A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?

A.

Develop and employ an Ishikawa diagram

B.

Analyze the assumptions and constraints

C.

Perform a review of project documents

D.

Create prompt lists for expert interviews

During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

What action should the project manager take?

A.

Reassess the design for the two pieces.

B.

Escalate the situation and request approval to move forward.

C.

Confirm the results through a second pilot.

D.

Update the assumptions log and assess the risk associated with it.

During the project's lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?

A.

Carry out the agreed risk response action should the risk occur.

B.

Provide a numerical estimate of the overall effect of risk on the objectives.

C.

Track identified risks and maintain the viability of response plans.

D.

Develop the overall risk management strategy for risk integration. 

Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company.

How should the project manager address this concern?

A.

Evaluate the risk with the team and update the issueing

B.

Discuss the concern with the local business owners.

C.

Update the key risks and perform a quantitative risk analysis.

D.

Adjust construction work hours to after business hours.

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.

B.

Assess and modify the project risk management plan in response to the new directive.

C.

Accept project risks since it is already within the enterprise-wide threshold.

D.

Advise that the decision could increase the risk of their portfolio exponentially.

A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.

What should the risk manager do next with the data set?

A.

Perform a probability and impact assessment

B.

Perform Monte Carlo simul-ations

C.

Perform a sensitivity analysis

D.

Perform a risk data quality assessment

A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:

1 = Very Low

2 = Low

3 = Medium

4 = High

5 = Very High

What type of risk analysis is the risk manager performing?

A.

Scenario-based risk analysis

B.

Quantitative risk analysis

C.

Qualitative risk analysis

D.

Monte Carlo analysis 

A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

A.

Highlight this situation to the project manager

B.

Conduct a cost-benefit analysis

C.

Change the risk response strategy

D.

Analyze the situation and meet with the risk owner

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

Which risk identification technique should the risk manager use?

A.

Prompt lists

B.

Interviews

C.

Delphi technique

D.

Nominal group technique