Weekend Sale - Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: sntaclus

A new team member asks what changes could accelerate a change to the project plan What should be the proper response?

A.

Competitors joined forces with the team

B.

The customer changed requirements

C.

Project team members obtained additional certifications

D.

Technology which did not interfere with the final product

An agile learn has only one database administrator with the necessary knowledge of database-related tasks. The project manager identifies the risk that if this person leaves, team velocity will significantly decrease.

What should the agile coach do?

A.

Start the hiring process for a new, equally skilled database administrator as a replacement.

B.

Move this database administrator to another team so that team members learn database-related tasks.

C.

Add another database administrator to balance the workload and aid with knowledge retention.

D.

Obtain agreement from the team that, on upcoming sprints, the database administrator will act only in an advisory capacity.

One of the senior stakeholders on a project did not want to be engaged on a daily basis. During the iteration, the team encounters complexities but are convinced these issues can be resolved in time for the demo.

What should the agile practitioner do?

A.

Be transparent with all the stakeholders and make them aware of the issues encountered and the current project's status.

B.

Ensure the agile leader documents a risk in the risk register and communicates the risk to the project sponsor.

C.

Support the team's decision, and since the team is confident about being able to resolve the issues in time, do not raise the issues as risks with the stakeholders.

D.

Ask the product owner to make a decision as to whether or not all the stakeholders should be kept informed about the current project's status.

There is a database feature requiring three members of a seven person team. A meeting is scheduled at the beginning of the sprint to go over technical needs to complete the story. Who should the Scrum Master invite to the meeting?

A.

The core team and the customer

B.

The product owner and key stakeholders

C.

The customer and the sponsor

D.

The core team and the product owner