A.

Document the problem, escalate to the project manager, and develop a solution for the team

B.

Add the problem to the backlog and assign resolution to a future iteration

C.

Instruct the team to try to solve the problem within the team

D.

Perform root cause analysis and report the problem to the product owner

An organization wants to execute a corporate website redesign project using Scrum. There is an experienced pool of agile team members from a previous project, as well as a pool of available internal team members with some Scrum background.

What should be considered when selecting the team?

A.

Review any reports of conflict between each of the team members over the last two years, and select only those with a track record of working well together.

B.

Ensure there is a balanced mix of people who are experts and members with broad experience based on the work to be performed and determine training needs.

C.

Ensure that none of the team members are geographically dispersed so that all team members can be colocated.

D.

Review each team member ' s contributions to the velocity of their previous projects and select the highest performers.

What should the agile team lead do?

A.

Create a new team to deliver the dependencies, and bring team B under performance management.

B.

Conduct a vision-sharing session with the teams to communicate the project ' s overall goals.

C.

Swap team members from both teams so that deliveries are better supported.

D.

Discuss negotiating the delivery timelines with team A.

In a project, the customer asks for a requirement that clearly deviates from the contract terms.

How should the contractor react?

A.

Proceed with the work only after the contract is amended.

B.

Discuss the value of the change for the project with the customer.

C.

Evaluate effort and impact and ask for steering committee and shareholder approval.

D.

Stick with the contract terms and agree to review the requirement if time allows.

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns " To do, " " In progress, " " Ready to be tested, " " Test in progress, " and " Done. " Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of " Ready to be tested " work items has been building up.

What should the team do to improve its speed of delivery?

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns " To do, " " In progress, " " Ready to be tested, " " Test in progress, " and " Done. " Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of " Ready to be tested " work items has been building up.

What should the team do to improve its speed of delivery?

A.

Analyze the process efficiency, cycle time, and lead time of the entire process.

B.

Estimate in story points and pull in new work per the team ' s capacity

C.

Add limits to all columns and only pull work in when the queue is not full.

D.

Create a cumulative flow diagram and start looking for bottlenecks.

During planning, a project team and sponsor created a visual representation of the high-level specifications of the features and user stories to be implemented in a product. Consensus was achieved on this high-level depiction of the product characteristics, but the sponsor is having difficulty understanding what to develop and when.

How should the project manager explain this to the customer and save time in the meeting?

A.

Team performance and velocity can be determined only after the project has started

B.

Point out the Walking Skeleton and highlight the basic features that provide value.

C.

Create a kanban board for visualizing the work in process (WIP) and future development.

D.

High-level release planning is part of iteration 0 and works as a proof of concept

The first project vision statement meeting for a newly formed team did not achieve its outcome. Lack of participation combined with conflicting views of those who participated led to disagreement on how to proceed.

How can the team improve their collaboration?

A.

Set clear expectations and allow everyone to contribute.

B.

Prepare the project vision statement and then present it to the team.

C.

Ask senior management to address the situation.

D.

Seek assistance from the scrum master to mediate the conflict.

What should the Scrum Master mention at the next retrospective?

A.

Solutions to project problems that were built into the last sprint

B.

Problems that arose

C.

Solutions that saved the organization the most time and money

D.

Problems that were solved

What should the product owner do?

A.

Accept responsibility for the product ' s delay.

B.

Ensure that the project sponsor ' s priorities are in the product backlog.

C.

Negotiate with the project sponsor for increased funding.

D.

Empower the project sponsor to manage the product backlog.

An agile project was underway for two months and delivered the expected value to the stakeholders. However, during a sprint review, a team member complained that the product owner constantly changes requirements and the member feels that this is blocking the team’s performance.

How can the scrum master handle this situation?

A.

Work with the product owner to include fewer features in the next sprint planning.

B.

Hire more team members to elevate the team ' s velocity to increase performance.

C.

Tell the team members that changes are natural and welcome if the project is delivering value.

D.

Schedule more meetings with the team and the product owner to refine the backlog constantly.