Update the risk register to identify, analyze, and plan a response for any new risk.

A risk manager is preparing the risk strategy for a strategic project, which involves stakeholders based in multiple locations. What should the risk manager do at this stage?

A.

Update the risk communications plan to include all stakeholders.

B.

Define the risk processes and tools to be adopted.

C.

Update the risk register to include this stakeholder-related risk.

D.

Refine the risk assumptions and criteria to be used.

A new risk manager has been hired on a project and meets with the project director. The project director supplies the project's risk register and asks the risk manager for an analysis of its effectiveness.

What two actions should the risk manager do next? (Choose two.)

A.

Check to ensure that the risk is supported by a Monte Carlo simul-ation.

B.

Check to ensure that the risks are gathered using Delphi technique.

C.

Check for risk classification and that probability and impact are identified.

D.

Check to ensure that risk origin, triggering event, and ownership is identified.

E.

Check to ensure the risk meeting agenda and supporting documents are distributed.

After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?

A.

Probability of a response triggering a secondary risk

B.

How the response will affect the quality of the components

C.

If the risk response is tied to an activity on the critical path

D.

Verify due dates for the actions have been identified

A risk management team has completed a quantitative analysis, and the individual score in terms of schedule and cost has been identified. The team is consolidating inputs for contingency planning and notices that the available time and funds are not sufficient for all the risks.

What should the risk manager advise the project team?

A.

Ask the project sponsor for more time and funds if needed.

B.

Create a change request if there are additional needs based on the risk responses.

C.

Accept some risks might not be materialized so no extra time and funds will be needed.

D.

Focus on the high-impact risk for contingency planning purposes.

A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the

client's vendor, which apparently has been causing all of the issues.

What should the risk manager do first?

A.

Enhance risk identification.

B.

Review the contingency reserves.

C.

Create a risk response plan.

D.

Review the risk registry.

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

A.

Gather risk information from all parties and compile all submissions into a strength, weaknesses, opportunities, and threats (SWOT) analysis template.

B.

Create a repository for project documents and related artifacts that can be accessed by all parties.

C.

Communicate program metrics to all parties and create a scorecard to measure the effectiveness.

D.

Work with the project manager to develop a start-up workshop and colocate the team if permitted.