In a large energy company, a PMO was recently established to help organize the numerous projects that are completed every year. Executives have passionate discussions in meetings to select and prioritize projects to enter the portfolio. These discussions cause frequent delays and result in decisions being questioned by some of the executive board members.
What should the PMO professional do to improve this situation?
A PMO professional joins an existing PMO that displays warning signs that the organization's perception of the PMO's value is deteriorating.
Which step should the PMO professional recommend?
A PMO professional is responsible for a team of project managers who lead projects for the business departments. A business manager has mentioned to the PMO professional that one of the project managers assigned to them is very set in their ways, which is causing friction among the project team members.
How should the PMO professional respond to this feedback?
A PMO professional overseeing multiple projects notices that project managers have varying levels of adherence to the project governance processes.
What should the PMO professional do first to ensure consistent governance across projects?
A PMO professional is supporting project managers who are implementing a new organization-wide user support system. The PMO professional needs to help the project managers enable change management effectively within the organization. In recent years, similar initiatives have failed because employees were too focused on the negative effects of change. The changes were enforced by sending memos to employees who did not adopt the new processes. The instructions to adopt the new processes did not offer any flexibility.
Which approach should the PMO professional recommend to enable change this time?
A new PMO has been started in a medium-sized retail company that has several concurrently running strategic projects. A team of project managers with no PMO experience has been assigned to the new PMO.
Which two actions should the PMO professional take to help the project managers prepare for their roles? (Choose 2)
In recent months, a company was contracted to deliver several projects requiring specialist technical resources. Several clients have begun to complain about the limited availability of the specialist technical resources, which will impact their project timelines.
What should the PMO professional do to help solve the problem?
An enterprise PMO (EPMO) is working with different countries to staff project managers across the organization. Customers are providing feedback stating that the staffing is taking more time than expected when compared to the deadlines agreed upon with the customer.
Which two key performance indicators (KPIs) should the PMO professional monitor for this PMO service? (Choose 2)
A PMO was recently established to support the organization's new strategy following a global restructuring process.
Which two actions should the PMO leader take to effectively identify the expectations of PMO customers? (Choose 2)
A PMO professional has been hired to establish a PMO within an organization. However, upon starting, they discovered that a PMO had already been implemented a few years ago but was shut down due to its failure to generate perceived value at the executive level.
What approach should the PMO professional take when beginning this task?