An executive notices a Kanban board in a highly visible location and expresses concerns to the project manager that too many people will see it. What should the project manager do?

A.

Cover up the Kanban board every time the project team is not actively updating it.

B.

Demonstrate how the Kanban board is necessary for assigning proper ownership for the work that has been done.

C.

Explain that the Kanban board enables the team to complete the work and increases transparency on work that is not done.

D.

Remove the Kanban board immediately and place it in a location where it is not visible.

The Scrum Master for a large project must provide an estimate of what can be delivered in six months.

What should the Scrum Master do?

A.

Commit to a specific feature set for delivery

B.

Explain that a commitment will be provided after planning

C.

Have the team estimate in story points to commit to a specific set of features

D.

Use the team's historical velocity to calculate a range of features that can be delivered

What is a benefit of this meeting?

A.

The team will learn how its contribution will create product value

B.

It will enable team acceptance of client priorities

C.

It will enable the team to see the entire project in one glance

D.

It will enable the team to ask any questions to the customer upfront

The product owner is working on an application that will be built in a data lake leveraging a data

integration and transformation software application. With a budget of US$17,000 remaining, how should the product owner allocate the money? (Refer to Exhibit A)

A.

Prioritize the features based on customer feedback and potential value.

B.

Focus on the reporting module since it has the highest estimated cost.

C.

Complete the data repository and reprioritize based on the remaininq budqet.

D.

Proceed with all of the planned features to ensure completeness.

During sprints, the development team members are frequently invited to various meetings to provide technical opinions, consuming the team's working time and causing compliance issues. Which action should the scrum master take to address this situation?

A.

Request additional resources to prevent compliance issues while still fostering a collaborative workplace.

B.

Escalate the concern to the product owner and request that they prioritize the development work.

C.

Designate a single team member to attend the meetings and establish a capacity buffer for each sprint.

D.

Reject all external meetings for the development team so they can fully focus on their sprint tasks.

How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?

A.

Collect stakeholder requirements

B.

Conduct an iteration planning meeting

C.

Communicate product backlog items to the stakeholders

D.

Facilitate a product development roadmap workshop

Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this.

What should the agile practitioner do?

A.

Jointly meet with the team and product owner to discuss options and determine the end date

B.

Announce that the team has exceeded the predicted velocity and that the end date will be earlier than planned

C.

Ask the product owner to include additional features in the product backlog, then replan subsequent iterations

D.

Ask the team to decrease velocity to meet contractual obligations and document this decision

While working on a sprint for a software development project, the team is unsure of how the feature should be designed. The project sponsor recommends developing a prototype of the user interface to discover more about this feature.

Why is the project sponsor making this suggestion?

A.

The information gathered will help the team improve the allocation of resources in developing the most important features.

B.

The project sponsor believes that the agile team is not adding in the most important features during this sprint.

C.

The users can help the team understand if the feature adds value, avoiding the risk of building the wrong product.

D.

The users will start using the software sooner, and the team can start working on the next iteration.

A product owner has various items in a product backlog and does not know how to prioritize them. How should the agile practitioner coach the product owner?

A.

Sort the stories in the backlog by descending story points and release the stories at the top of the list equal to the team's velocity.

B.

Prioritize the most valuable product features in the backlog first.

C.

Determine the features with the highest risk and release those first.

D.

Determine which features comprise the smallest feature set that could be successful in the market and establish viability of the product.

While reviewing the sprint burndown during a stand-up, the Scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.

What should the Scrum team do?

A.

For upcoming sprints, have QA team members ensure that their respective skill sets are considered when accepting stories

B.

Have QA team members with the appropriate skill sets spend extra time to help the team succeed

C.

Ensure that QA team members who lack the appropriate skill sets sign up for training within the next few weeks

D.

Ask QA team members experienced with the new automation framework to cross-train the other QA members