One of the overseas stakeholders on an agile project has not been actively involved in the project's development. What would be the first step to reengage the stakeholder?

A.

Increase the frequency of emails and/or try to call the stakeholder.

B.

Remind the stakeholder of their obligation to engage in the project.

C.

Talk to the stakeholder's superior so they can offer coaching and guidance on project involvement.

D.

Set up a meeting with the stakeholder to modify the working agreement and ensure future engagement.

Following approval of a business case, a company will introduce a new mobile app for customers to place orders. Time to market is a key concern. The product has entered into the 3rd iteration, but the team is concerned because they feel the technical designs do not meet the agreed-on definition of done (DoD). An agile coach has been hired to help validate product delivery against business requirements.

What should the agile coach do?

A.

Incorporate quality assurance in the planning stage of product development.

B.

Schedule a dedicated meeting with the product owner to tackle this roadblock.

C.

Conduct a brainstorming exercise to get to the root of the issue and devise action plans.

D.

Conduct a retrospective meeting at the end of the current iteration to identity necessary improvements.

An organization is using a predictive approach to managing projects. The executives like to see more deliverables in a short time and require that the milestones be achieved on time.

What value can the organization gain by moving to an iterative approach?

A.

New tools that deliver iterative and incremental work

B.

A more predictable delivery schedule and better quality

C.

Higher levels of activity-based planning and user histories

D.

Increased focus on the value and benefits delivered

A product owner is responsible for a new product. The internal customer questions using an agile approach because they need a product that works without any bugs or missing features once it is launched.

What should the product owner do?

A.

Plan regular retrospectives with the development team to continuously improve processes to eliminate any potential issues with the product.

B.

Apply an agile approach to write the specifications in an incremental way and develop the product once the final specifications are agreed upon.

C.

Set up test-driven development to focus on customer requirements and eliminate issues in the software as testing progresses,

D.

Ask the customer to provide additional representatives to help test and evaluate the product for early and frequent feedback.

Which of the following allows DevOps to enable and sustain a fast workflow from development into operations?

A.

A mindset shift to establish controls over all development and operations processes.

B.

Planned incremental iterations and a focus on people over processes.

C.

A culture of collaboration, tools, and processes to support continuous delivery.

D.

New tools that enable teams to continuously build, test, and integrate.

A Scrum team is visualizing the blockers that arise when they work on their activities on the kanban board. The team decided to analyze why the blockers occur so they can take action to minimize their occurrence and reduce lead times.

Which practices should the team use?

A.

The most important principle in Scrum is reducing work in process (WIP). The lower the number of items, the lower the risk of items getting blocked. Based on the team’s capacity, they should set the lowest WIP limits possible.

B.

The team should look at all the blockers, determine the reason behind them, group them, and determine if there is a pattern. They should then determine what and how they can make relevant changes.

C.

The team should discuss the issue with their scrum master because it is their responsibility to remove impediments, such as blockers, in cooperation with other teams.

D.

Blockers are a result of bottlenecks. The team should ask for more resources to prevent bottlenecks from arising and reduce the risk of long lead times.

An executive sponsor asks a team when a specific feature will be ready for release. A team member states the feature will be ready by the end of release 3 because it is not a core feature. The team member directs the sponsor to an information radiator, where the sponsor sees several notes grouped by release numbers and posted on the wall.

What is the sponsor looking at?

A.

Project management plan

B.

Product backlog

C.

Gantt chart

D.

Product roadmap

A servant leader is leading a high-visibility project to deliver a new product. The servant leader has been able to build a cross-functional team and create a team space where the team is collocated. The servant leader started receiving frequent visits from a company director, who continually asks a specific team member questions about project progress. The conversations are distracting the team from their goal.

What should the servant leader do?

A.

Coach the company director on agile approaches and good practices.

B.

Ask the product owner to speak to the director because their visits are delaying the project.

C.

Ask the director and team member to leave the room so they can have a private conversation.

D.

Coach the team member on how to report progress to directors and executives.

A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.

What should the Scrum Master do?

A.

Tell the technical lead to do the testing

B.

Facilitate an open and focused team discussion that reinforces team agreements

C.

Ask the team manager to advise the technical lead that all tasks are important

D.

Encourage the team to take ownership of the delivery

Why should an agile coach model agile principles and behaviors, become self-aware, and be present?

A.

To better listen, serve, and help the team grow their strengths individually and as a team

B.

To convince people what they need to do

C.

To help better disguise the command and control approach

D.

To understand team dynamics and develop a high performing team